HomeMy WebLinkAboutDDW-2024-010302Utah Department Of Environmental Quality
Division Of Drinking Water Sanitary Survey
Sanitary Survey
General System Information
Site Visit Date Surveyor Name
07/30/2024 Nagendra Dev
SUMMIT WATER
DISTRIBUTION COMPANY
PWS ID: UTAH22059 Rating: Approved 08/02/1985 Active
1 Admin Contact (AC) [ eMail address is REQUIRED ]
MIN | 15pts | SM | G004 | R309-100-4(5) | Rule requires a person or organization be
designated as the owner of the system and name, address and phone number of such
be supplied to the Division.
*First Name: MIKE S
*Last Name: FOLKMAN
*Organization:
*Address: Redacted
*City: HEBER CITY
*State: UT
*Zip: 84032
*Email: mike@swdc.us
*Phone: 435-649-7324
2 Legal Contact (LC) [ if no eMail address is available, enter NoeMail@utah.gov ]
MIN | 15pts | SM | G004 | R309-100-4(5) | Rule requires a person or organization be
designated as the owner of the system and name, address and phone number of such
be supplied to the Division.
*First Name:
*Last Name:
*Organization: SUMMIT WATER
DISTRIBUTION
*Address: 8506 BLUEBIRD LN
*City: PARK CITY
*State: UT
*Zip: 84098
*Email:
*Phone: 435-649-7324
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 1 of 97
3 Owner Contact (OW) [ if no eMail address is available, enter NoeMail@utah.gov ]
MIN | 15pts | SM | G004 | R309-100-4(5) | Rule requires a person or organization be
designated as the owner of the system and name, address and phone number of such
be supplied to the Division.
*First Name:
*Last Name:
*Organization: SUMMIT WATER DIST
COXX
*Address: 8506 Bluebird Ln
*City: PARK CITY
*State: UT
*Zip: 84098
*Email: summitwater@swdc.us
*Phone: 435-649-7324
Emergency Phone: 435-649-7324
4 Direct Operator in Charge (DO) [ if no eMail address is available, enter
NoeMail@utah.gov ]
MIN | 15pts | SM | G004 | R309-100-4(5) | Rule requires a person or organization be
designated as the owner of the system and name, address and phone number of such
be supplied to the Division.
*First Name: MIKE S
*Last Name: FOLKMAN
*Organization:
*Address: 532 N 1300 E
*City: HEBER CITY
*State: UT
*Zip: 84032
*Email: mike@swdc.us
*Phone: 435-649-7324
5 Does the system serve a Residential population?Y
5A Population - Residential 6000
5B Operating Period (Start Date) - Residential 01/01
5C Operating Period (End Date) - Residential 12/31
6 Does the system serve a Transient population? (A transient population is a rotating
population that is served by a water system that does not remain in the jurisdiction of
the water system for long periods of time. Examples of a transient population include,
but are not limited to, campers at a campground, users of a highway rest stop, skiers
at a ski resort, guests at a hotel, or patrons of a restaurant or a shopping center.)
N
7 Does the system serve a Non-Transient population? (A non-transient population is a
population served by a water system that is the same population being served by the
system for at least six months of the year, but is not a resident in the system.
Examples of a non-transient population include, but are not limited to, employees of a
restaurant, shop, or ski resort; teachers and students at a school, day-care center, or
church; doctors, nurses, and other employees at a hospital or healthcare clinic.)
N
8 Population - Wholesale :850
9 Residential Connections:3015
10 Commercial Connections:1956
11 Industrial Connections:1094
12 Agricultural Connections:0
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 2 of 97
Site Visit Info
Management and Operations
13 Date of Survey (First Day of Field Work)07/29/2024
14 Date of Survey (Last Day of Field Work) ** this should match the Date of Survey in the
header **
07/30/2024
15 Date final report sent to system (questionnaire, deficiency report and capacity
spreadsheet)
08/26/2024
16 Water system representative present during the survey:Kaden Nielsen (Notes: David Hilton)
17 How much time was spent to prepare survey documents prior to field survey? (Round
up to nearest quarter hour)
5
18 How much time was spent to complete the field survey (arrival to completion; include
travel time between water system facilities)? (Round up to nearest quarter hour)
10
19 How much time was spent traveling from the office to system and back again at the
end of the field survey? (Round up to nearest quarter hour)
2
20 How much time did it take to finish the Survey Report? (Round up to nearest quarter
hour)
6
21 Did you survey multiple water systems in one trip? ... if yes, answer the following
question(s)
N
22 For a community water system with water sources that require power to produce
sufficient flow, system is equipped with standby power option.
SIG | 25pts | SO | S033 | R309-515-6(2)(a) | Rule requires a community water system
without naturally flowing water sources, such as springs or flowing wells, to have one
or more of the system's sources equipped for operation during power outages. To
ensure continuous service when the primary power has been interrupted, a redundant
power supply is required. A redundant power supply may include a transfer switch for
auxiliary power such as a generator or a power supply service with coverage from two
independent substations. This significant deficiency must be corrected within 120 days
of notification or have a corrective action plan approved by DDW.
C
23 There are no undocumented drinking water facilities (i.e. tanks, pump stations,
treatment facilities, etc.) or recent modifications that have not gone through or in
process of DDW review [LIST UNDOCUMENTED FACILITIES OR DESCRIBE
MODIFICATIONS, IF APPLICABLE] [undocumented sources are covered in a
different question]
SIG | 50pts | SM | G001 | R309-100-5(2), R309-500-6, R309-500-9, R309-500-9(2)
and (3) | Rule requires complete plans & specification for all public drinking water
projects to be approved in writing by the Director. Any facility found that has not
started DDW review shall be considered unapproved. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
24 Are there any individual home booster pumps installed in the distribution system (not
for fire suppression)?
SIG | 50pts | SM | M008 | R309-550-11(3) | R309-550-11(3)
C
25 Does the system haul water?N
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 3 of 97
Cross Connection and Operator Certification
26 For a community system serving 100 or more connections, at least 2 water sources
are available.
SIG | 50pts | SO | TGR7 | R309-515-4(3) | Rule requires Community Water Systems
serving more than 100 connections to have a minimum of two sources except where
served by a water treatment plant. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
27 Does system have a consecutive connection to another water system not listed in the
SOURCE section of Waterlink Report? If yes, answer the following question(s)
N
28 Does the system have a deficiency meeting the required source capacity? (USE
SPREADSHEET FOR CALCULATIONS) *IF YES, SELECT CORRECT STATEMENT
FROM THE FOLLOWING AND MARK "YES"; MARK ALL OTHER STATEMENTS
"NO."
N
29 Does the system have a deficiency meeting the required storage capacity DUE
SOLELY TO FIRE SUPPRESSION NEEDS? (USE SPREADSHEET FOR
CALCULATIONS) *IF YES, SELECT CORRECT STATEMENT FROM THE
FOLLOWING AND MARK "YES"; MARK ALL OTHER STATEMENTS "NO."
N
30 Does the system have a deficiency meeting the required equalization storage capacity
for indoor/outdoor demands (but not because of fire suppression needs)? (USE
SPREADSHEET FOR CALCULATIONS) *IF YES, SELECT CORRECT STATEMENT
FROM THE FOLLOWING AND MARK "YES"; MARK ALL OTHER STATEMENTS
"NO."
N
31 Does your water system have an Emergency Response Plan?
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
Y
31A Does your Emergency Response Plan include cybersecurity?
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
Y
31B Does your water system use any computers, laptops, phones, tablets, or any other
computer systems to manage, operate, or maintain the PWS (SCADA or Industrial
Control Systems)? This includes any water sources, treatment, distribution or any
process related to operation function
C
31C Does your water system use any computer systems in regular business operations
such as accounting, billing, payroll, human resources, or management?
C
32 Legally adopted authority statement
MIN | 15pts | SM | M003 | R309-105-12(2) | Rule requires each public water system to
have a cross connection control program that includes a legally adopted and functional
local authority to enforce the program (i.e., ordinance, bylaw, or policy).
C
33 Documentation of annual public awareness and/or employee training
MIN | 15pts | SM | M004 | R309-105-12(2) | Rule requires each public water system to
have a cross connection control program that includes providing public education or
awareness material or presentations.
C
34 Documentation of personnel trained to manage the program (COMMUNITY WATER
SYSTEMS POPULATION 500 AND ABOVE REQUIRE A DDW CERTIFIED CCC
PROGRAM ADMINISTRATOR. ALL OTHER WATER SYSTEMS REQUIRE AT A
MINIMUM BACKFLOW 101 OR EQUIVALENT/ GREATER CCC TRAINING)
MIN | 15pts | SM | M005 | R309-105-12(2) | Rule requires each public water system to
have a cross connection control program that includes an operator with adequate
training in the area of cross connection control or backflow prevention.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 4 of 97
General Maintenance and Environment
Distribution
35 Does the water system have detailed records of cross connection control activities?
(inventories of backflow assemblies, devices, and air gaps installed within the system)
MIN | 15pts | SM | M006 | R309-105-12(2) | Rule requires each public water system to
have a cross connection control program that includes written records of cross
connection control activities.
C
36 Does the water system have records of on-going enforcement activities? (test history,
enforcement activities, hazard assessments)
MIN | 15pts | SM | M007 | R309-105-12(2) | Rule requires each public water system to
have a cross connection control program that includes test history and documentation
of on-going enforcement activities.
C
37 Operator meets required level of certification for water system. ( IF NO CERTIFIED
OPERATOR IS REQUIRED MARK COMPLIANT )
SIG | 50pts | OC | C001 | R309-105-11, R309-300-5(3) | Rule requires every
community and NTNC water system and public water systems that utilize
treatment/filtration to have at least one operator certified at the classified grade of the
water system. Certification must be appropriate for the type of system operated
(treatment and/or distribution). This significant deficiency must be corrected within 120
days of notification or have a corrective action plan approved by DDW.
C
38 Certified operator is within 1 hour travel time of water system. ( IF NO CERTIFIED
OPERATOR IS REQUIRED MARK COMPLIANT )
MIN | 0pts | OC | C002 | R309-300-5(14) | Rule requires the operator to be within 1
hour travel time, under normal work and home conditions, of each drinking water
system for which he is considered in direct responsible charge.
C
39 Are there any visual indications of unsanitary conditions?
SIG | 50pts | SM | M017 | R309-200-6, R309-105-18, R309-215-4(3) | R309-200-6 The
Secondary Maximum Contaminant Levels for public water systems deals with
substances which affect the aesthetic quality of drinking water. They are presented
here as recommended limits or ranges and are not grounds for rejection. The taste of
water may be unpleasant and the usefulness of the water may be impaired if these
standards are significantly exceeded.
R309-105-18 The Director or the local health department shall be informed by
telephone by a water supplier of any "emergency situation". The term "emergency
situation...
R309-215-4(3) If the water fails to meet minimum standards, then certain public
notification procedures shall be carried out, as outlined in R309-220. Water suppliers
shall also keep analytical records in their possession, for a required length of time, as
outlined in R309-105-17.
C
40 No unprotected connection between the distribution system and a source of
contamination. (If there is an unprotected connection, describe the location in detail.)
