SUBJECT: Proposed Work Plan and Price for Groundwater Sampling
Former Wile Oil
8370 South State Street
Midvale, Utah
Facility ID #4001272
UST Release Site LDA
Work Assignment LDA-16
UDEQ Technical Services Contract #216364
Dear Mr. Tao:
Please find attached a copy of the Proposed Work Plan and Price to conduct groundwater
sampling and reporting at the above referenced site.
Our services consist of professional opinions and recommendations made in accordance with
generally accepted geotechnical and environmental engineering principles and practices. This
warranty is in lieu of all other warranties either expressed or implied.
Should you have any questions, please do not hesitate to call us at 801-971-1064.
Sincerely,
Atlas Technical Consultants LLC
Jim Coletta, P.G.
Branch Manager
Utah Certified UST Consultant
Former Wiles Oil, LDA-16
Atlas
PROPOSED WORK PLAN
GROUNDWATER SAMPLING AND REPORTING
FORMER WILES OIL
8370 SOUTH STATE STREET
MIDVALE, UTAH
FACILITY ID #4001272
UST RELEASE SITE LDA
WORK ASSIGNMENT LDA-16
UDEQ TECHNICAL SERVICES CONTRACT #216364
September 17, 2024
Prepared for:
Mr. Hong Lee Tao
State of Utah
Department of Environmental Quality
Division of Environmental Response and Remediation
195 North 1950 West
Salt Lake City, Utah 84114
Prepared by:
Atlas Technical Consultants
358 South 700 East, B518
Salt Lake City, Utah 84102
Former Wiles Oil, LDA-16
Atlas
TABLE OF CONTENTS
Letter of Transmittal
Title Page
Table of Contents
1. INTRODUCTION ................................................................................................................................... 1
2. SCOPE OF SERVICES ........................................................................................................................ 1
2.1 Task 1 – Groundwater Sampling and Reporting .............................................................................. 1
3. DELIVERABLES ................................................................................................................................... 2
4. PROPOSED PROJECT SCHEDULE ................................................................................................... 2
5. PERSONNEL ........................................................................................................................................ 2
6. SUBCONTRACTORS ........................................................................................................................... 2
7. EXCEPTIONS, ANTICIPATED PROBLEMS, OR SPECIAL REQUIREMENTS .................................. 2
8. CONFLICT OF INTEREST ................................................................................................................... 3
9. COST ESTIMATE ................................................................................................................................. 3
ATTACHMENTS
Figure 1 – Site Map
Table 1 – Proposed Project Schedule
Table 2 – Cost Estimate
Appendix A – Contract Required Paperwork
Former Wiles Oil, LDA-16
Atlas
1
PROPOSED WORK PLAN
GROUNDWATER SAMPLIG AND REPORTING
FORMER WILES OIL
8370 SOUTH STATE STREET
MIDVALE, UTAH
FACILITY ID #4001272
UST RELEASE SITE LDR
WORK ASSIGNMENT LDR-16
UDEQ TECHNICAL SERVICES CONTRACT #216364
1. INTRODUCTION
Under Work Assignments LDA-16, the Utah Department of Environmental Quality, Division of Environmental Response and Remediation (UDEQ) requested Atlas Technical Consultants prepare a work plan and price to conduct groundwater sampling and reporting at the above referenced site. Please refer to the work plan attachments for a Site Map depicting the well locations. This following proposed Work Plan presents a brief description of the tasks to be performed including a schedule (Table 1) for completing the activities described herein and a detailed cost breakdown (Table 2).
2. SCOPE OF SERVICES
The objective of this proposed Work Plan is to conduct one round of groundwater sampling and to prepare a summary report for documenting the sampling event. Each task is described in greater detail in the following sections. Utah Certified Soil and Groundwater Samplers would perform the soil and groundwater sampling activities described below under the direction of a Utah Certified UST Consultant.
2.1 Task 1 – Groundwater Sampling and Reporting
The procedures described in the following paragraphs will be used to sample monitoring wells MW -1, MW -2, MW -3, MW-4, MW -5, MW -7, MW -8, MW -9, MW -11, MW -12, MW -13, MW-14, MW -15, and MW -16. Initially, the groundwater depth and free product thickness (if present) will be measured at each well location. These measurements will be taken with a down-hole water level/free product interface probe. The water level/free product probe will be decontaminated between each well with an Alconox detergent wash and tap water rinse. The wells will then be developed/purged of a minimum of three well casing volumes or until dry using new disposable bailers. If free product is measured in a well, that well will not be sampled. The purge and decontamination water will be poured on the ground surface allowed to evaporate. The groundwater samples will be analyzed for MBTEXN, TPH-GRO, and TPH-DRO using USEPA Methods 8260B and 8015B, respectively. In addition, the off-site well registering the highest TPH concentration above the DERR ISL, and the on-site well registering the highest concentration above the DERR Tier I Screening Level will be analyzed for TPH Fractionation. A trip blank and a field duplicate will also be included for analysis.
Upon completion of the sampling event a summary report will be prepared. The report will
include:
• Data tables for newly obtained analytic data and historical data;
• Measurements for depth to water and free product;
• Laboratory reports and chain of custody forms;
Former Wiles Oil, LDA-16
Atlas
2
• Groundwater gradient map;
• QA/QC for sample results; and
• Field observations including standard operating procedures for well purging and
sampling.
One copy of the report will be provided to the DERR.
3. DELIVERABLES
The anticipated deliverables for the work identified in this proposed Work Plan include the
following:
• Groundwater Monitoring Report; and
• Invoices, backup documentation, and contract required forms.
4. PROPOSED PROJECT SCHEDULE
The proposed schedule for the activities described herein is presented in Table 1.
