HomeMy WebLinkAboutDAQ-2024-010443
195 North 1950 West • Salt Lake City, UT
Mailing Address: P.O. Box 144820 • Salt Lake City, UT 84114-4820
Telephone (801) 536-4000 • Fax (801) 536-4099 • T.D.D. (801) 903-3978
www.deq.utah.gov
Printed on 100% recycled paper
State of Utah
Department of
Environmental Quality
Kimberly D. Shelley
Executive Director
DIVISION OF AIR QUALITY
Bryce C. Bird
Director
SPENCER J. COX
Governor
DEIDRE HENDERSON
Lieutenant Governor
DAQC-928-24
Site ID 10972 (B1)
Jefferey Cowlishaw
Staker Parson Companies
1900 West 2350 South
Ogden, UT 84401
Dear Mr. Cowlishaw:
Re: Staker Parson Companies – Temporary Relocation/Operation, Notice of Intent – Weber
County
Your Notice of Intent dated August 12, 2024, to relocate a portable track-mounted impactor to the
temporary recycling project for Staker Parson Companies’ Ogden Hot Mix Asphalt Plant, located
at 2350 South 1900 West, Ogden, UT, was received by the Utah Division of Air Quality (DAQ)
and has been reviewed.
The following equipment has been approved for operation for this temporary project:
One (1) KPI-JCI 500 tph/328 kW Impactor Crusher
The State of Utah has permitted portable equipment for Staker Parson Companies on the Approval
Order (AO) DAQE-AN115180014-15, dated July 6, 2015. The above referenced location is a
permanent site with established opacity limits for crushing equipment. The impactor crusher shall
operate within acceptable opacity ranges and utilize dust suppression methods established in
Conditions II.B.1.c and II.B.3.e of AO DAQE-AN0109720009-15, dated October 22, 2015.
Hours of operation for this equipment shall be held to 16 hours each day. The maximum
production rate shall be held to the permitted equipment design capacity of 500 tons per hour.
Emissions for this project have been estimated at the following:
Pollutant gram/sec lbs/hr lbs/24 hr tons/yr
PM10 1.97 15.67 156.71 12.22
SOx 0.78 6.16 61.56 4.80
NOx 5.15 40.91 409.11 31.91
CO 1.36 10.75 107.54 8.39
VOC 0.21 1.68 16.83 1.31
" - 1 " * " / Ú à Û Ù Û Ý
DAQC-928-24
Page 2
Approval is granted to relocate and operate this equipment at the new location for a period not to
exceed 180 operational days. As per Utah Administrative Code (UAC) R307-401-17, the
operation of equipment at this temporary site may be for up to 180 working days in any calendar
year not to exceed 365 consecutive days, starting from the initial relocation date. The operational
days per site cannot be extended beyond the stipulated 365 consecutive day period.
The owner/operator shall maintain records of the actual operation hours, days, and production
rate, of the above referenced equipment at this relocation site and have the ability to submit the
information to the DAQ upon the request of representatives of the director. Please make certain
that the plant operator is aware of all the location specific requirements for this site and the
conditions of the aforementioned AO.
Federal New Source Performance Standards Subpart OOO requires that initial Method 9
observations be performed for all applicable portable crushers, screens, and attached conveyors.
Subpart OOO also mandates that all crushers constructed, modified, or reconstructed on or after
April 22, 2008, which are not enclosed, must install spray bars on the equipment and keep
maintenance records to ensure proper spray bar operations.
Utah Division of Water Quality Storm Water Permits and regulations may apply to this temporary
project. Please refer to Utah DEQ Water Quality’s current Storm Water Construction
requirements for additional information.
This approval for relocation in no way releases the owner or operator from any liability for
compliance with all other applicable federal, state, and local regulations including the UAC.
If you have any questions regarding this relocation authorization or the temporary relocation
process, please contact Jordan Garahana at (385) 271-2871.
Sincerely,
Jay P. Morris
Assistant Director
JPM:JG:jl
Enclosures: Submitted Temporary Relocation Form
TRP Request Clarification Email
cc: Weber-Morgan Health Department
4 * - - $ . — + @ E v A ? A C @ D w ? @ ˜
Jordan Garahana <jordangarahana@utah.gov>
Portable/Temporary Relocation Form
6 messages
noreply@qemailserver.com <noreply@qemailserver.com>Mon, Aug 12, 2024 at 4:12 PM
Reply-To: trigger@qemailserver.com
To: jordangarahana@utah.gov
Susan/Chad:
Site # -- Staker Parson Companies has requested a Temporary Relocation. Please see the information below. Any
attachments can be access by clicking on the links.