SIG | 50pts | DS | D009 | R309-550-5(11) | R309-550-5(11)
C
41 Are air release/vacuum valves in the distribution system? ... if yes, answer the
following question(s)
Y
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 5 of 97
41A Open end of vent line covered with #14 mesh screen
SIG | 25pts | DS | D004 | R309-550-6(6)(b) | Rule states the open end of the air relief
vent pipe from automatic valves shall be provided with a #14 mesh, non-corrodible
screen and a downward elbow, and where possible, be extended to at least one foot
above grade. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
41B For a valve in a chamber, open end of vent pipe is at least 12 inches above grade or
one foot above distribution line in a chamber that does not flood.
SIG | 25pts | DS | D006 | R309-550-6(6)(b) | Rule states the open end of the air relief
vent pipe from automatic valves shall be provided with a #14 mesh, non-corrodible
screen and a downward elbow, and where possible, be extended to at least one foot
above grade. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
41C Chamber has drain to daylight, gravel-filled adsorption pit if not subject to flooding, or
sump pump.
SIG | 25pts | DS | D007 | R309-550-6(6)(b) and (7)(b) | Rule states chambers shall be
provided with a drain to daylight, if possible. Where this is not possible, underground
gravel-filled absorption pits may be used if the site is not subject to flooding and
conditions will assure adequate drainage. Sump pumps may also be considered if a
drain to daylight or absorption pit is not feasible. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
41D Open end of vent line down-turned.
SIG | 25pts | DS | D006 | R309-550-6(6)(b) | Rule states the open end of the air relief
vent pipe from automatic valves shall be provided with a #14 mesh, non-corrodible
screen and a downward elbow, and where possible, be extended to at least one foot
above grade. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
42 Water system has a program to maintain, operate, or control the use of fire hydrants.
REC | 0pts | DS | D012 | N/A | Fire hydrants provide a direct access to the water in the
distribution system. In order to protect the quality and integrity of the water, fire
hydrant access should be controlled.
C
43 Blow offs or air release valves are not directly connected to a sanitary sewer line.
SIG | 50pts | DS | D013 | R309-550-6(5)(a), R309-550-6(6)(c) and (7)(a) | Rule states
blow-offs or air relief valves shall not be connected directly to a sewer. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
C
44 Blow offs or air release valves do not discharge below flood level in ditches or
streams.
SIG | 50pts | DS | D016 | R309-550-9(1) and (2), R309-550-13(2) | R309-550-9(1 & 3)
C
45 All water mains installed after 1995 that provide fire flow are at least 8 inches in
diameter.
MIN | 15pts | DS | D019 | R309-550-5(4) & (5) | Rule states that the minimum line size
serving a fire hydrant lateral shall be 8-inch diameter unless a hydraulic analysis
indicates that required flow and pressures can be maintained by 6-inch lines.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 6 of 97
General Disinfection
ST013 - RED HAWK TANK 2 - Proposed
TP011 - EAST CANYON WTP (SOLD TO WBWCD) - Inactive (SD - SOLD/TRANSFERRED)
WS002 - HI-UTE WELL - Inactive (AB - ABANDONED)
WS010 - UPPER SPRING CREEK SPRING -
46 Distribution system capable of providing minimum pressure of 20 psi at all service
connections.
SIG | 50pts | DS | D003 | R309-105-9, R309-550-5(1) | Rule states the distribution
system shall maintain minimum pressures as required by R309-105-9 at all points of
connection under all flow conditions. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
47 Was the water system constructed or new portions added after January 1, 2007? ... if
yes, answer the following question(s)
N
48 Water system follows AWWA disinfection procedures for new, repaired, or seasonal
water mains and tanks.
SIG | 25pts | MR | D018 | R309-550-8(10) | All new and repaired water mains and
appurtenances shall be disinfected in accordance with AWWA Standard C651. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
49 How often do you periodically disinfect any or all parts of your water system (i.e. batch
disinfection) other than for repairs or maintenance?
SIG | 50pts | SM | G006 | R309-105-6(1)(a), R309-500-6 | R309-105-6(1) Approval of
Engineering Plans and Specifications
R309-500-6 Plan Approval Procedure.
C
52 Is this facility in operation without an Operating Permit?
SIG | 50pts | SM | G001 | R309-100-5(2), R309-500-6, R309-500-9, R309-500-9(2)
and (3) | Rule requires complete plans & specification for all public drinking water
projects to be approved in writing by the Director. Any facility found that has not
started DDW review shall be considered unapproved. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
N
52A When is the anticipated date to request an Operating Permit? Explain in comments...several years
50 Does the water system still have physical access to this facility? Y/N Guidance:
Answer NO if sold and no longer have security access or the facility is demolished and
can not be inspected.
N
51 Does the water system still have physical access to this facility? Y/N Guidance:
Answer NO if sold and no longer have security access or the facility is demolished and
can not be inspected.
N
53 Is this facility Active or Inactive? (Active status means used on a routine/seasonal
basis without long periods of inactivity and water quality samples are routinely
collected))
I
53A Explain why this facility is Inactive (Is this facility in stand-by mode and not used
regularly, has not been used for multiple years, does it have known water quality
concerns?)
stand-by mode
54 Operating Period (Start Date)01/01
55 Operating Period (End Date)12/31
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 7 of 97
56 Undocumented sources shall not be physically connected to the drinking water
system. (IF SOURCE IS NOT IN SYSTEM INVENTORY MARK "DEFICIENT")
SIG | 200pts | SO | S001 | R309-515-6(5), R309-515-7(4), R309-500-9(2) and (3) |
R309-105-6(1) requires plans and specifications for all public drinking water projects to
be approved in writing by the Director prior to the commencement of construction. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
57 Area of equal or higher elevation within 50 feet of spring collection devices is fenced.
MIN | 15pts | SO | SS02 | R309-515-7(7)(e) | Rule requires a stock-tight fence around
the spring collection area.
C
58 Surface water runoff diverted away from spring by diversion channel or berm.
MIN | 15pts | SO | SS03 | R309-515-7(7)(g) | Rule requires a diversion channel or
berm, constructed immediately inside the fenced area, capable of diverting all
anticipated surface water runoff away from the spring collection area.
C
59 Spring box has a means to release overflow?
MIN | 15pts | SO | SS23 | R309-515-7(7)(d), R309-545-13(1) | All junction boxes and
collection boxes, must comply with R309-545 with respect to access openings,
venting, and tank overflow. Lids for these spring boxes shall be gasketed and the box
adequately vented.
Y
59A Overflow screened with #4 mesh screen
SIG | 25pts | SO | SS04 | R309-515-7(7)(d), R309-545-13(3) | Overflow pipes on
junction and collection boxes shall comply with R309-545 and be screened with No. 4
mesh non-corrodible screens. This significant deficiency must be corrected within 120
days of notification or have a corrective action plan approved by DDW.
C
59B Overflow has a minimum of 12 inch clearance above flood rim of receiving basin
SIG | 25pts | SO | SS14 | R309-515-7(7)(d), R309-545 | Overflow pipes on junction
and collection boxes shall comply with R309-545 and discharge a minimum of 12
inches above the ground surface or rim of the receiving basin. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
C
60 Drain has minimum of 12 inch clearance above flood rim of receiving basin
SIG | 25pts | SO | SS14 | R309-515-7(7)(d), R309-545 | Overflow pipes on junction
and collection boxes shall comply with R309-545 and discharge a minimum of 12
inches above the ground surface or rim of the receiving basin. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
C
61 Spring collection area graded and no evidence of water ponding or flow on surface?
SIG | 25pts | SO | SS06 | R309-515-7(7)(i) | Rule requires the spring to be developed
as thoroughly as possible to minimize the possibility of excess water ponding within
the collection area. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 8 of 97
62 If a liner is present, spring liner integrity is maintained.
SIG | 50pts | SO | SS19 | R309-515-7(7)(b)(iv) | If a liner is present, it shall be installed
to assure its integrity. No sharp-edged stones or stones two inches or larger shall be
located within two inches of the liner. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
63 No deep-rooted vegetation is within the 50 ft collection area.
SIG | 25pts | SO | SS07 | R309-515-7(7)(f) | All deep-rooted vegetation within the
fenced collection area shall be removed by a means not negatively affecting water
quality. This significant deficiency must be corrected within 120 days of notification or
have a corrective action plan approved by DDW.
C
64 No roots seen in collection boxes and junctions.
SIG | 25pts | SO | SS08 | R309-105-10(4)(a), R309-515-8(1)(a) | Spring collection
areas shall be periodically (preferably annually) cleared of deep-rooted vegetation to
prevent root growth from clogging collection lines. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
65 Is a spring collection box present? ... if yes, answer the following question(s)
MIN | 5pts | SO | L014 | R309-515-7(7)(c) | Rule requires each spring collection area
to be provided with at least one collection box to permit spring inspection and testing.
Y
65A Spring box has shoe box type lid with 2 inch overlap around frame
SIG | 25pts | SO | SS09 | R309-515-7(7)(d), R309-545-14 (2) | Access openings shall
comply with R309-545 and be provided with a close-fitting, solid shoebox-type cover
that extends down around the frame at least 2 inches. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
65B Spring box lid is gasketed
SIG | 25pts | SO | SS10 | R309-515-7(7)(d), R309-545-14 (2) | Access openings shall
comply with R309-545 and be provided with a cover furnished with a gasket between
the lid and frame. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
65C Spring box lid does not show evidence of a vacuum.
MIN | 5pts | SO | SS11 | R309-515-7(7)(d), R309-545-15 | Rule requires junction
boxes and collection boxes to comply with R309-545 with respect to venting.
Therefore, a junction or collection box requires a vent to be fitted with #14 mesh or
finer non-corrodible screen, be fitted with a protective heavy-gauge screen or covering
if 6 inches in diameter or greater, be down-turned and shielded to prevent the
entrance of contaminants, be located and sized to avoid blockage during winter, and
have the end of the vent discharge a minimum of 24 inches above the earth on buried
structures.
C
65D Spring box opening is at least 4 inches above the surface of the box or 18 inches
above an earthen cover if the box is buried.
MIN | 15pts | SO | SS12 | R309-515-7(7)(d), R309-545-14 (1), | Access openings shall
comply with R309-545 and be framed at least 4 inches above the surface of the spring
box roof at the opening or 18 inches above the ground surface on a buried spring box.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 9 of 97
65E Spring box lid is locked
SIG | 25pts | SO | SS13 | R309-515-7(7)(d), R309-545-14 (3) | Access openings shall
comply with R309-545 and the lids to the openings shall be locked. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
C
65F All openings/penetrations in the spring collection box are sealed.
SIG | 50pts | SO | SS20 | R309-515-7(7)(d), R309-545-9(1) and (2) | All junction and
collection boxes shall comply with R309-545 and shall have suitable watertight roofs
and sidewalls that exclude birds, animals, insects, and excessive dust. All openings
shall be kept to a minimum and be watertight. Pipes that may contain water of lesser
quality than drinking water shall not penetrate the spring box. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
C
66 Is a spring box vent present? ... if yes, answer the following question(s)
MIN | 5pts | SO | SS11 | R309-515-7(7)(d), R309-545-15 | Rule requires junction
boxes and collection boxes to comply with R309-545 with respect to venting.
