HomeMy WebLinkAboutDAQ-2024-0112171 DAQC-1056-24 Site ID 10423 (B2) MEMORANDUM TO: FILE – INTERSTATE BRICK COMPANY THROUGH: Harold Burge, Major Source Compliance Section Manager FROM: Robert Haynes, Environmental Scientist DATE: October 16, 2024 SUBJECT: Title V Annual Compliance Certification Receipt/Review, FRS ID # UT0000004903500200 REPORT RECEIVED/DUE DATE: October 9, 2024 / October 10, 2024 TITLE V PERMIT: #3500200002 DATE OF LAST PERMIT REVISION: February 19, 2024 CERTIFICATION PERIOD: September 23, 2023 – September 23, 2024 FACILITY REPORT COMPLIANCE STATUS: Intermittent REPORT EVALUATION: • Was report submitted on time? Yes • Did report identify status of compliance for each condition? Yes • Was compliance status marked as continuous/intermittent for each condition? Yes • Did report identify method used to determine compliance with each condition? Yes • Was report signed and properly certified by responsible official? Yes • Were exceedances/excursions reported? Yes • Were deviations reported? Yes II.B.3.b Kiln 4 excess emissions, scrubber down for maintenance March 20, 2024. Deviation reported March 22, 2024, NFA. CURRENT RECOMMENDATION: The report appears to meet the requirements of the Title V operating permit condition I.L. ATTACHMENTS: Annual Compliance Certification Report. 8 0 . () INTERSTATE"BRIcK TO: FROM: DATE: RE: r*tnr P,ABCO' Executive Secretary Utah Air Quality Board P.O. Box 144820 salt Lake city, uT 84714-4820 lnterstate Brick Company 9780 South 5200 West West Jordan, UT 84081-5625 Septernber 23,2024 Annual Compllance Certlflcation for Permlt #3500200002 -6 DEPARTMENT OF ENVIIIONMENTAL OUAIITY, 1)an d de-lt t)orti ocT - 9 n24 DIVIS]ON OF AIR OUALTTY Under Operating Permit Provision I.L and Utah Administrative Code (UAC) R307415-6c(5), the following compliance certification is submified. This certification covers the period of operations from September 23, 2023, to September 23, 2024: Term Description of permit provision Method used to determine compliance status Was compliance during the permit period continuous, intermittent or undetermined Other facts relevant to compliance status, including any and all deviations 1A Federal Enforcement Continuous 1B Permitted Activity(ies)Continuous 1.C.7 Duty to Comply with all conditions of the permlt Continuous t.c,2 Not an excuse ln permit action to say halting or reducing permitted activity would have been necessary to maintain compliance. Continuous t.c.3 The source shallfurnish any information that may be requested by the Executive Secretary. Continuous 1.C.4 Continuous 1.D.1 Fixed term of permit and expiration Continuous 1.D.2 for renewal Continuous submitted 3124t2023 1.D.3 tion for renewal after due date Continuous 7,D,4 Permit expiration and right to operate Continuous Parle 1lB REVIEWEDInitials:Date: Oct 10, 2024Compliance Status: Non-compliantFile #: 10423 (B2)Comment: Revise- For II.B.3.b is the Kiln 4 scrubber required maintenance, or is it a breakdown? 1,,E Timely application renewal shie ld Continuous L,F lf parts of permit found invalid the rest remains valid Continuous r.G.1 The source shall pay an annual emissions fee consistent with R307-415-9 (R307- 41s-6a(7)). Continuous t.G.2 "fee shall be due on October 1 ofeach calendar year or45 days after the source receives notice of the amount of the fee" 2022Fee was due on October 1, 2023. Continuous 2023 Emissions Fee was paid and delivsred on 9/30/2024 1.H Permit conveys on property rights Continuous 1.1 Continuous 1.J.1.a Continuous 1.J.1,b Continuous 7.t.7.c Continuous 1.J.1.d Continuous \).2 Continuous 1.K Continuous 1.1.1 Continuous LL.1.a The permittee shallsubmit to the Director an annual compliance certificatio n, ce rtif,/ing co m plia nce with the terms