Recipient Data:
Time Finished: 2024-08-12 16:12:35 MDT
IP: 165.225.10.116
ResponseID: R_1hRx7Ayu7oXIMjD
Link to View Results: Click Here
URL to View Results: https://utahgov.iad1.qualtrics.com/apps/single-response-reports/reports/
o9V6lNxGqD6L5kV25IN2d6ykKmJ1q3yE4c6oF23wMyRHbX057xhaFLxY7FgiVDjZX0lKS%
2E6qpNHOsMDjgjgJMXBJ4SWJFW17aTOuSShOprG41GWAEP1eTmlNtt1iXh3q
fO70NKEuUi4wmT685hbdPmnX0BxSVap6a70DUxpBqtOuC7hlYYXd90JyP610hZKUwnv41Dg832k6omFk9dMAD9--%
2E4gWXvLieZ-hsIk4Vp4BuGmrO5fWP2Lg8xveC4WmtUymMDPZ6dwkUPEkjMJyGD9hvplCZMm
ObUI2zKbxs461yZHWMiYuCp-qdz9eGDgcvCYXbjEkUaicP%2ENAiFrcwg
Response Summary:
Please fill out the information below:
Contact Person: Jeffery Cowlishaw
Company Name: Staker Parson Companies
Mailing Address: 2350 S 1900 W
City: Ogden
Zip: 84401
Phone Number: 385-405-4315
Email: jeffery.cowlishaw@stakerparson.com
Is the site located within a PM2.5 non-attainment and maintenance plan areas on cleared land grea...
Yes
All temporary relocation projects are required to submit a Fugitive Dust Control Plan (FDCP). Lo...
BA14A18E71
Briefly give directions to the site and/or physical address:
2350 S 1900 W Ogden. East side of property.
Proposed Relocation Information:
Closest City Ogden
County Weber
UTM X Coordinates 4,564,298.939
UTM Y Coordinates 414,793.044
Approximate distance to the nearest house/business 455 feet
UTM X Coordinates to nearest house/business 4,564,452.666
UTM Y Coordinates to nearest house/business 414,829.062
Does this site currently have a permit with DAQ?
8/30/24, 10:05 AM State of Utah Mail - Portable/Temporary Relocation Form
https://mail.google.com/mail/u/0/?ik=038c40f7b3&view=pt&search=all&permthid=thread-f:1807221538870234616&simpl=msg-f:180722153887023461…1/4
Yes
If yes, what is the Permit (DAQ-AN) # ?
DAQE-AN0109720008-09
If yes, what is the Permit Holder's Name?
Staker Parson Companies
Please provide the permit ID for the equipment? (DAQE-XXXXXXXXX-XX)
DAQE-AN115180014-15
Please list all the Equipment on Site:Note: It is important to identify ALL diesel powered engine...
1
Equipment Type Impactor Crusher
Make/Model KPI-JCI
Serial or ID# II.A.33
Design Capacity 500 tph/328kW
Please attach a site diagram showing the equipment layout and general site dimensions for this re...
https://utahgov.co1.qualtrics.com/WRQualtricsControlPanel/File.php?F=F_1psaeysMQl9RDkx
Have any other state or local regulatory agencies issued any other "Conditional Use Permits" for...
No
Operational Information: (Please note: Operating time over 16 hours in a 24 hour period will re...
Total Hours of operation per 24 hr period 16
Starting time of operation (am/pm) 6am
Ending time of operation (am/pm) 10pm
Maximum hourly production rate for project 500 tph
Expected startup date 08/15/2024
Expected completion date 08/14/2024
What type of application is this for?