Therefore, a junction or collection box requires a vent to be fitted with #14 mesh or
finer non-corrodible screen, be fitted with a protective heavy-gauge screen or covering
if 6 inches in diameter or greater, be down-turned and shielded to prevent the
entrance of contaminants, be located and sized to avoid blockage during winter, and
have the end of the vent discharge a minimum of 24 inches above the earth on buried
structures.
Y
66A Vent is down-turned.
SIG | 25pts | SO | SS16 | R309-515-7(7)(d), R309-545-15(1) | All vents on junction
and collection boxes shall comply with R309-545 and be downturned a minimum of 2
inches below any opening and shielded to prevent the entrance of contaminants. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
66B Vent has #14 or finer non-corrodible mesh screen and a protective screen/covering if
6-inch diameter or greater.
SIG | 25pts | SO | SS17 | R309-515-7(7)(d), R309-545-15(4) and (5) | All vents on
junction and collection boxes shall comply with R309-545 and be fitted with No. 14 or
finer non-corrodible mesh screen. Vents 6-inch diameter or larger shall be fitted with
additional heavy gage screen or substantial covering to protect the No. 14 mesh
screen. This significant deficiency must be corrected within 120 days of notification or
have a corrective action plan approved by DDW.
C
66C End of vent has sufficient clearance to prevent ice/snow blockage or is at least 24
inches above the earthen cover
SIG | 25pts | SO | SS18 | R309-515-7(7)(d), R309-545-15(2) and (3) | All vents on
junction and collection boxes shall comply with R309-545 and shall be located and
sized to avoid blockage during winter. The end of a vent on a buried spring box shall
discharge a minimum of 24 inches above the ground. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 10 of 97
WS001 - NEW REST STOP WELL - Active
67 Spring has a permanent flow-measuring device.
MIN | 5pts | SO | SS01 | R309-515-7(7)(h) | Rule requires a spring to have a
permanent flow measuring device.
C
68 Is this facility Active or Inactive?A
69 Operating Period (Start Date)01/01
70 Operating Period (Ending Date)12/31
71 Undocumented sources shall not be physically connected to the drinking water
system. (IF SOURCE IS NOT IN SYSTEM INVENTORY MARK "DEFICIENT")
SIG | 200pts | SO | S001 | R309-515-6(5), R309-515-7(4), R309-500-9(2) and (3) |
R309-105-6(1) requires plans and specifications for all public drinking water projects to
be approved in writing by the Director prior to the commencement of construction. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
72 Well casing is at least 18 inches above finished ground surface and 12 inches above
well house floor.
SIG | 25pts | SO | S003 | R309-515-6(6)(b)(vi), R309-515-6(12)(c)(ii), R309-515-
6(13)(a) | Rule requires the permanent well casing to project at least 18 inches above
the final ground surface and 12 inches above the pump house floor; at sites subject to
flooding, the top of the casing must terminate at least 3 feet above the 100-year flood
level or highest known flood elevation, whichever is higher. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
73 Wellhead is sealed to prevent contamination.
SIG | 50pts | SO | S013 | R309-515-6(6)(i) | R309-515-6(6)(i) and R309-515-
6(12)(b,c,d)require a sanitary seal be installed and maintained at the wellhead and
discharge piping. This significant deficiency should be corrected within 120 days of
notification or have a corrective action plan approved by
C
74 Is the well casing vented? ... if yes, answer the following question(s)Y
74A Vent screened with #14 mesh screen
SIG | 25pts | SO | S006 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(a)require vents be fitted with a #14 mesh or finer non-corrodible screen.
C
74B Vent down-turned
SIG | 25pts | SO | S007 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(b) requires vents be downturned or shielded to prevent the entrance of
surface water or rainwater.
C
74C Vent has adequate clearance to prevent contamination from entering the well
SIG | 25pts | SO | S008 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(b) requires vents be terminated with a discharge with an appropriate air gap.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 11 of 97
75 Does the well have a pump to waste line? ... if yes, answer the following question(s)Y
75A Pump to waste line discharges with a minimum of 12-inch clearance to flood rim
SIG | 25pts | SO | S009 | R309-515-6(12)(d)(ix) | Rule requires a pump-to-waste line
connected to a sewer/storm drain to have a minimum 12-inch clearance to the flood
rim. This significant deficiency must be corrected within 120 days of notification or
have a corrective action plan approved by DDW.
C
75B Pump to waste line equipped with #4 non-corrodible mesh screen
SIG | 25pts | SO | S010 | R309-515-6(12)(d)(ix) | The discharge end of the pump-to-
waste line shall be covered with a No. 4 mesh corrosion-resistant screen. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
75C Pump to waste line downturned if it discharges to sewer/storm drain or allowing
complete drainage if not downturned
SIG | 25pts | SO | S011 | R309-515-6(12)(d)(ix) | The discharge end of the pump-to-
waste line shall be downturned. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
76 Provisions available to periodically measure water levels
MIN | 5pts | SO | S015 | R309-515-6(12)(e ), R309-515-6(12)(c)(vi) | Rule requires
provisions be made to permit periodic measurement of water levels in the completed
well.
C
77 Wellhead secured to protect quality water
SIG | 25pts | SO | S002 | R309-105-10(5) | All water system facilities shall be secure.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
78 Well head or well house and equipment protected from flooding
SIG | 25pts | SO | S020 | R309-515-6(6)(b)(vi), R309-515-6(12)(d)(iii), R309-515-
6(13)(a) to (d) | Top of well casing shall terminate at least 18” above ground level or
12” above well house floor and for sites that flood at least 3’ above 100-year flood
level or highest known flood elevation. Well casing terminating in underground vault
shall have a drain to daylight and surface runoff directed away from vault access. Well
house floor shall be sloped for drainage, and have a drain to daylight unless highly
impractical. This significant deficiency must be corrected within 120 days of notification
or have a corrective action plan approved by DDW.
C
79 There are no unprotected cross-connections in well discharge piping.
SIG | 50pts | SO | S021 | R309-105-12(1), R309-515-6(12)(d)(iii) | Rule requires the
well discharge piping to be protected against the entrance of contamination. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
80 No toxic chemicals, hazardous or flammable materials, or lubricants inside the well
house or near well head?
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 12 of 97
81 Well discharge line has a smooth-nosed sampling tap, which samples the well water
before any chemical injection. (first item from the wellhead).
MIN | 5pts | SO | S023 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with a smooth nosed sampling tap, a check valve, a pressure gauge, a
means of measuring flow, and a shutoff valve. (smooth nosed sampling tap being the
first item from the well head and the shut-off valve as the last item)
C
82 Well discharge line has a check valve.
MIN | 5pts | SO | S024 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
83 Well discharge line has a pressure gauge.
MIN | 5pts | SO | S025 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
84 Well discharge line has a means to measure flow.
MIN | 5pts | SO | S026 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
85 Well discharge line has a shut-off valve (last item from the well head).
MIN | 5pts | SO | S027 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
86 Is there an air/vac valve on the well discharge line? If yes, answer the following
question(s)
Y
86A Air vacuum relief valve on well discharge piping downturned
SIG | 25pts | SO | S028 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be down-turned.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
86B Air vacuum relief valve on well discharge piping screened with #14 mesh screen
SIG | 25pts | SO | S029 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be covered with a
#14 mesh corrosion-resistant screen. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
86C Air vacuum relief valve on well discharge piping has at least 6 inches of clearance
above floor
SIG | 25pts | SO | S030 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be at least 6
inches above the well house floor. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 13 of 97
WS003 - JEREMY RANCH WELL #4 - Active
87 Wells that pump directly into a distribution system have means to release trapped air
from pump discharge piping (for example, pumps directly to a tank, has an air release
valve or pump to waste line)
MIN | 5pts | SO | SL01 | R309-515-6(12)(d)(v) | Rule requires a well that pumps
directly into the distribution system be equipped with an air release/vacuum relief valve
located upstream of the check valve, unless the wellhead valve and piping provide for
pumping to waste all trapped air before water is introduced into the distribution
system.
C
88 Does well require oil-lubrication?N
89 Is this facility Active or Inactive?A
90 Operating Period (Start Date)01/01
91 Operating Period (Ending Date)12/31
92 Undocumented sources shall not be physically connected to the drinking water
system. (IF SOURCE IS NOT IN SYSTEM INVENTORY MARK "DEFICIENT")
SIG | 200pts | SO | S001 | R309-515-6(5), R309-515-7(4), R309-500-9(2) and (3) |
R309-105-6(1) requires plans and specifications for all public drinking water projects to
be approved in writing by the Director prior to the commencement of construction. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
93 Well casing is at least 18 inches above finished ground surface and 12 inches above
well house floor.
SIG | 25pts | SO | S003 | R309-515-6(6)(b)(vi), R309-515-6(12)(c)(ii), R309-515-
6(13)(a) | Rule requires the permanent well casing to project at least 18 inches above
the final ground surface and 12 inches above the pump house floor; at sites subject to
flooding, the top of the casing must terminate at least 3 feet above the 100-year flood
level or highest known flood elevation, whichever is higher. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
94 Wellhead is sealed to prevent contamination.
SIG | 50pts | SO | S013 | R309-515-6(6)(i) | R309-515-6(6)(i) and R309-515-
6(12)(b,c,d)require a sanitary seal be installed and maintained at the wellhead and
discharge piping. This significant deficiency should be corrected within 120 days of
notification or have a corrective action plan approved by
C
95 Is the well casing vented? ... if yes, answer the following question(s)Y
95A Vent screened with #14 mesh screen
SIG | 25pts | SO | S006 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(a)require vents be fitted with a #14 mesh or finer non-corrodible screen.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 14 of 97
95B Vent down-turned
SIG | 25pts | SO | S007 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(b) requires vents be downturned or shielded to prevent the entrance of
surface water or rainwater.
C
95C Vent has adequate clearance to prevent contamination from entering the well
SIG | 25pts | SO | S008 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(b) requires vents be terminated with a discharge with an appropriate air gap.
C
96 Does the well have a pump to waste line? ... if yes, answer the following question(s)Y
96A Pump to waste line discharges with a minimum of 12-inch clearance to flood rim
SIG | 25pts | SO | S009 | R309-515-6(12)(d)(ix) | Rule requires a pump-to-waste line
connected to a sewer/storm drain to have a minimum 12-inch clearance to the flood
rim. This significant deficiency must be corrected within 120 days of notification or
have a corrective action plan approved by DDW.
C
96B Pump to waste line equipped with #4 non-corrodible mesh screen
SIG | 25pts | SO | S010 | R309-515-6(12)(d)(ix) | The discharge end of the pump-to-
waste line shall be covered with a No. 4 mesh corrosion-resistant screen. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
96C Pump to waste line downturned if it discharges to sewer/storm drain or allowing
complete drainage if not downturned
SIG | 25pts | SO | S011 | R309-515-6(12)(d)(ix) | The discharge end of the pump-to-
waste line shall be downturned. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
97 Provisions available to periodically measure water levels
MIN | 5pts | SO | S015 | R309-515-6(12)(e ), R309-515-6(12)(c)(vi) | Rule requires
provisions be made to permit periodic measurement of water levels in the completed
well.