and conditions contained in this permit...., Continuous Annual Cornpliance Certifi cation for Interstate Brick was submitted on October 2nd 2024 1.1.1.b Continuous 1.1.1.c Continuous 1.1.1.d Continuous t.1.2 The permittee shallalso send all compliance certifications to EPA, Region vill. Environmental Protectlon Agency, Region Vlll, Office of Enforcement, Compliance and Environmental Justice (mail code SENF) 1595 Wynkoop Street, Denver, CO 80202-7t29 Continuous 1.M.1. a Continuous 1.M.1. b Continuous 1..M.2. a Continuous 1..M.2. b Continuous 1.M.2,c Continuous 1.M.2, d Continuous t']age.2l8 1.N.1 Continuous 1.N.2.a Continuous 1.N.2.b Continuous 1.N.2.c Continuous 1. N.2,d Continuous 1.N.3 Continuous 1.N.4 Continuous 1.O Continuous 1.P Continuous 1.Q Continuous 1.R Continuous l.S.1.a The records of all required monitoring data and support informatlon shallbe retained by the permittee for a period of at least five years from the date ofthe monitoring sam ple, measurement, report, or a pplication. Records as specified in the permit Continuous 1.S.1.b, L Continuous 1.S.1.b. 2 Continuous 1.S.1,b. 3 Continuous 1,S.1.b, 4 Continuous 1.S.1.b. 5 Continuous 1.S.1.b. 6 Continuous 1.S.1.c Continuous l.S.2,a Did the permittee submit monitoring reports every six rnonths, or more frequently if specified in Section ll, and were all instances of deviation from permit requirements clearly identified in the monitorins renorts? Continuous The Six Month Monitoring Reports were submitted on March 22nd, 2024, and October 2nd, 2024. 1.S.2.b Continuous r.S.2.c The Director shall be notified promptly of any deviations from permit requirements. Deviation Reports are due within t4 days of occurrence Continuous Deviation Report for Excess Ernissions on March 2oth,2}24 was submitted on March 22"d.2024. 1.S,3.a Continuous r..s.3.b Continuous 1.T.1.a Continuous 1.T.1.b Continuous 1.T.1,c Continuous 1.T.1.d Continuous 1.T.2 Continuous 1.T.3 Continuous t.u Did the permittee submit the inventory required by R307-1.50 in accordance with the requirements of that rule? (This covers R307-150, 155 and 158 if listed in permit) ll.B,x Each provision in Section ll.B, including each monitoring, record keeplne, and reporting reouirement. 2023 Emissions Inventory was due April i5, 2024, Continuous Inventory was submitted to UDAQ on April5, 2024. 1.V Continuous ll.B.L.a "Plant wide production/consumption shall not exceed: 1) 2,880 tons raw clay consumption per rolling 24-hr perlod. 21393,236 tons of brick produced in Line #3 and Line fl4 combined per rolllng L2- month period. 31512,582 tons of brick produced plant- wide per rolling 12 month period" Clay Preparation production report and Mass Balance plan. Continuous il,8.1.b "Visible emissions from the following shall not exceed 1) All screens - 10% opacity (no screens are open to the outside ai4 2l All conveyor transfer points - 10% opacity. 3) All baghouses- LO% opacity 4) All buildings enclosing crushers - 10% opacity 5) All crushers - 15% opacity All other points onsite - 2A% opacity," Fugitive Dust Control Plan. Certified Opacity Readers. Continuous ll.B.1.c The Moisture content of clay was maintained at an average of no less than 4.0Yoby weight. A hand-held moisture meter was used to veriff the moisture content ofthe clays. Continuous ll.B.1.c. 2 The moisture meter was calibrated biannually according to the manufacturer as per a maintenance contract. Service records and invoices from vendor. Continuous P;rgt:418 il.8.1.d Plant-wide emissions of VOCs from the brick manufacturlng plant and associated operations shall not exceed 14,87 tons oer rolline 12-month period for VOCs. Rolling l2- rnonth total VOC log. Continuous ll.B.1.e Plant-wide emissions of HAPs from the brick manufacturing