New Application
In accordance with the fee schedule approved by the Utah State Legislature, the Division of Air Q...
https://utahgov.co1.qualtrics.com/WRQualtricsControlPanel/File.php?F=F_2b4a109k2VD9rGf
Owner/Operator Representative:
https://utahgov.co1.qualtrics.com/WRQualtricsControlPanel/File.php?F=F_247Sq0qFWDpnUtM
Jordan Garahana <jordangarahana@utah.gov>Tue, Aug 20, 2024 at 11:39 AM
To: Chad Gilgen <cgilgen@utah.gov>, Susan Weisenberg <sweisenberg@utah.gov>
Hey Chad and Susan,
This is the only TRP request aside from BJ Rees that came in while Susan was away. I meant to email you about this
request since the start up and closing dates are invalid. What should we do about this request?
Thanks,
Jordan
[Quoted text hidden]
--
8/30/24, 10:05 AM State of Utah Mail - Portable/Temporary Relocation Form
https://mail.google.com/mail/u/0/?ik=038c40f7b3&view=pt&search=all&permthid=thread-f:1807221538870234616&simpl=msg-f:180722153887023461…2/4
Jordan Garahana
Environmental Scientist | Minor Source Compliance
M: (385) 271-2871
airquality.utah.gov
Emails to and from this email address may be considered public records and thus
subject to Utah GRAMA requirements.
Chad Gilgen <cgilgen@utah.gov>Tue, Aug 20, 2024 at 12:03 PM
To: Jordan Garahana <jordangarahana@utah.gov>
Cc: Susan Weisenberg <sweisenberg@utah.gov>
Jordan,
That end date looks like a typo and Jeffrey likely intended to put 2025. This is one where you can email the source
contact to clarify the dates and then process the TRP including that additional correspondence.
Thanks,
Chad
Chad Gilgen | Manager | Minor Source Compliance
385-306-6500 (cell)
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA requirements.
[Quoted text hidden]
Jordan Garahana <jordangarahana@utah.gov>Tue, Aug 20, 2024 at 12:08 PM
To: Chad Gilgen <cgilgen@utah.gov>
Cc: Susan Weisenberg <sweisenberg@utah.gov>
Hey Chad,
Thanks for the update. I will email Staker Parsons and then get the TRP process started.
Thanks,
Jordan
[Quoted text hidden]
Susan Weisenberg <sweisenberg@utah.gov>Tue, Aug 20, 2024 at 12:49 PM
To: Jordan Garahana <jordangarahana@utah.gov>
Cc: Chad Gilgen <cgilgen@utah.gov>
I suspect that he meant the completion date to be August 14, 2025 rather than 2024. This type of typo is pretty common.
8/30/24, 10:05 AM State of Utah Mail - Portable/Temporary Relocation Form
https://mail.google.com/mail/u/0/?ik=038c40f7b3&view=pt&search=all&permthid=thread-f:1807221538870234616&simpl=msg-f:180722153887023461…3/4
Susan Weisenberg,
Environmental Scientist
Office: 385-306-6512
On Tue, Aug 20, 2024 at 11:39 AM Jordan Garahana <jordangarahana@utah.gov> wrote:
[Quoted text hidden]
Jordan Garahana <jordangarahana@utah.gov>Tue, Aug 20, 2024 at 1:35 PM
To: Susan Weisenberg <sweisenberg@utah.gov>
Cc: Chad Gilgen <cgilgen@utah.gov>
I emailed Jeffery with Staker Parson to confirm the dates and will await his response. Once I receive that, I will get out a
draft for review.
Thanks,
Jordan
[Quoted text hidden]
8/30/24, 10:05 AM State of Utah Mail - Portable/Temporary Relocation Form
https://mail.google.com/mail/u/0/?ik=038c40f7b3&view=pt&search=all&permthid=thread-f:1807221538870234616&simpl=msg-f:180722153887023461…4/4
Jordan Garahana <jordangarahana@utah.gov>
TRP Request Clarification
9 messages
Jordan Garahana <jordangarahana@utah.gov>Tue, Aug 20, 2024 at 12:12 PM
To: jeffery.cowlishaw@stakerparson.com
Hey Jeffery,
I was looking for some clarification in regards to the TRP request you filed last week for a project in Ogden. You put the
expected start up date as 08/15/2024 and the completion date as 08/14/2024. What is the intended start and end date for
this project?
Thanks,
Jordan Garahana
--
Jordan Garahana
Environmental Scientist | Minor Source Compliance
M: (385) 271-2871
airquality.utah.gov
Emails to and from this email address may be considered public records and thus
subject to Utah GRAMA requirements.