C
98 Wellhead secured to protect quality water
SIG | 25pts | SO | S002 | R309-105-10(5) | All water system facilities shall be secure.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
99 Well head or well house and equipment protected from flooding
SIG | 25pts | SO | S020 | R309-515-6(6)(b)(vi), R309-515-6(12)(d)(iii), R309-515-
6(13)(a) to (d) | Top of well casing shall terminate at least 18” above ground level or
12” above well house floor and for sites that flood at least 3’ above 100-year flood
level or highest known flood elevation. Well casing terminating in underground vault
shall have a drain to daylight and surface runoff directed away from vault access. Well
house floor shall be sloped for drainage, and have a drain to daylight unless highly
impractical. This significant deficiency must be corrected within 120 days of notification
or have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 15 of 97
100 There are no unprotected cross-connections in well discharge piping.
SIG | 50pts | SO | S021 | R309-105-12(1), R309-515-6(12)(d)(iii) | Rule requires the
well discharge piping to be protected against the entrance of contamination. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
101 No toxic chemicals, hazardous or flammable materials, or lubricants inside the well
house or near well head?
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
102 Well discharge line has a smooth-nosed sampling tap, which samples the well water
before any chemical injection. (first item from the wellhead).
MIN | 5pts | SO | S023 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with a smooth nosed sampling tap, a check valve, a pressure gauge, a
means of measuring flow, and a shutoff valve. (smooth nosed sampling tap being the
first item from the well head and the shut-off valve as the last item)
C
103 Well discharge line has a check valve.
MIN | 5pts | SO | S024 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
104 Well discharge line has a pressure gauge.
MIN | 5pts | SO | S025 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
105 Well discharge line has a means to measure flow.
MIN | 5pts | SO | S026 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
106 Well discharge line has a shut-off valve (last item from the well head).
MIN | 5pts | SO | S027 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
107 Is there an air/vac valve on the well discharge line? If yes, answer the following
question(s)
Y
107A
Air vacuum relief valve on well discharge piping downturned
SIG | 25pts | SO | S028 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be down-turned.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
107B
Air vacuum relief valve on well discharge piping screened with #14 mesh screen
SIG | 25pts | SO | S029 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be covered with a
#14 mesh corrosion-resistant screen. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 16 of 97
WS004 - KNIGHT WELL #3 -
107C
Air vacuum relief valve on well discharge piping has at least 6 inches of clearance
above floor
SIG | 25pts | SO | S030 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be at least 6
inches above the well house floor. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
108 Wells that pump directly into a distribution system have means to release trapped air
from pump discharge piping (for example, pumps directly to a tank, has an air release
valve or pump to waste line)
MIN | 5pts | SO | SL01 | R309-515-6(12)(d)(v) | Rule requires a well that pumps
directly into the distribution system be equipped with an air release/vacuum relief valve
located upstream of the check valve, unless the wellhead valve and piping provide for
pumping to waste all trapped air before water is introduced into the distribution
system.
C
109 Does well require oil-lubrication?Y
109A
Well shaft lubricants ANSI/NSF 60 certified
SIG | 25pts | SO | S031 | R309-105-10(7), R309-515-6(6)(a) | Rules require all oil-
lubricated pumps for drinking water wells to utilize food-grade mineral oil suitable for
human consumption as determined by the Director. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
<a href="https://www.youtube.com/watch?v=UABQMeeUz1g">Click here for addition
training</a>
C
110 Is this facility Active or Inactive?I
110A
Explain why this facility is Inactive (Is this facility in stand-by mode?)stand-by mode
111 Operating Period (Start Date)01/01
112 Operating Period (Ending Date)12/30
113 Undocumented sources shall not be physically connected to the drinking water
system. (IF SOURCE IS NOT IN SYSTEM INVENTORY MARK "DEFICIENT")
SIG | 200pts | SO | S001 | R309-515-6(5), R309-515-7(4), R309-500-9(2) and (3) |
R309-105-6(1) requires plans and specifications for all public drinking water projects to
be approved in writing by the Director prior to the commencement of construction. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
114 Well casing is at least 18 inches above finished ground surface and 12 inches above
well house floor.
SIG | 25pts | SO | S003 | R309-515-6(6)(b)(vi), R309-515-6(12)(c)(ii), R309-515-
6(13)(a) | Rule requires the permanent well casing to project at least 18 inches above
the final ground surface and 12 inches above the pump house floor; at sites subject to
flooding, the top of the casing must terminate at least 3 feet above the 100-year flood
level or highest known flood elevation, whichever is higher. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 17 of 97
115 Wellhead is sealed to prevent contamination.
SIG | 50pts | SO | S013 | R309-515-6(6)(i) | R309-515-6(6)(i) and R309-515-
6(12)(b,c,d)require a sanitary seal be installed and maintained at the wellhead and
discharge piping. This significant deficiency should be corrected within 120 days of
notification or have a corrective action plan approved by
C
116 Is the well casing vented? ... if yes, answer the following question(s)Y
116A
Vent screened with #14 mesh screen
SIG | 25pts | SO | S006 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(a)require vents be fitted with a #14 mesh or finer non-corrodible screen.
C
116B
Vent down-turned
SIG | 25pts | SO | S007 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(b) requires vents be downturned or shielded to prevent the entrance of
surface water or rainwater.
C
116C
Vent has adequate clearance to prevent contamination from entering the well
SIG | 25pts | SO | S008 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(b) requires vents be terminated with a discharge with an appropriate air gap.
C
117 Does the well have a pump to waste line? ... if yes, answer the following question(s)Y
117A
Pump to waste line discharges with a minimum of 12-inch clearance to flood rim
SIG | 25pts | SO | S009 | R309-515-6(12)(d)(ix) | Rule requires a pump-to-waste line
connected to a sewer/storm drain to have a minimum 12-inch clearance to the flood
rim. This significant deficiency must be corrected within 120 days of notification or
have a corrective action plan approved by DDW.
C
117B
Pump to waste line equipped with #4 non-corrodible mesh screen
SIG | 25pts | SO | S010 | R309-515-6(12)(d)(ix) | The discharge end of the pump-to-
waste line shall be covered with a No. 4 mesh corrosion-resistant screen. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
117C
Pump to waste line downturned if it discharges to sewer/storm drain or allowing
complete drainage if not downturned
SIG | 25pts | SO | S011 | R309-515-6(12)(d)(ix) | The discharge end of the pump-to-
waste line shall be downturned. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
118 Provisions available to periodically measure water levels
MIN | 5pts | SO | S015 | R309-515-6(12)(e ), R309-515-6(12)(c)(vi) | Rule requires
provisions be made to permit periodic measurement of water levels in the completed
well.
C
119 Wellhead secured to protect quality water
SIG | 25pts | SO | S002 | R309-105-10(5) | All water system facilities shall be secure.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 18 of 97
120 Well head or well house and equipment protected from flooding
SIG | 25pts | SO | S020 | R309-515-6(6)(b)(vi), R309-515-6(12)(d)(iii), R309-515-
6(13)(a) to (d) | Top of well casing shall terminate at least 18” above ground level or
12” above well house floor and for sites that flood at least 3’ above 100-year flood
level or highest known flood elevation. Well casing terminating in underground vault
shall have a drain to daylight and surface runoff directed away from vault access. Well
house floor shall be sloped for drainage, and have a drain to daylight unless highly
impractical. This significant deficiency must be corrected within 120 days of notification
or have a corrective action plan approved by DDW.
C
121 There are no unprotected cross-connections in well discharge piping.
SIG | 50pts | SO | S021 | R309-105-12(1), R309-515-6(12)(d)(iii) | Rule requires the
well discharge piping to be protected against the entrance of contamination. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
122 No toxic chemicals, hazardous or flammable materials, or lubricants inside the well
house or near well head?
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
123 Well discharge line has a smooth-nosed sampling tap, which samples the well water
before any chemical injection. (first item from the wellhead).
MIN | 5pts | SO | S023 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with a smooth nosed sampling tap, a check valve, a pressure gauge, a
means of measuring flow, and a shutoff valve. (smooth nosed sampling tap being the
first item from the well head and the shut-off valve as the last item)
C
124 Well discharge line has a check valve.
MIN | 5pts | SO | S024 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
125 Well discharge line has a pressure gauge.
MIN | 5pts | SO | S025 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
126 Well discharge line has a means to measure flow.
MIN | 5pts | SO | S026 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
127 Well discharge line has a shut-off valve (last item from the well head).
MIN | 5pts | SO | S027 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
128 Is there an air/vac valve on the well discharge line? If yes, answer the following
question(s)
Y
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 19 of 97
WS005 - WHITE PINE WELL - Active
128A
Air vacuum relief valve on well discharge piping downturned
SIG | 25pts | SO | S028 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be down-turned.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
128B
Air vacuum relief valve on well discharge piping screened with #14 mesh screen
SIG | 25pts | SO | S029 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be covered with a
#14 mesh corrosion-resistant screen. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
128C
Air vacuum relief valve on well discharge piping has at least 6 inches of clearance
above floor
SIG | 25pts | SO | S030 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be at least 6
inches above the well house floor. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
129 Wells that pump directly into a distribution system have means to release trapped air
from pump discharge piping (for example, pumps directly to a tank, has an air release
valve or pump to waste line)
MIN | 5pts | SO | SL01 | R309-515-6(12)(d)(v) | Rule requires a well that pumps
directly into the distribution system be equipped with an air release/vacuum relief valve
located upstream of the check valve, unless the wellhead valve and piping provide for
pumping to waste all trapped air before water is introduced into the distribution
system.
C
130 Does well require oil-lubrication?Y
130A
Well shaft lubricants ANSI/NSF 60 certified
SIG | 25pts | SO | S031 | R309-105-10(7), R309-515-6(6)(a) | Rules require all oil-
lubricated pumps for drinking water wells to utilize food-grade mineral oil suitable for
human consumption as determined by the Director. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
<a href="https://www.youtube.com/watch?v=UABQMeeUz1g">Click here for addition
training</a>
C
131 Is this facility Active or Inactive?A
132 Operating Period (Start Date)01/01
133 Operating Period (Ending Date)12/31
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 20 of 97
134 Undocumented sources shall not be physically connected to the drinking water
system. (IF SOURCE IS NOT IN SYSTEM INVENTORY MARK "DEFICIENT")
SIG | 200pts | SO | S001 | R309-515-6(5), R309-515-7(4), R309-500-9(2) and (3) |
R309-105-6(1) requires plans and specifications for all public drinking water projects to
be approved in writing by the Director prior to the commencement of construction. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
135 Well casing is at least 18 inches above finished ground surface and 12 inches above
well house floor.
SIG | 25pts | SO | S003 | R309-515-6(6)(b)(vi), R309-515-6(12)(c)(ii), R309-515-
6(13)(a) | Rule requires the permanent well casing to project at least 18 inches above
the final ground surface and 12 inches above the pump house floor; at sites subject to
flooding, the top of the casing must terminate at least 3 feet above the 100-year flood
level or highest known flood elevation, whichever is higher. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
136 Wellhead is sealed to prevent contamination.
SIG | 50pts | SO | S013 | R309-515-6(6)(i) | R309-515-6(6)(i) and R309-515-
6(12)(b,c,d)require a sanitary seal be installed and maintained at the wellhead and
discharge piping. This significant deficiency should be corrected within 120 days of
notification or have a corrective action plan approved by
C
137 Is the well casing vented? ... if yes, answer the following question(s)Y
137A
Vent screened with #14 mesh screen
SIG | 25pts | SO | S006 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(a)require vents be fitted with a #14 mesh or finer non-corrodible screen.