5. PERSONNEL
The key personnel for the proposed activities are as follows:
• Atlas Senior Project Manager: Jim Coletta (P101)
• Atlas Professional Geologist: Jim Coletta (P102)
• Atlas Project Manager: Jim Coletta (P103)
• Atlas Senior Technician: Olaf Questereit (P105)
6. SUBCONTRACTORS
The following subcontractors would be used in the performance of the above scope of work:
• Chemtech Ford - would provide state certified laboratory services.
Based on information provided by each selected subcontractor, the following contract
requirements have been met:
• The selected subcontractor is not currently debarred pursuant to Utah Code Section 63-56-
48 or EPA’s most recent “Master List of Debarred or Suspended Facilities”;
• The selected subcontractor has no apparent conflict of interest; and
• The selected subcontractor is not a minority or women owned business enterprises.
7. EXCEPTIONS, ANTICIPATED PROBLEMS, OR SPECIAL REQUIREMENTS
At this time, no exceptions or special requirements to the proposed Work Plan are anticipated
with the exception of the grant of access agreement. In the event exceptions or special
conditions arise, Atlas would amend this proposed Work Plan or submit a new Work Plan for
UDEQ approval before initiating any work outside the scope of services described herein.
Former Wiles Oil, LDA-16
Atlas
3
8. CONFLICT OF INTEREST
Based on Atlas’s present knowledge of the site location and conditions, no personal or
corporate conflict of interest has been identified for the performance of the scope of services
described in this proposed Work Plan. Atlas would contact UDEQ immediately if a potential
conflict of interest is identified during the performance of this proposed Work Plan.
9. COST ESTIMATE
The estimated cost for implementation of this proposed Work Plan is presented in Table 2. The
estimated budget would require adjustment if the scope of services identified herein is modified
or any assumptions are incorrect. Exhibit 3 from the UDEQ Technical Services contract is
presented in Appendix A.
FIGURE #:
1
GASGASGASGASGASGASGASGAS
GA
S
GA
S
GA
S
GA
S
GA
S
GA
S
GA
S
GAS
Former Wiles Oil, LDA-16
Atlas
TABLE 1 PROPOSED PROJECT SCHEDULE
TASK
MONTH
November 2024 December 2024
Task 1 – Groundwater Monitoring and Reporting
X
(Sampling)
X
(Reporting)
Labor
Category Staff Quantity Hourly Rate Subtotal Subtotal Totals
P101 Senior Project Manager - Project setup and coordination 2 152.00$ 304.00$ 304.00$
P103 Project Manager - Coordinate with laboratory, coordination of
sampling effort, and update HASP
5 118.00$ 590.00$ 590.00$
P105 Senior Technician - Preparation, collect groundwater elevation and
free product data, sample wells, and process samples
26 90.00$ 2,340.00$ 2,340.00$
P105 Senior Technician - Travel (round trip)1 90.00$ 90.00$ 90.00$
P108 Administrative Assistant - Project setup and invoicing 2 62.00$ 124.00$ 124.00$
Labor Subtotal 3,448.00$ #REF!
Direct Costs
Equipment/Materials/Supplies
Oil/Water Interface Probe 2 55.00$ 110.00$ 110.00$
Sampling Supplies 2 25.00$ 50.00$ 50.00$
Traffic Safety Equipment 2 15.00$ 30.00$ 30.00$
Disposable Bailers 14 9.00$ 126.00$ 126.00$
Outside Services
16 93.50$ 1,496.00$ 1,496.00$
2 214.50$ 429.00$ 429.00$
Per Diem
Meals 0 15.00$ -$ -$
Lodging 0 100.00$ -$ -$
90 0.655$ 58.95$ 58.95$
Direct Costs Subtotal 2,299.95$
Groundwater Monitoring Report
Labor
Category Staff Quantity Hourly Rate Subtotal Subtotal Totals
P101 Senior Project Manager - Coordination and review 1 152.00$ 152.00$ 152.00$
P103 Project Manager - Report review and preparation, payment request
preparation, and project close out
7 118.00$ 826.00$ 826.00$
P102 Professional Geologist - Preparation of the groundwater gradient
map
2 147.00$ 294.00$ 294.00$
P105 Senior Technician - Data entry and report preparation 13 90.00$ 1,170.00$ 1,170.00$
P107 Drafter - Prepare groundwater gradient map in AutoCAD 2 85.00$ 170.00$ 170.00$
P108 Administrative Assistant 1 62.00$ 62.00$ 62.00$
Labor Subtotal 2,674.00$ #REF!
Task 1 Total :8,421.95$
Table 2
Former Wiles Oil
Groundwater Sampling and Reporting
8370 South State Street
Midvale, Utah
Work Assignment LDA-16
Laboratory - TPH Fraction (GRO/DRO)
Laboratory - MBTEXN/TPH-GRO/TPH-DRO (Trip Blank and Field Duplicate)
Mileage (Two round trips, plus pickup and drop off samples at lab)
Task 1- Groundwater Monitoring (Sample Wells MW-1, MW-2, MW-3, MW-4, MW-5, MW-7, MW-8, MW-9, MW-11, MW-12, MW-13, MW-14, MW-15, and
MW-16)
Facility I.D. 4001272
APPENDIX A
CONTRACT REQUIRED PAPER
EXHIBIT “3”
DELIVERABLE AND PAYMENT SCHEDULE
Date September 17, 2024
Work Assignment No. LDA-16
Facility I.D. No. 4001272
Deliverable/Task
Number Description Due Date Price
Task 1
Groundwater Monitoring and
Reporting
Sampling – November 30, 2024
Reporting – December 31, 2024
$8,421.95
Work Assignment Total $8,421.95