Jordan Garahana <jordangarahana@utah.gov>Mon, Aug 26, 2024 at 11:49 AM
To: jeffery.cowlishaw@stakerparson.com
Hey Jefferey,
Can you please respond with the correct dates for this TRP request so I can get this processed for you?
Thanks,
Jordan
[Quoted text hidden]
Cowlishaw, Jeffery (Staker & Parson Companies) <jeffery.cowlishaw@stakerparson.com>Mon, Aug 26, 2024 at 4:29
PM
To: Jordan Garahana <jordangarahana@utah.gov>
Jordan,
9/12/24, 1:36 PM State of Utah Mail - TRP Request Clarification
https://mail.google.com/mail/u/0/?ik=038c40f7b3&view=pt&search=all&permthid=thread-a:r4649074149326808391&simpl=msg-a:r8572407062511264…1/6
You don't often get email from jordangarahana@utah.gov. Learn why this is important
Sorry, I didn’t see the first message you sent. The start date was intended to be 8/15/2024 and the
completion date would be 8/14/2025.
Thanks,
Jeffery (J) Cowlishaw
Environmental Specialist
North Wasatch
C +1(385)405-4315
E Jeffery.cowlishaw@stakerparson.com
www.crhamericasmaterials.com
From: Jordan Garahana <jordangarahana@utah.gov>
Sent: Monday, August 26, 2024 11:49 AM
To: Cowlishaw, Jeffery (Staker & Parson Companies) <jeffery.cowlishaw@stakerparson.com>
Subject: [EXT] Re: TRP Request Clarifica on
CAUTION: This email originated from outside of the organiza on. Do not click links or open a achments unless you are
expec ng this email and know the contents are safe. If you believe this email may be phishing or malicious, please use the
Report Phish bu on.
[Quoted text hidden]
ATTENTION: Ce courriel vient de l'exterieur de l'entreprise. Ne cliquez pas sur les liens, et n'ouvrez pas les pièces jointes, à
moins que vous ne connaissiez l'expéditeur du courriel et savez que le contenu est sécuritaire. Si vous pensez qu’il s’agit d’un
courriel d’hameçonnage ou malveillant, veuillez cliquer sur le bouton Signaler une tenta ve d’hameçonnage.
Jordan Garahana <jordangarahana@utah.gov>Tue, Sep 3, 2024 at 12:03 PM
To: "Cowlishaw, Jeffery (Staker & Parson Companies)" <jeffery.cowlishaw@stakerparson.com>
Hey Jefferey,
One more question for clarification. Is this crusher going to run off of line power or a diesel generator? If it's running on
diesel generator, please let me know the horsepower of the generator it will be operating off of.
Thanks,
Jordan
[Quoted text hidden]
9/12/24, 1:36 PM State of Utah Mail - TRP Request Clarification
https://mail.google.com/mail/u/0/?ik=038c40f7b3&view=pt&search=all&permthid=thread-a:r4649074149326808391&simpl=msg-a:r8572407062511264…2/6
You don't often get email from jordangarahana@utah.gov. Learn why this is important
Cowlishaw, Jeffery (Staker & Parson Companies) <jeffery.cowlishaw@stakerparson.com>Tue, Sep 3, 2024 at 1:43
PM
To: Jordan Garahana <jordangarahana@utah.gov>
Will you please send me the ID number for the equipment for this request so that I can match it up. I don’t
have a copy of the request available to me.
Jeffery (J) Cowlishaw
Environmental Specialist
North Wasatch
C +1(385)405-4315
E Jeffery.cowlishaw@stakerparson.com
www.crhamericasmaterials.com
From: Jordan Garahana <jordangarahana@utah.gov>
Sent: Tuesday, September 3, 2024 12:04 PM
To: Cowlishaw, Jeffery (Staker & Parson Companies) <jeffery.cowlishaw@stakerparson.com>
Subject: Re: [EXT] Re: TRP Request Clarifica on
CAUTION: This email originated from outside of the organiza on. Do not click links or open a achments unless you are
expec ng this email and know the contents are safe. If you believe this email may be phishing or malicious, please use the
Report Phish bu on.
Hey Jefferey,
One more question for clarification. Is this crusher going to run off of line power or a diesel generator? If it's running on
diesel generator, please let me know the horsepower of the generator it will be operating off of.