C
137B
Vent down-turned
SIG | 25pts | SO | S007 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(b) requires vents be downturned or shielded to prevent the entrance of
surface water or rainwater.
C
137C
Vent has adequate clearance to prevent contamination from entering the well
SIG | 25pts | SO | S008 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(b) requires vents be terminated with a discharge with an appropriate air gap.
C
138 Does the well have a pump to waste line? ... if yes, answer the following question(s)Y
138A
Pump to waste line discharges with a minimum of 12-inch clearance to flood rim
SIG | 25pts | SO | S009 | R309-515-6(12)(d)(ix) | Rule requires a pump-to-waste line
connected to a sewer/storm drain to have a minimum 12-inch clearance to the flood
rim. This significant deficiency must be corrected within 120 days of notification or
have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 21 of 97
138B
Pump to waste line equipped with #4 non-corrodible mesh screen
SIG | 25pts | SO | S010 | R309-515-6(12)(d)(ix) | The discharge end of the pump-to-
waste line shall be covered with a No. 4 mesh corrosion-resistant screen. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
138C
Pump to waste line downturned if it discharges to sewer/storm drain or allowing
complete drainage if not downturned
SIG | 25pts | SO | S011 | R309-515-6(12)(d)(ix) | The discharge end of the pump-to-
waste line shall be downturned. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
139 Provisions available to periodically measure water levels
MIN | 5pts | SO | S015 | R309-515-6(12)(e ), R309-515-6(12)(c)(vi) | Rule requires
provisions be made to permit periodic measurement of water levels in the completed
well.
C
140 Wellhead secured to protect quality water
SIG | 25pts | SO | S002 | R309-105-10(5) | All water system facilities shall be secure.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
141 Well head or well house and equipment protected from flooding
SIG | 25pts | SO | S020 | R309-515-6(6)(b)(vi), R309-515-6(12)(d)(iii), R309-515-
6(13)(a) to (d) | Top of well casing shall terminate at least 18” above ground level or
12” above well house floor and for sites that flood at least 3’ above 100-year flood
level or highest known flood elevation. Well casing terminating in underground vault
shall have a drain to daylight and surface runoff directed away from vault access. Well
house floor shall be sloped for drainage, and have a drain to daylight unless highly
impractical. This significant deficiency must be corrected within 120 days of notification
or have a corrective action plan approved by DDW.
C
142 There are no unprotected cross-connections in well discharge piping.
SIG | 50pts | SO | S021 | R309-105-12(1), R309-515-6(12)(d)(iii) | Rule requires the
well discharge piping to be protected against the entrance of contamination. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
143 No toxic chemicals, hazardous or flammable materials, or lubricants inside the well
house or near well head?
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
144 Well discharge line has a smooth-nosed sampling tap, which samples the well water
before any chemical injection. (first item from the wellhead).
MIN | 5pts | SO | S023 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with a smooth nosed sampling tap, a check valve, a pressure gauge, a
means of measuring flow, and a shutoff valve. (smooth nosed sampling tap being the
first item from the well head and the shut-off valve as the last item)
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 22 of 97
WS006 - CHURCH WELL - Active
145 Well discharge line has a check valve.
MIN | 5pts | SO | S024 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
146 Well discharge line has a pressure gauge.
MIN | 5pts | SO | S025 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
147 Well discharge line has a means to measure flow.
MIN | 5pts | SO | S026 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
148 Well discharge line has a shut-off valve (last item from the well head).
MIN | 5pts | SO | S027 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
149 Is there an air/vac valve on the well discharge line? If yes, answer the following
question(s)
Y
149A
Air vacuum relief valve on well discharge piping downturned
SIG | 25pts | SO | S028 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be down-turned.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
149B
Air vacuum relief valve on well discharge piping screened with #14 mesh screen
SIG | 25pts | SO | S029 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be covered with a
#14 mesh corrosion-resistant screen. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
149C
Air vacuum relief valve on well discharge piping has at least 6 inches of clearance
above floor
SIG | 25pts | SO | S030 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be at least 6
inches above the well house floor. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
150 Wells that pump directly into a distribution system have means to release trapped air
from pump discharge piping (for example, pumps directly to a tank, has an air release
valve or pump to waste line)
MIN | 5pts | SO | SL01 | R309-515-6(12)(d)(v) | Rule requires a well that pumps
directly into the distribution system be equipped with an air release/vacuum relief valve
located upstream of the check valve, unless the wellhead valve and piping provide for
pumping to waste all trapped air before water is introduced into the distribution
system.
C
151 Does well require oil-lubrication?N
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 23 of 97
152 Is this facility Active or Inactive?A
153 Operating Period (Start Date)01/01
154 Operating Period (Ending Date)12/31
155 Undocumented sources shall not be physically connected to the drinking water
system. (IF SOURCE IS NOT IN SYSTEM INVENTORY MARK "DEFICIENT")
SIG | 200pts | SO | S001 | R309-515-6(5), R309-515-7(4), R309-500-9(2) and (3) |
R309-105-6(1) requires plans and specifications for all public drinking water projects to
be approved in writing by the Director prior to the commencement of construction. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
156 Well casing is at least 18 inches above finished ground surface and 12 inches above
well house floor.
SIG | 25pts | SO | S003 | R309-515-6(6)(b)(vi), R309-515-6(12)(c)(ii), R309-515-
6(13)(a) | Rule requires the permanent well casing to project at least 18 inches above
the final ground surface and 12 inches above the pump house floor; at sites subject to
flooding, the top of the casing must terminate at least 3 feet above the 100-year flood
level or highest known flood elevation, whichever is higher. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
157 Wellhead is sealed to prevent contamination.
SIG | 50pts | SO | S013 | R309-515-6(6)(i) | R309-515-6(6)(i) and R309-515-
6(12)(b,c,d)require a sanitary seal be installed and maintained at the wellhead and
discharge piping. This significant deficiency should be corrected within 120 days of
notification or have a corrective action plan approved by
C
158 Is the well casing vented? ... if yes, answer the following question(s)Y
158A
Vent screened with #14 mesh screen
SIG | 25pts | SO | S006 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(a)require vents be fitted with a #14 mesh or finer non-corrodible screen.
C
158B
Vent down-turned
SIG | 25pts | SO | S007 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(b) requires vents be downturned or shielded to prevent the entrance of
surface water or rainwater.
C
158C
Vent has adequate clearance to prevent contamination from entering the well
SIG | 25pts | SO | S008 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(b) requires vents be terminated with a discharge with an appropriate air gap.
C
159 Does the well have a pump to waste line? ... if yes, answer the following question(s)Y
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 24 of 97
159A
Pump to waste line discharges with a minimum of 12-inch clearance to flood rim
SIG | 25pts | SO | S009 | R309-515-6(12)(d)(ix) | Rule requires a pump-to-waste line
connected to a sewer/storm drain to have a minimum 12-inch clearance to the flood
rim. This significant deficiency must be corrected within 120 days of notification or
have a corrective action plan approved by DDW.
C
159B
Pump to waste line equipped with #4 non-corrodible mesh screen
SIG | 25pts | SO | S010 | R309-515-6(12)(d)(ix) | The discharge end of the pump-to-
waste line shall be covered with a No. 4 mesh corrosion-resistant screen. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
159C
Pump to waste line downturned if it discharges to sewer/storm drain or allowing
complete drainage if not downturned
SIG | 25pts | SO | S011 | R309-515-6(12)(d)(ix) | The discharge end of the pump-to-
waste line shall be downturned. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
160 Provisions available to periodically measure water levels
MIN | 5pts | SO | S015 | R309-515-6(12)(e ), R309-515-6(12)(c)(vi) | Rule requires
provisions be made to permit periodic measurement of water levels in the completed
well.
C
161 Wellhead secured to protect quality water
SIG | 25pts | SO | S002 | R309-105-10(5) | All water system facilities shall be secure.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
162 Well head or well house and equipment protected from flooding
SIG | 25pts | SO | S020 | R309-515-6(6)(b)(vi), R309-515-6(12)(d)(iii), R309-515-
6(13)(a) to (d) | Top of well casing shall terminate at least 18” above ground level or
12” above well house floor and for sites that flood at least 3’ above 100-year flood
level or highest known flood elevation. Well casing terminating in underground vault
shall have a drain to daylight and surface runoff directed away from vault access. Well
house floor shall be sloped for drainage, and have a drain to daylight unless highly
impractical. This significant deficiency must be corrected within 120 days of notification
or have a corrective action plan approved by DDW.
C
163 There are no unprotected cross-connections in well discharge piping.
SIG | 50pts | SO | S021 | R309-105-12(1), R309-515-6(12)(d)(iii) | Rule requires the
well discharge piping to be protected against the entrance of contamination. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
164 No toxic chemicals, hazardous or flammable materials, or lubricants inside the well
house or near well head?
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 25 of 97
165 Well discharge line has a smooth-nosed sampling tap, which samples the well water
before any chemical injection. (first item from the wellhead).
MIN | 5pts | SO | S023 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with a smooth nosed sampling tap, a check valve, a pressure gauge, a
means of measuring flow, and a shutoff valve. (smooth nosed sampling tap being the
first item from the well head and the shut-off valve as the last item)
C
166 Well discharge line has a check valve.
MIN | 5pts | SO | S024 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
167 Well discharge line has a pressure gauge.
MIN | 5pts | SO | S025 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
168 Well discharge line has a means to measure flow.
MIN | 5pts | SO | S026 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
169 Well discharge line has a shut-off valve (last item from the well head).
MIN | 5pts | SO | S027 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
170 Is there an air/vac valve on the well discharge line? If yes, answer the following
question(s)
Y
170A
Air vacuum relief valve on well discharge piping downturned
SIG | 25pts | SO | S028 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be down-turned.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
170B
Air vacuum relief valve on well discharge piping screened with #14 mesh screen
SIG | 25pts | SO | S029 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be covered with a
#14 mesh corrosion-resistant screen. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
170C
Air vacuum relief valve on well discharge piping has at least 6 inches of clearance
above floor
SIG | 25pts | SO | S030 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be at least 6
inches above the well house floor. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 26 of 97
WS007 - STORAGE WELL -
171 Wells that pump directly into a distribution system have means to release trapped air
from pump discharge piping (for example, pumps directly to a tank, has an air release
valve or pump to waste line)
MIN | 5pts | SO | SL01 | R309-515-6(12)(d)(v) | Rule requires a well that pumps
directly into the distribution system be equipped with an air release/vacuum relief valve
located upstream of the check valve, unless the wellhead valve and piping provide for
pumping to waste all trapped air before water is introduced into the distribution
system.
C
172 Does well require oil-lubrication?Y
172A
Well shaft lubricants ANSI/NSF 60 certified
SIG | 25pts | SO | S031 | R309-105-10(7), R309-515-6(6)(a) | Rules require all oil-
lubricated pumps for drinking water wells to utilize food-grade mineral oil suitable for
human consumption as determined by the Director. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
<a href="https://www.youtube.com/watch?v=UABQMeeUz1g">Click here for addition
training</a>
C
173 Is this facility Active or Inactive?I
173A
Explain why this facility is Inactive (Is this facility in stand-by mode?)stand-by mode
174 Operating Period (Start Date)01/01
175 Operating Period (Ending Date)12/31
176 Undocumented sources shall not be physically connected to the drinking water
system. (IF SOURCE IS NOT IN SYSTEM INVENTORY MARK "DEFICIENT")
SIG | 200pts | SO | S001 | R309-515-6(5), R309-515-7(4), R309-500-9(2) and (3) |
R309-105-6(1) requires plans and specifications for all public drinking water projects to
be approved in writing by the Director prior to the commencement of construction. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
177 Well casing is at least 18 inches above finished ground surface and 12 inches above
well house floor.
