HomeMy WebLinkAboutDDW-2024-012144October 16, 2024
Jason Binder
South Duchesne Culinary Water
PO Box 1142
Duchesne, Utah 84021
Subject:Plan Approval, Pump Station 1 Replacement (PF001)
System #07067, File #16772, SRF #3F1879The Division of Drinking Water (the Division) received the plans and specifications for the subject project from your consultant, Jones and Demille
Engineering on September 27, 2024. The Division understands that the project consists of replacing the existing Pump Station 1 building, and replacing the interior components in-kind,
so the pump station will still meet the Divisions rules and regulations.
The Division has completed its review of the plans and specifications, stamped and signed byErik W. Rube, P.E., dated September 27, and find they basically comply with the applicable
portions of Utah’s Administrative Rules for Public Drinking Water Systems in R309. On this basis, the plans for Pump Station 1 Replacement are hereby approved.
This approval pertains to construction only. An Operating Permit must be obtained from the Director before the new pump station may be put in service, unless otherwise authorized by
the Division. A checklist outlining the items required for operating permit issuance is enclosed for your information.Approvals or permits from the local authority or the county may
be necessary before beginning construction of this project. As the project proceeds, notice of any changes in the approved design, as well as any change affecting the quantity or quality
of the delivered water, must be submitted to the Division. We may also conduct interim and final inspections of this project. Please notify us when actual construction begins so that
these inspections can be scheduled.
This approval must be renewed if construction has not begun or if substantial equipment has not been ordered within one year of the date of this letter.The project, as described herein,
is generally eligible for assistance under the Drinking Water Construction Assistance Program. All change orders will need to be reviewed and approved for compliance with the Drinking
Water Rules and the conditions of this construction approval.The project may now be advertised for bids. But, as a condition of the project funding, you must not award the contract or
proceed with construction until the Division of Drinking Water has authorized you to do so. This is necessary to comply with applicable requirements and to protect you, as the funding
recipient, by ensuring that the contract meets requirements for funded projects.
If you have any questions regarding this approval, please contact Nathan Hall, P.E., TriCounty DEQ District Engineer at (435) 630-3852, or me at (385) 515-1464.
Sincerely,
Michael Newberry, P.E.
Permitting and Engineering Support Manager
NDH/HP/mrn/mdbEnclosures –Operating Permit Checklist
cc: Joe Hadlock, TriCounty Health Department, jhadlock@tricountyhealthut.gov
Jason Binder, South Duchesne Water Company, plottdogs73@gmail.com
Erik Rube, Jones and Demille Engineering, eric.m@jonesanddemille.com
Nathan Hall, P.E., DEQ District Engineer, nhall@utah.gov
Kjori Shelley, Division of Drinking Water, kashelley@utah.govNhall 07067 16772 PA Pump Station Replacement
Utah Division of Drinking Water ― Checklist for Issuing Operating PermitsWater System Name:System Number: Project Description:File Number:
Items 1 through 8 below must be submitted to the Division and found to be acceptable prior to operating permit issuance (unless a water line project meets the requirements of R309-500-7
and is not required to obtain an Operating Permit).
Distribution lines (not including in-line booster pump stations) requiring Plan Approval may be placed into service prior to submitting all of the following items and receipt of Operating
Permit if the water system has received items 1 and 4 below.☐1.Certification of Rule Conformance by a professional engineer (P.E.) that all conditions of Plan Approval were accomplished,
and if applicable, changes made during construction were in conformance with rules R309-500 through 550☐2.As-built or record drawings incorporating all changes to approved plans and
specifications (unless no changes were made to the previously approved plans during construction)☐3.Confirmation that as-built or record drawings have been received by the water system☐4.Satisfactory
bacteriological samples as evidence of proper disinfection and flushing in accordance with the appropriate ANSI/AWWA standards:
☐ANSI/AWWA C651-14 AWWA Standard for Disinfecting Water MainsTwo consecutive sample sets at least 16 hours apart, none positive (e.g., every 1,200 feet, end-of-line, each branch)☐ANSI/AWWA
C652-11 AWWA Standard for Disinfection of Water-Storage FacilitiesOne or more samples, none positive☐ANSI/AWWA C653-13 AWWA Standard for Disinfection of Water Treatment PlantsTwo consecutive
samples per unit, none positive, no less than 30 minutes apart☐ANSI/AWWA C654-13 AWWA Standard for Disinfection of WellsTwo consecutive samples, none positive, no less than 30 minutes
apart☐5.Water quality data, where appropriate [For example, include raw and finished water data that demonstrate satisfactory performance of the treatment facility; sample should be
taken from a storage tank for residual volatile organic compounds after tank interior re-coating; etc.]☐6.If applicable, all other documentation that may have been required during the
plan review process☐7.If applicable, confirmation that the water system owner has received the O&M manual for the new facility☐8.If applicable, location data of new storage tank, treatment
facility, or source