Thanks,
Jordan
On Mon, Aug 26, 2024 at 4:29 PM Cowlishaw, Jeffery (Staker & Parson Companies) <jeffery.cowlishaw@
stakerparson.com> wrote:
Jordan,
9/12/24, 1:36 PM State of Utah Mail - TRP Request Clarification
https://mail.google.com/mail/u/0/?ik=038c40f7b3&view=pt&search=all&permthid=thread-a:r4649074149326808391&simpl=msg-a:r8572407062511264…3/6
Sorry, I didn’t see the first message you sent. The start date was intended to be 8/15/2024 and the
completion date would be 8/14/2025.
Thanks,
Jeffery (J) Cowlishaw
Environmental Specialist
North Wasatch
C +1(385)405-4315
E Jeffery.cowlishaw@stakerparson.com
http://secure-web.cisco.com/11UIATK9tUiHPagQyl4WjVEvTknBo6tGNvi6jVDejUwu7Gx_fq4LUNokUOPFw982D-
E4Pwl6htUQ8p80YJ0YR41O1DNvIpZ1rfmat9p3ptZwuKZyIT10HcPZfmbLd4YgY5AqdFhZqNY8_
5Bbma1PLwoYFwBGq1mJDUt-s5gELHfQ9jxvJ1JDOX7nn1p7D_KjevZkP58EfVvMsOKZD6ZaljDCq--3q-bAw-xCfN-
AiJyeckEGskBBep_Gl7yEMW33TMrem38cf6lHgoR7cBwmQKzskv7ID-FB4s5vERKKrQe5vhZcWC_
9LHTRlblvjTeINuxQ3RnlE5pIdRVX3Oghcig/http%3A%2F%2Fwww.crhamericasmaterials.com
[Quoted text hidden]
[Quoted text hidden]
[Quoted text hidden]
Jordan Garahana <jordangarahana@utah.gov>Tue, Sep 3, 2024 at 2:39 PM
To: "Cowlishaw, Jeffery (Staker & Parson Companies)" <jeffery.cowlishaw@stakerparson.com>
It is II.A.33 on the portable AO permit under ID 11518. It is a KPI/JCI 500 tph/ 328 kW Impactor Crusher.
[Quoted text hidden]
Cowlishaw, Jeffery (Staker & Parson Companies) <jeffery.cowlishaw@stakerparson.com>Wed, Sep 4, 2024 at
11:30 AM
To: Jordan Garahana <jordangarahana@utah.gov>
Jordan,
This is a trsck crusher that has an integrated generator that is 328kw.
Sent from my Verizon, Samsung Galaxy smartphone
Get Outlook for Android
From: Jordan Garahana <jordangarahana@utah.gov>
Sent: Tuesday, September 3, 2024 2:39:13 PM
To: Cowlishaw, Jeffery (Staker & Parson Companies) <jeffery.cowlishaw@stakerparson.com>
Subject: Re: [EXT] Re: TRP Request Clarifica on
CAUTION: This email originated from outside of the organiza on. Do not click links or open a achments unless you are expec ng
this email and know the contents are safe. If you believe this email may be phishing or malicious, please use the Report Phish
bu on.
It is II.A.33 on the portable AO permit under ID 11518. It is a KPI/JCI 500 tph/ 328 kW Impactor Crusher.
9/12/24, 1:36 PM State of Utah Mail - TRP Request Clarification
https://mail.google.com/mail/u/0/?ik=038c40f7b3&view=pt&search=all&permthid=thread-a:r4649074149326808391&simpl=msg-a:r8572407062511264…4/6
On Tue, Sep 3, 2024 at 1:43 PM Cowlishaw, Jeffery (Staker & Parson Companies) <jeffery.cowlishaw@
stakerparson.com> wrote:
Will you please send me the ID number for the equipment for this request so that I can match it up. I don’t
have a copy of the request available to me.