SIG | 25pts | SO | S003 | R309-515-6(6)(b)(vi), R309-515-6(12)(c)(ii), R309-515-
6(13)(a) | Rule requires the permanent well casing to project at least 18 inches above
the final ground surface and 12 inches above the pump house floor; at sites subject to
flooding, the top of the casing must terminate at least 3 feet above the 100-year flood
level or highest known flood elevation, whichever is higher. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
178 Wellhead is sealed to prevent contamination.
SIG | 50pts | SO | S013 | R309-515-6(6)(i) | R309-515-6(6)(i) and R309-515-
6(12)(b,c,d)require a sanitary seal be installed and maintained at the wellhead and
discharge piping. This significant deficiency should be corrected within 120 days of
notification or have a corrective action plan approved by
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 27 of 97
179 Is the well casing vented? ... if yes, answer the following question(s)Y
179A
Vent screened with #14 mesh screen
SIG | 25pts | SO | S006 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(a)require vents be fitted with a #14 mesh or finer non-corrodible screen.
C
179B
Vent down-turned
SIG | 25pts | SO | S007 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(b) requires vents be downturned or shielded to prevent the entrance of
surface water or rainwater.
C
179C
Vent has adequate clearance to prevent contamination from entering the well
SIG | 25pts | SO | S008 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(b) requires vents be terminated with a discharge with an appropriate air gap.
C
180 Does the well have a pump to waste line? ... if yes, answer the following question(s)Y
180A
Pump to waste line discharges with a minimum of 12-inch clearance to flood rim
SIG | 25pts | SO | S009 | R309-515-6(12)(d)(ix) | Rule requires a pump-to-waste line
connected to a sewer/storm drain to have a minimum 12-inch clearance to the flood
rim. This significant deficiency must be corrected within 120 days of notification or
have a corrective action plan approved by DDW.
C
180B
Pump to waste line equipped with #4 non-corrodible mesh screen
SIG | 25pts | SO | S010 | R309-515-6(12)(d)(ix) | The discharge end of the pump-to-
waste line shall be covered with a No. 4 mesh corrosion-resistant screen. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
180C
Pump to waste line downturned if it discharges to sewer/storm drain or allowing
complete drainage if not downturned
SIG | 25pts | SO | S011 | R309-515-6(12)(d)(ix) | The discharge end of the pump-to-
waste line shall be downturned. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
181 Provisions available to periodically measure water levels
MIN | 5pts | SO | S015 | R309-515-6(12)(e ), R309-515-6(12)(c)(vi) | Rule requires
provisions be made to permit periodic measurement of water levels in the completed
well.
C
182 Wellhead secured to protect quality water
SIG | 25pts | SO | S002 | R309-105-10(5) | All water system facilities shall be secure.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 28 of 97
183 Well head or well house and equipment protected from flooding
SIG | 25pts | SO | S020 | R309-515-6(6)(b)(vi), R309-515-6(12)(d)(iii), R309-515-
6(13)(a) to (d) | Top of well casing shall terminate at least 18” above ground level or
12” above well house floor and for sites that flood at least 3’ above 100-year flood
level or highest known flood elevation. Well casing terminating in underground vault
shall have a drain to daylight and surface runoff directed away from vault access. Well
house floor shall be sloped for drainage, and have a drain to daylight unless highly
impractical. This significant deficiency must be corrected within 120 days of notification
or have a corrective action plan approved by DDW.
C
184 There are no unprotected cross-connections in well discharge piping.
SIG | 50pts | SO | S021 | R309-105-12(1), R309-515-6(12)(d)(iii) | Rule requires the
well discharge piping to be protected against the entrance of contamination. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
185 No toxic chemicals, hazardous or flammable materials, or lubricants inside the well
house or near well head?
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
186 Well discharge line has a smooth-nosed sampling tap, which samples the well water
before any chemical injection. (first item from the wellhead).
MIN | 5pts | SO | S023 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with a smooth nosed sampling tap, a check valve, a pressure gauge, a
means of measuring flow, and a shutoff valve. (smooth nosed sampling tap being the
first item from the well head and the shut-off valve as the last item)
C
187 Well discharge line has a check valve.
MIN | 5pts | SO | S024 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
188 Well discharge line has a pressure gauge.
MIN | 5pts | SO | S025 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
189 Well discharge line has a means to measure flow.
MIN | 5pts | SO | S026 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
190 Well discharge line has a shut-off valve (last item from the well head).
MIN | 5pts | SO | S027 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
191 Is there an air/vac valve on the well discharge line? If yes, answer the following
question(s)
Y
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 29 of 97
WS008 - OLD F-7 WELL - Active
191A
Air vacuum relief valve on well discharge piping downturned
SIG | 25pts | SO | S028 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be down-turned.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
191B
Air vacuum relief valve on well discharge piping screened with #14 mesh screen
SIG | 25pts | SO | S029 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be covered with a
#14 mesh corrosion-resistant screen. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
191C
Air vacuum relief valve on well discharge piping has at least 6 inches of clearance
above floor
SIG | 25pts | SO | S030 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be at least 6
inches above the well house floor. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
192 Wells that pump directly into a distribution system have means to release trapped air
from pump discharge piping (for example, pumps directly to a tank, has an air release
valve or pump to waste line)
MIN | 5pts | SO | SL01 | R309-515-6(12)(d)(v) | Rule requires a well that pumps
directly into the distribution system be equipped with an air release/vacuum relief valve
located upstream of the check valve, unless the wellhead valve and piping provide for
pumping to waste all trapped air before water is introduced into the distribution
system.
C
193 Does well require oil-lubrication?Y
193A
Well shaft lubricants ANSI/NSF 60 certified
SIG | 25pts | SO | S031 | R309-105-10(7), R309-515-6(6)(a) | Rules require all oil-
lubricated pumps for drinking water wells to utilize food-grade mineral oil suitable for
human consumption as determined by the Director. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
<a href="https://www.youtube.com/watch?v=UABQMeeUz1g">Click here for addition
training</a>
C
194 Is this facility Active or Inactive?A
195 Operating Period (Start Date)01/01
196 Operating Period (Ending Date)12/31
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 30 of 97
197 Undocumented sources shall not be physically connected to the drinking water
system. (IF SOURCE IS NOT IN SYSTEM INVENTORY MARK "DEFICIENT")
SIG | 200pts | SO | S001 | R309-515-6(5), R309-515-7(4), R309-500-9(2) and (3) |
R309-105-6(1) requires plans and specifications for all public drinking water projects to
be approved in writing by the Director prior to the commencement of construction. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
198 Well casing is at least 18 inches above finished ground surface and 12 inches above
well house floor.
SIG | 25pts | SO | S003 | R309-515-6(6)(b)(vi), R309-515-6(12)(c)(ii), R309-515-
6(13)(a) | Rule requires the permanent well casing to project at least 18 inches above
the final ground surface and 12 inches above the pump house floor; at sites subject to
flooding, the top of the casing must terminate at least 3 feet above the 100-year flood
level or highest known flood elevation, whichever is higher. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
199 Wellhead is sealed to prevent contamination.
SIG | 50pts | SO | S013 | R309-515-6(6)(i) | R309-515-6(6)(i) and R309-515-
6(12)(b,c,d)require a sanitary seal be installed and maintained at the wellhead and
discharge piping. This significant deficiency should be corrected within 120 days of
notification or have a corrective action plan approved by
C
200 Is the well casing vented? ... if yes, answer the following question(s)Y
200A
Vent screened with #14 mesh screen
SIG | 25pts | SO | S006 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(a)require vents be fitted with a #14 mesh or finer non-corrodible screen.
C
200B
Vent down-turned
SIG | 25pts | SO | S007 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(b) requires vents be downturned or shielded to prevent the entrance of
surface water or rainwater.
C
200C
Vent has adequate clearance to prevent contamination from entering the well
SIG | 25pts | SO | S008 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(b) requires vents be terminated with a discharge with an appropriate air gap.
C
201 Does the well have a pump to waste line? ... if yes, answer the following question(s)Y
201A
Pump to waste line discharges with a minimum of 12-inch clearance to flood rim
SIG | 25pts | SO | S009 | R309-515-6(12)(d)(ix) | Rule requires a pump-to-waste line
connected to a sewer/storm drain to have a minimum 12-inch clearance to the flood
rim. This significant deficiency must be corrected within 120 days of notification or
have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 31 of 97
201B
Pump to waste line equipped with #4 non-corrodible mesh screen
SIG | 25pts | SO | S010 | R309-515-6(12)(d)(ix) | The discharge end of the pump-to-
waste line shall be covered with a No. 4 mesh corrosion-resistant screen. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
201C
Pump to waste line downturned if it discharges to sewer/storm drain or allowing
complete drainage if not downturned
SIG | 25pts | SO | S011 | R309-515-6(12)(d)(ix) | The discharge end of the pump-to-
waste line shall be downturned. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
202 Provisions available to periodically measure water levels
MIN | 5pts | SO | S015 | R309-515-6(12)(e ), R309-515-6(12)(c)(vi) | Rule requires
provisions be made to permit periodic measurement of water levels in the completed
well.
C
203 Wellhead secured to protect quality water
SIG | 25pts | SO | S002 | R309-105-10(5) | All water system facilities shall be secure.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
204 Well head or well house and equipment protected from flooding
SIG | 25pts | SO | S020 | R309-515-6(6)(b)(vi), R309-515-6(12)(d)(iii), R309-515-
6(13)(a) to (d) | Top of well casing shall terminate at least 18” above ground level or
12” above well house floor and for sites that flood at least 3’ above 100-year flood
level or highest known flood elevation. Well casing terminating in underground vault
shall have a drain to daylight and surface runoff directed away from vault access. Well
house floor shall be sloped for drainage, and have a drain to daylight unless highly
impractical. This significant deficiency must be corrected within 120 days of notification
or have a corrective action plan approved by DDW.
C
205 There are no unprotected cross-connections in well discharge piping.
SIG | 50pts | SO | S021 | R309-105-12(1), R309-515-6(12)(d)(iii) | Rule requires the
well discharge piping to be protected against the entrance of contamination. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
206 No toxic chemicals, hazardous or flammable materials, or lubricants inside the well
house or near well head?
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
207 Well discharge line has a smooth-nosed sampling tap, which samples the well water
before any chemical injection. (first item from the wellhead).