plant and associated operations shall not exceed: 7.2 tons per rolling l2-month period for HCL, 6.7 tons per rolling 12-month period for HF, 7,0 tons per rolling l2-month period for miscellaneous HAPs, and 18.2 tons per rolling 12-month period for all HAPs combined, Mass balance plan and stack testing. Continuous il.8.1.f Fugitive Dust. (1)the permittee shall submit and abide by a fugitive dust control plan.." (Origin: Permit #3500200001 Opacity caused by fugitive dust shall not exceed 10% at the property boundary and 20% on site. Vehicle speeds on haul roads shall be limited to 15 rnph within the plant and in vicinity of the crusher, and 25 mph between the plant and the paved highway. Speed limit signs shall be posted at the entrance to the active haul road area," Fugitive Dust control plan log(s) (water truck log, wind speed log), speed limit signs. Continuous ll.B.2.a All exhaust air from l(iln #3 shall be routed through the wet scrubber before being vented to the atmosphere. Scrubber operating log Continuous il.8.2.b Emissions from the Kiln #3 Scrubber Tunnel did not exceed Total PM2.5*.....8.66 lb/hr (l-hr average). PM10....8.56 lblhr (l-hr average) NOx....5.07 lb/hr (1-hr average) SO2,...8.09 lb/hr (1-hr average) Total Fluorides... L.77 lb/hr (1-hr average) *lncluding front half and back half condensables as per authority granted under R307-401- 8(1)(a)tBACTl and condition originated in Permit #3500200001. Mass balance log and Annual Stack testing Continuous il.8.2.b ,t Stack testing shall be performed... PM10 and PM2.5,..every three calendar yea rs NOx....every three calendar years SO2...every ca lendar year Total Fluorides....every five years based on the date ofthe last test. Stack Testing Reports Continuous Stack Testing Report Subrnitted September 5th 2024. Pagr:518 ll.B.2.c Emissions from the Line #3 Baghouse shall not exceed (1)Total PM2.5,..0.18 lblhr and 0.016 gralns/dscf (1-hr average); and (2) PM10....0.18 lb/hr and 0.016 grains/dscf (1-hr ave rage). Stack testing perfonned every three years, Continuous ll.B.2.c. 1 Stack testing shall be performed... Every 3 calendar years Stack test results Continuous il.8.2.d The Line #3 tunnel kiln shall not exceed 17.92 tons of product per hour. Mass balance production records Continuous ll.B.2.e Clay Prep for Line #3 shall not exceed 6,240 hours of operation per rolling 12- month period (does not include l(iln #3 operatine hours). Mass balance ptoduction records Continuous il.B.2.f Naturalgas shall be used in Klln #3 with propane as a backup, Fuel usage records. Continuous ll.B.2.g A rninimum pressure drop for Line #3 scrubber shall be 0.1. inches w,g. Scrubber operatins los Continuous il.8.2.h The Line 3 scrubber fluid shall be maintained between 5-9 pH Scrubber operatins los Continuous il.8.2.i The minimum flow rate of the Line #3 scrubber was 200 gallons per minute Scrubber operatins loe Continuous il.8.2,i, L Flowmeter for continuous measurement of flow rate shall be installed, calibrated, ma intained, and operated. Scrubber operating log and annual calibration record. Continuous ll.B.3.a All exhaust air from Kiln #4 process streams shall be routed through the wet scrubber before being vented off to the atmosphere Scrubber operating log Continuous il.8.3.b Emissions from the Kiln #4 Scrubber Tunnel shall not exceed Total PM2.5*.....3.97 lblhr (1-hr average). PM10..,.3.97 lblhr (1-hr average) NOx....10.52 lb/hr (1-hr average) SO2....5.87 lb/hr (1-hr average) Total Fluorides... 