July 29,2024
Utah Division of Air Quality
P.O. Box 144820
Salt Lake City, UT 84114-4820
Re: Subpart KKK Semi-Annual Monitoring Report: March 11,
Lisbon Valley Helium Plant, San Juan County, UT
Green NaturalGas Ventures LLC
2024 - June 30,2024
Dear Sir or Madam:
Green Natural Gas Ventures LLC (GNG) is submitting the NSPS KKK semi-annual monitoring
report for the period of March 11,2024 - June 30,2024 for the Lisbon Valley Helium Plant. The
Lisbon Valley Helium Plant was purchased out of bankruptcy; therefore, per UDAQ guidance,
this report only covers the compliance period from the date that GNG assumed ownership.
lf you have any questions regarding this report, please contact Mandy Miller of GNG at 970-
209-3981 or mmiller@gng-partners.com; or Jim Corbit of Bums & McDonnell at 34&41$5107
or jrcorbit@burnsmcd.com.
Enclosure
cc: Director, Air and Toxics Technical Enforcement Program, EPA Region 8
(Mandy) Miller,
REVIEWED
Initials JBR Date 9/30/24
Comp Status Meets
File # 10034 Blue 2
post inspection ldar
tlO CFR Part 60, Subpart KKK
Semi-Annual Equipment Leak Report
Units: Reciprocating compressors (E4A, E4B), Dehy, Gas sweetening, upset Flare, cryo
Month
Valves Pumps Compressors PRDS
Leaking
Not
Repaired Leaking
Not
Repaired leaking
Not
Repaired leaking
Not
Repaired
Mar-24 31 0 2 0 0 0 1 0
Apr-24 77 0 0 0 0 0 1 0
May-24 0 0 0 0 0 0 0 0
lun-24 0 0 0 0 0 0 0 0