MIN | 5pts | SO | S023 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with a smooth nosed sampling tap, a check valve, a pressure gauge, a
means of measuring flow, and a shutoff valve. (smooth nosed sampling tap being the
first item from the well head and the shut-off valve as the last item)
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 32 of 97
WS009 - U224 WELL - Active
208 Well discharge line has a check valve.
MIN | 5pts | SO | S024 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
209 Well discharge line has a pressure gauge.
MIN | 5pts | SO | S025 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
210 Well discharge line has a means to measure flow.
MIN | 5pts | SO | S026 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
211 Well discharge line has a shut-off valve (last item from the well head).
MIN | 5pts | SO | S027 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
212 Is there an air/vac valve on the well discharge line? If yes, answer the following
question(s)
Y
212A
Air vacuum relief valve on well discharge piping downturned
SIG | 25pts | SO | S028 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be down-turned.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
212B
Air vacuum relief valve on well discharge piping screened with #14 mesh screen
SIG | 25pts | SO | S029 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be covered with a
#14 mesh corrosion-resistant screen. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
212C
Air vacuum relief valve on well discharge piping has at least 6 inches of clearance
above floor
SIG | 25pts | SO | S030 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be at least 6
inches above the well house floor. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
213 Wells that pump directly into a distribution system have means to release trapped air
from pump discharge piping (for example, pumps directly to a tank, has an air release
valve or pump to waste line)
MIN | 5pts | SO | SL01 | R309-515-6(12)(d)(v) | Rule requires a well that pumps
directly into the distribution system be equipped with an air release/vacuum relief valve
located upstream of the check valve, unless the wellhead valve and piping provide for
pumping to waste all trapped air before water is introduced into the distribution
system.
C
214 Does well require oil-lubrication?N
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 33 of 97
215 Is this facility Active or Inactive?A
216 Operating Period (Start Date)01/01
217 Operating Period (Ending Date)12/31
218 Undocumented sources shall not be physically connected to the drinking water
system. (IF SOURCE IS NOT IN SYSTEM INVENTORY MARK "DEFICIENT")
SIG | 200pts | SO | S001 | R309-515-6(5), R309-515-7(4), R309-500-9(2) and (3) |
R309-105-6(1) requires plans and specifications for all public drinking water projects to
be approved in writing by the Director prior to the commencement of construction. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
219 Well casing is at least 18 inches above finished ground surface and 12 inches above
well house floor.
SIG | 25pts | SO | S003 | R309-515-6(6)(b)(vi), R309-515-6(12)(c)(ii), R309-515-
6(13)(a) | Rule requires the permanent well casing to project at least 18 inches above
the final ground surface and 12 inches above the pump house floor; at sites subject to
flooding, the top of the casing must terminate at least 3 feet above the 100-year flood
level or highest known flood elevation, whichever is higher. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
220 Wellhead is sealed to prevent contamination.
SIG | 50pts | SO | S013 | R309-515-6(6)(i) | R309-515-6(6)(i) and R309-515-
6(12)(b,c,d)require a sanitary seal be installed and maintained at the wellhead and
discharge piping. This significant deficiency should be corrected within 120 days of
notification or have a corrective action plan approved by
C
221 Is the well casing vented? ... if yes, answer the following question(s)Y
221A
Vent screened with #14 mesh screen
SIG | 25pts | SO | S006 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(a)require vents be fitted with a #14 mesh or finer non-corrodible screen.
C
221B
Vent down-turned
SIG | 25pts | SO | S007 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(b) requires vents be downturned or shielded to prevent the entrance of
surface water or rainwater.
C
221C
Vent has adequate clearance to prevent contamination from entering the well
SIG | 25pts | SO | S008 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(b) requires vents be terminated with a discharge with an appropriate air gap.
C
222 Does the well have a pump to waste line? ... if yes, answer the following question(s)Y
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 34 of 97
222A
Pump to waste line discharges with a minimum of 12-inch clearance to flood rim
SIG | 25pts | SO | S009 | R309-515-6(12)(d)(ix) | Rule requires a pump-to-waste line
connected to a sewer/storm drain to have a minimum 12-inch clearance to the flood
rim. This significant deficiency must be corrected within 120 days of notification or
have a corrective action plan approved by DDW.
C
222B
Pump to waste line equipped with #4 non-corrodible mesh screen
SIG | 25pts | SO | S010 | R309-515-6(12)(d)(ix) | The discharge end of the pump-to-
waste line shall be covered with a No. 4 mesh corrosion-resistant screen. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
222C
Pump to waste line downturned if it discharges to sewer/storm drain or allowing
complete drainage if not downturned
SIG | 25pts | SO | S011 | R309-515-6(12)(d)(ix) | The discharge end of the pump-to-
waste line shall be downturned. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
223 Provisions available to periodically measure water levels
MIN | 5pts | SO | S015 | R309-515-6(12)(e ), R309-515-6(12)(c)(vi) | Rule requires
provisions be made to permit periodic measurement of water levels in the completed
well.
C
224 Wellhead secured to protect quality water
SIG | 25pts | SO | S002 | R309-105-10(5) | All water system facilities shall be secure.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
225 Well head or well house and equipment protected from flooding
SIG | 25pts | SO | S020 | R309-515-6(6)(b)(vi), R309-515-6(12)(d)(iii), R309-515-
6(13)(a) to (d) | Top of well casing shall terminate at least 18” above ground level or
12” above well house floor and for sites that flood at least 3’ above 100-year flood
level or highest known flood elevation. Well casing terminating in underground vault
shall have a drain to daylight and surface runoff directed away from vault access. Well
house floor shall be sloped for drainage, and have a drain to daylight unless highly
impractical. This significant deficiency must be corrected within 120 days of notification
or have a corrective action plan approved by DDW.
C
226 There are no unprotected cross-connections in well discharge piping.
SIG | 50pts | SO | S021 | R309-105-12(1), R309-515-6(12)(d)(iii) | Rule requires the
well discharge piping to be protected against the entrance of contamination. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
227 No toxic chemicals, hazardous or flammable materials, or lubricants inside the well
house or near well head?
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 35 of 97
228 Well discharge line has a smooth-nosed sampling tap, which samples the well water
before any chemical injection. (first item from the wellhead).
MIN | 5pts | SO | S023 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with a smooth nosed sampling tap, a check valve, a pressure gauge, a
means of measuring flow, and a shutoff valve. (smooth nosed sampling tap being the
first item from the well head and the shut-off valve as the last item)
C
229 Well discharge line has a check valve.
MIN | 5pts | SO | S024 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
230 Well discharge line has a pressure gauge.
MIN | 5pts | SO | S025 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
231 Well discharge line has a means to measure flow.
MIN | 5pts | SO | S026 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
232 Well discharge line has a shut-off valve (last item from the well head).
MIN | 5pts | SO | S027 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
233 Is there an air/vac valve on the well discharge line? If yes, answer the following
question(s)
Y
233A
Air vacuum relief valve on well discharge piping downturned
SIG | 25pts | SO | S028 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be down-turned.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
233B
Air vacuum relief valve on well discharge piping screened with #14 mesh screen
SIG | 25pts | SO | S029 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be covered with a
#14 mesh corrosion-resistant screen. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
233C
Air vacuum relief valve on well discharge piping has at least 6 inches of clearance
above floor
SIG | 25pts | SO | S030 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be at least 6
inches above the well house floor. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 36 of 97
WS012 - NEW F-7 WELL - Active
234 Wells that pump directly into a distribution system have means to release trapped air
from pump discharge piping (for example, pumps directly to a tank, has an air release
valve or pump to waste line)
MIN | 5pts | SO | SL01 | R309-515-6(12)(d)(v) | Rule requires a well that pumps
directly into the distribution system be equipped with an air release/vacuum relief valve
located upstream of the check valve, unless the wellhead valve and piping provide for
pumping to waste all trapped air before water is introduced into the distribution
system.
C
235 Does well require oil-lubrication?Y
235A
Well shaft lubricants ANSI/NSF 60 certified
SIG | 25pts | SO | S031 | R309-105-10(7), R309-515-6(6)(a) | Rules require all oil-
lubricated pumps for drinking water wells to utilize food-grade mineral oil suitable for
human consumption as determined by the Director. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
<a href="https://www.youtube.com/watch?v=UABQMeeUz1g">Click here for addition
training</a>
C
236 Is this facility Active or Inactive?A
237 Operating Period (Start Date)01/01
238 Operating Period (Ending Date)12/31
239 Undocumented sources shall not be physically connected to the drinking water
system. (IF SOURCE IS NOT IN SYSTEM INVENTORY MARK "DEFICIENT")
SIG | 200pts | SO | S001 | R309-515-6(5), R309-515-7(4), R309-500-9(2) and (3) |
R309-105-6(1) requires plans and specifications for all public drinking water projects to
be approved in writing by the Director prior to the commencement of construction. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
240 Well casing is at least 18 inches above finished ground surface and 12 inches above
well house floor.
SIG | 25pts | SO | S003 | R309-515-6(6)(b)(vi), R309-515-6(12)(c)(ii), R309-515-
6(13)(a) | Rule requires the permanent well casing to project at least 18 inches above
the final ground surface and 12 inches above the pump house floor; at sites subject to
flooding, the top of the casing must terminate at least 3 feet above the 100-year flood
level or highest known flood elevation, whichever is higher. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
241 Wellhead is sealed to prevent contamination.
SIG | 50pts | SO | S013 | R309-515-6(6)(i) | R309-515-6(6)(i) and R309-515-
6(12)(b,c,d)require a sanitary seal be installed and maintained at the wellhead and
discharge piping. This significant deficiency should be corrected within 120 days of
notification or have a corrective action plan approved by
C
242 Is the well casing vented? ... if yes, answer the following question(s)Y
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 37 of 97
242A
Vent screened with #14 mesh screen
SIG | 25pts | SO | S006 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(a)require vents be fitted with a #14 mesh or finer non-corrodible screen.
C
242B
Vent down-turned
SIG | 25pts | SO | S007 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(b) requires vents be downturned or shielded to prevent the entrance of
surface water or rainwater.
C
242C
Vent has adequate clearance to prevent contamination from entering the well
SIG | 25pts | SO | S008 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(b) requires vents be terminated with a discharge with an appropriate air gap.
C
243 Does the well have a pump to waste line? ... if yes, answer the following question(s)Y
243A
Pump to waste line discharges with a minimum of 12-inch clearance to flood rim
SIG | 25pts | SO | S009 | R309-515-6(12)(d)(ix) | Rule requires a pump-to-waste line
connected to a sewer/storm drain to have a minimum 12-inch clearance to the flood
rim. This significant deficiency must be corrected within 120 days of notification or
have a corrective action plan approved by DDW.
C
243B
Pump to waste line equipped with #4 non-corrodible mesh screen
SIG | 25pts | SO | S010 | R309-515-6(12)(d)(ix) | The discharge end of the pump-to-
waste line shall be covered with a No. 4 mesh corrosion-resistant screen. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
243C
Pump to waste line downturned if it discharges to sewer/storm drain or allowing
complete drainage if not downturned
SIG | 25pts | SO | S011 | R309-515-6(12)(d)(ix) | The discharge end of the pump-to-
waste line shall be downturned. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
244 Provisions available to periodically measure water levels
MIN | 5pts | SO | S015 | R309-515-6(12)(e ), R309-515-6(12)(c)(vi) | Rule requires
provisions be made to permit periodic measurement of water levels in the completed
well.