3.25 lb/hr (L-hr average) Mass balance log and Annual Stack testing Intern:ittent Ifiln 4 Scrubber Excess Emissions due to required maintenance to keep the scrubber in operation on March 20il',2024 from Tamto 4pm. il,8.3.b .1 Stack testing shall be performed... PML0 and PM2.5...every three calendar years NOx,,..every three calendar years SO2...every calendar yea r Total Fluorides.,..every five years based on the date of the last test. Stack testing records Continuous 618 ll.8.3.c Emissions from the Llne #4 baghouse shall not exceed... Total PM2.5 ,..0,34 lb/hr and 0.0L6 grains/dscf (1-hr average), PM10..0.34 lb/hr (dry filterable particulate only), and 0.016 grains/dscf (1-hr, average). Stack testing Continuous ll.B.3.c. L Stack testing shall be performed... Every 3 calendar years Stack test records Continuous il.8.3.d The Line 4 tunnel kiln production shall not exceed 26.97 tons of product per hour averaged over a rolling Z4-hour period. Mass balance log Continuous ll.B.3.e. 7 Clay Prep for Line #4 shall not exceed 6,240 hours of operation per rolling 12- month perlod (does not include l(iln #3 operatins hours). Mass balance production records Continuous il.8.3.f Natural gas shall be used in Kiln #4 with propane as a backup. Fuel usage records. Continuous ll.B.3.g A minimum pressure drop for Line #4 scrubber shall be 2.0 inches w.g. Scrubber ooeratins lop Continuous il.8.3.h The Line 4 scrubber fluid shall be maintained between 5-9 pH Scrubber ooeratins los Continuous il.8.3.i The minimum flow rate of the Line #4 scrubber was 600 gallons per minute Scrubber ooeratins los Continuous il.8.3.i. 1 Flowmeter for continuous measurement of flow rate shall be installed, calibrated, maintained, and operated. Scrubber operating 1og and annual calibration record. Continuous il.B.4 All exhaust from the primary crusher building shall be routed through the Primary Crusher Baghouse before being vented to atmosphere. Baghouse operating log Continuous il.8.4,b Emissions from the Primary Crusher Baghouse Vent shall not exceed.... Total PM2.5 and PM10: 0.56 lblhr and 0.010 erains/dscf {1-hr averape} Stack testing results Continuous lt.B.4.b ,7 Stack testing shall be performed.,, Every 3 calendar years Stack test reoorts Continuous ll.B.4.c The minimum pressure drop for the Primary Crusher Baghouse shall be: (A) 2,0 inches/w.g. when using polyester felt; or (B) 0.4 in inches/w.g. when using PTFE membrane. Bag house operating log Continuous 7lB ll.B.5.a Gasoline Storage Tank - 40 CFR 63 Subpart CCCCCC For each gasoline storage tank with a throughput less than 1.0,000 gallons per month the permittee allow gasoline to be handled in a mannerthat would not result in vapor releases to the atmosphere for extended periods of time.......... Gasoline Tanks inspected monthly. Continuous il.B.6 Degreasers: The permittee shall ensure that the following conditions are met: (1) All solvent degreasers are equipped with a cover which remains closed except during actual parts cleanlng. The cover is designed so it can easily be operated with one hand. (2) internal draining racks are installed and are used. Parts were enclosed under cover whlle draining. (3) waste or used solvent shall be stored in covered containers. (4) solvent cleaning equipment shall be maintained in good operatin8 condition and there were no leaks. (5) procedures for operation are posted. (6) The solvent volatility is less than 4.3 kPa (7) solvent spray strearn pressure is such that it does not cause excessive solashine. Degreasers are inspected monthly. Continuous reasonable inquiry, I certifo that the statements and information in Name and Title of cial for the Source ln accordance with Operating Permit provision l.K and UAC R307-415-5d and based on information and belief formed after this document are true, accurate, and complete. l',rrt,8l8 REVIEWEDInitials:Date: Oct 10, 2024Compliance Status: Non-compliantFile #: 10423 (B2)Comment: Revise- is the Kiln 4 scrubber requiredmaintenance, or is it a breakdown?