Jeffery (J) Cowlishaw
Environmental Specialist
North Wasatch
C +1(385)405-4315
E Jeffery.cowlishaw@stakerparson.com
http://secure-web.cisco.com/185nUffeJG5tRPVCJM94JnHFgOMsKV10iC2pjnBlfge4vFpEA8PcNCy2JrAl
e_1umbwbROhL8q8W-aaNtNsRPlAVdtpgoDwBeUwJWAEM6CXMBR4CT2oRf5GvJe6jXwXyCffH7JzCR
fA8vy8qsoTIpwMuxIL7WnTtaRXItsW3YKHvb4TKXL6FkgUXb74iyI_NVxuGEJkhtEX2thauiIhexiOJHg4-LOeBYFC_
G79ivmzBqEOLYILarfkSDkHwvvDKPgXiP3o6PO41O8YRC-Zzw4OvaHwx64dgDpRltYvb_DwXfi34LZ-
1sNrPFCOpxKnG98VfQMu_wHi5Oc7nVuPp2ag/http%3A%2F%2Fwww.crhamericasmaterials.com
[Quoted text hidden]
[Quoted text hidden]
[Quoted text hidden]
Cowlishaw, Jeffery (Staker & Parson Companies) <jeffery.cowlishaw@stakerparson.com>Mon, Sep 9, 2024 at 9:40
AM
To: Jordan Garahana <jordangarahana@utah.gov>
Jordan,
Where are you at on the air permit? Do you need any other information?
Thanks,
Jeffery (J) Cowlishaw
Environmental Specialist
North Wasatch
C +1(385)405-4315
E Jeffery.cowlishaw@stakerparson.com
www.crhamericasmaterials.com
9/12/24, 1:36 PM State of Utah Mail - TRP Request Clarification
https://mail.google.com/mail/u/0/?ik=038c40f7b3&view=pt&search=all&permthid=thread-a:r4649074149326808391&simpl=msg-a:r8572407062511264…5/6
From: Jordan Garahana <jordangarahana@utah.gov>
Sent: Tuesday, September 3, 2024 2:39 PM
To: Cowlishaw, Jeffery (Staker & Parson Companies) <jeffery.cowlishaw@stakerparson.com>
Subject: Re: [EXT] Re: TRP Request Clarifica on
CAUTION: This email originated from outside of the organiza on. Do not click links or open a achments unless you are
expec ng this email and know the contents are safe. If you believe this email may be phishing or malicious, please use the
Report Phish bu on.
It is II.A.33 on the portable AO permit under ID 11518. It is a KPI/JCI 500 tph/ 328 kW Impactor Crusher.
On Tue, Sep 3, 2024 at 1:43 PM Cowlishaw, Jeffery (Staker & Parson Companies) <jeffery.cowlishaw@
stakerparson.com> wrote:
Will you please send me the ID number for the equipment for this request so that I can match it up. I don’t
have a copy of the request available to me.
Jeffery (J) Cowlishaw
Environmental Specialist
North Wasatch
C +1(385)405-4315
E Jeffery.cowlishaw@stakerparson.com
http://secure-web.cisco.com/185nUffeJG5tRPVCJM94JnHFgOMsKV10iC2pjnBlfge4vFpEA8PcNCy2JrAl
e_1umbwbROhL8q8W-aaNtNsRPlAVdtpgoDwBeUwJWAEM6CXMBR4CT2oRf5GvJe6jXwXyCffH7JzCR
fA8vy8qsoTIpwMuxIL7WnTtaRXItsW3YKHvb4TKXL6FkgUXb74iyI_NVxuGEJkhtEX2thauiIhexiOJHg4-LOeBYFC_
G79ivmzBqEOLYILarfkSDkHwvvDKPgXiP3o6PO41O8YRC-Zzw4OvaHwx64dgDpRltYvb_DwXfi34LZ-
1sNrPFCOpxKnG98VfQMu_wHi5Oc7nVuPp2ag/http%3A%2F%2Fwww.crhamericasmaterials.com
[Quoted text hidden]
[Quoted text hidden]
[Quoted text hidden]
Jordan Garahana <jordangarahana@utah.gov>Mon, Sep 9, 2024 at 11:30 AM
To: "Cowlishaw, Jeffery (Staker & Parson Companies)" <jeffery.cowlishaw@stakerparson.com>
Hey Jefferey,
I have sent the letter out for review today. I will let you know when that gets finalized and approved. Sorry about the wait
on this!
Thanks,
Jordan
[Quoted text hidden]
9/12/24, 1:36 PM State of Utah Mail - TRP Request Clarification
https://mail.google.com/mail/u/0/?ik=038c40f7b3&view=pt&search=all&permthid=thread-a:r4649074149326808391&simpl=msg-a:r8572407062511264…6/6