C
245 Wellhead secured to protect quality water
SIG | 25pts | SO | S002 | R309-105-10(5) | All water system facilities shall be secure.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 38 of 97
246 Well head or well house and equipment protected from flooding
SIG | 25pts | SO | S020 | R309-515-6(6)(b)(vi), R309-515-6(12)(d)(iii), R309-515-
6(13)(a) to (d) | Top of well casing shall terminate at least 18” above ground level or
12” above well house floor and for sites that flood at least 3’ above 100-year flood
level or highest known flood elevation. Well casing terminating in underground vault
shall have a drain to daylight and surface runoff directed away from vault access. Well
house floor shall be sloped for drainage, and have a drain to daylight unless highly
impractical. This significant deficiency must be corrected within 120 days of notification
or have a corrective action plan approved by DDW.
C
247 There are no unprotected cross-connections in well discharge piping.
SIG | 50pts | SO | S021 | R309-105-12(1), R309-515-6(12)(d)(iii) | Rule requires the
well discharge piping to be protected against the entrance of contamination. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
248 No toxic chemicals, hazardous or flammable materials, or lubricants inside the well
house or near well head?
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
249 Well discharge line has a smooth-nosed sampling tap, which samples the well water
before any chemical injection. (first item from the wellhead).
MIN | 5pts | SO | S023 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with a smooth nosed sampling tap, a check valve, a pressure gauge, a
means of measuring flow, and a shutoff valve. (smooth nosed sampling tap being the
first item from the well head and the shut-off valve as the last item)
C
250 Well discharge line has a check valve.
MIN | 5pts | SO | S024 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
251 Well discharge line has a pressure gauge.
MIN | 5pts | SO | S025 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
252 Well discharge line has a means to measure flow.
MIN | 5pts | SO | S026 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
253 Well discharge line has a shut-off valve (last item from the well head).
MIN | 5pts | SO | S027 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
254 Is there an air/vac valve on the well discharge line? If yes, answer the following
question(s)
Y
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 39 of 97
WS016 - HI-UTE WELL REPL-1 - Active
Exception Granted: R309-515-6 (12)(d)(iv), Sampling Tap | Rule R309-515-6 (12)(d)(iv), requires that the well:
“be equipped with a smooth-nosed sampling tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve (with the smooth
nosed sampling tap being the first item from the well head and the shut-off valve as the last item), unless it is a naturally flowing well which may
need an alternative design.”
The basis for your request for an exception for The Hi-Ute Well REPL-1 Replacement Well is the well was configured with the sample tap placed
downstream of a pressure sustaining/control valve. This was approved during the Well Equipping Plan Approval. The pressure on the well side of
this valve can reach 350 PSI. As a result, the sampling tap could not located upstream of the valve safely, or functionally from an operations
perspective.
254A
Air vacuum relief valve on well discharge piping downturned
SIG | 25pts | SO | S028 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be down-turned.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
254B
Air vacuum relief valve on well discharge piping screened with #14 mesh screen
SIG | 25pts | SO | S029 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be covered with a
#14 mesh corrosion-resistant screen. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
254C
Air vacuum relief valve on well discharge piping has at least 6 inches of clearance
above floor
SIG | 25pts | SO | S030 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be at least 6
inches above the well house floor. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
255 Wells that pump directly into a distribution system have means to release trapped air
from pump discharge piping (for example, pumps directly to a tank, has an air release
valve or pump to waste line)
MIN | 5pts | SO | SL01 | R309-515-6(12)(d)(v) | Rule requires a well that pumps
directly into the distribution system be equipped with an air release/vacuum relief valve
located upstream of the check valve, unless the wellhead valve and piping provide for
pumping to waste all trapped air before water is introduced into the distribution
system.
C
256 Does well require oil-lubrication?Y
256A
Well shaft lubricants ANSI/NSF 60 certified
SIG | 25pts | SO | S031 | R309-105-10(7), R309-515-6(6)(a) | Rules require all oil-
lubricated pumps for drinking water wells to utilize food-grade mineral oil suitable for
human consumption as determined by the Director. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
<a href="https://www.youtube.com/watch?v=UABQMeeUz1g">Click here for addition
training</a>
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 40 of 97
257 Is this facility Active or Inactive?A
258 Operating Period (Start Date)01/01
259 Operating Period (Ending Date)12/31
260 Undocumented sources shall not be physically connected to the drinking water
system. (IF SOURCE IS NOT IN SYSTEM INVENTORY MARK "DEFICIENT")
SIG | 200pts | SO | S001 | R309-515-6(5), R309-515-7(4), R309-500-9(2) and (3) |
R309-105-6(1) requires plans and specifications for all public drinking water projects to
be approved in writing by the Director prior to the commencement of construction. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
261 Well casing is at least 18 inches above finished ground surface and 12 inches above
well house floor.
SIG | 25pts | SO | S003 | R309-515-6(6)(b)(vi), R309-515-6(12)(c)(ii), R309-515-
6(13)(a) | Rule requires the permanent well casing to project at least 18 inches above
the final ground surface and 12 inches above the pump house floor; at sites subject to
flooding, the top of the casing must terminate at least 3 feet above the 100-year flood
level or highest known flood elevation, whichever is higher. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
262 Wellhead is sealed to prevent contamination.
SIG | 50pts | SO | S013 | R309-515-6(6)(i) | R309-515-6(6)(i) and R309-515-
6(12)(b,c,d)require a sanitary seal be installed and maintained at the wellhead and
discharge piping. This significant deficiency should be corrected within 120 days of
notification or have a corrective action plan approved by
C
263 Is the well casing vented? ... if yes, answer the following question(s)Y
263A
Vent screened with #14 mesh screen
SIG | 25pts | SO | S006 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(a)require vents be fitted with a #14 mesh or finer non-corrodible screen.
C
263B
Vent down-turned
SIG | 25pts | SO | S007 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(b) requires vents be downturned or shielded to prevent the entrance of
surface water or rainwater.
C
263C
Vent has adequate clearance to prevent contamination from entering the well
SIG | 25pts | SO | S008 | R309-515-6(12)(d)(iii) | Guidance states provisions should be
made for venting the well casing, however if vented R309-515-6(12)(d)(iii) and R309-
550-6(6)(b) requires vents be terminated with a discharge with an appropriate air gap.
C
264 Does the well have a pump to waste line? ... if yes, answer the following question(s)Y
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 41 of 97
264A
Pump to waste line discharges with a minimum of 12-inch clearance to flood rim
SIG | 25pts | SO | S009 | R309-515-6(12)(d)(ix) | Rule requires a pump-to-waste line
connected to a sewer/storm drain to have a minimum 12-inch clearance to the flood
rim. This significant deficiency must be corrected within 120 days of notification or
have a corrective action plan approved by DDW.
C
264B
Pump to waste line equipped with #4 non-corrodible mesh screen
SIG | 25pts | SO | S010 | R309-515-6(12)(d)(ix) | The discharge end of the pump-to-
waste line shall be covered with a No. 4 mesh corrosion-resistant screen. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
264C
Pump to waste line downturned if it discharges to sewer/storm drain or allowing
complete drainage if not downturned
SIG | 25pts | SO | S011 | R309-515-6(12)(d)(ix) | The discharge end of the pump-to-
waste line shall be downturned. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
265 Provisions available to periodically measure water levels
MIN | 5pts | SO | S015 | R309-515-6(12)(e ), R309-515-6(12)(c)(vi) | Rule requires
provisions be made to permit periodic measurement of water levels in the completed
well.
C
266 Wellhead secured to protect quality water
SIG | 25pts | SO | S002 | R309-105-10(5) | All water system facilities shall be secure.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
267 Well head or well house and equipment protected from flooding
SIG | 25pts | SO | S020 | R309-515-6(6)(b)(vi), R309-515-6(12)(d)(iii), R309-515-
6(13)(a) to (d) | Top of well casing shall terminate at least 18” above ground level or
12” above well house floor and for sites that flood at least 3’ above 100-year flood
level or highest known flood elevation. Well casing terminating in underground vault
shall have a drain to daylight and surface runoff directed away from vault access. Well
house floor shall be sloped for drainage, and have a drain to daylight unless highly
impractical. This significant deficiency must be corrected within 120 days of notification
or have a corrective action plan approved by DDW.
C
268 There are no unprotected cross-connections in well discharge piping.
SIG | 50pts | SO | S021 | R309-105-12(1), R309-515-6(12)(d)(iii) | Rule requires the
well discharge piping to be protected against the entrance of contamination. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
269 No toxic chemicals, hazardous or flammable materials, or lubricants inside the well
house or near well head?
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 42 of 97
270 Well discharge line has a smooth-nosed sampling tap, which samples the well water
before any chemical injection. (first item from the wellhead).
MIN | 5pts | SO | S023 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with a smooth nosed sampling tap, a check valve, a pressure gauge, a
means of measuring flow, and a shutoff valve. (smooth nosed sampling tap being the
first item from the well head and the shut-off valve as the last item)
C
271 Well discharge line has a check valve.
MIN | 5pts | SO | S024 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
272 Well discharge line has a pressure gauge.
MIN | 5pts | SO | S025 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
273 Well discharge line has a means to measure flow.
MIN | 5pts | SO | S026 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
274 Well discharge line has a shut-off valve (last item from the well head).
MIN | 5pts | SO | S027 | R309-515-6(12)(d)(iv) | Rule requires the discharge piping to
be equipped with (in order of placement from the wellhead) a smooth nosed sampling
tap, a check valve, a pressure gauge, a means of measuring flow, and a shutoff valve.
C
275 Is there an air/vac valve on the well discharge line? If yes, answer the following
question(s)
Y
275A
Air vacuum relief valve on well discharge piping downturned
SIG | 25pts | SO | S028 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be down-turned.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
275B
Air vacuum relief valve on well discharge piping screened with #14 mesh screen
SIG | 25pts | SO | S029 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be covered with a
#14 mesh corrosion-resistant screen. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
275C
Air vacuum relief valve on well discharge piping has at least 6 inches of clearance
above floor
SIG | 25pts | SO | S030 | R309-515-6(12)(d)(v) | Rule requires the exhaust/relief piping
on an air release/vacuum relief valve on the well discharge piping to be at least 6
inches above the well house floor. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 43 of 97
ST001 - LOWER HIDDEN COVE TANK - Active
276 Wells that pump directly into a distribution system have means to release trapped air
from pump discharge piping (for example, pumps directly to a tank, has an air release
valve or pump to waste line)
MIN | 5pts | SO | SL01 | R309-515-6(12)(d)(v) | Rule requires a well that pumps
directly into the distribution system be equipped with an air release/vacuum relief valve
located upstream of the check valve, unless the wellhead valve and piping provide for
pumping to waste all trapped air before water is introduced into the distribution
system.
C
277 Does well require oil-lubrication?Y
277A
Well shaft lubricants ANSI/NSF 60 certified
SIG | 25pts | SO | S031 | R309-105-10(7), R309-515-6(6)(a) | Rules require all oil-
lubricated pumps for drinking water wells to utilize food-grade mineral oil suitable for
human consumption as determined by the Director. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
<a href="https://www.youtube.com/watch?v=UABQMeeUz1g">Click here for addition
training</a>
C
278 Is this facility Active or Inactive?A
279 Storage tank capacity in gallons (from SDWIS; if different explain why in the
comments)
500000
280 There are no undocumented drinking water facilities (i.e. tanks, pump stations,
treatment facilities, etc.) or recent modifications that have not gone through DDW
review
SIG | 50pts | SM | G001 | R309-100-5(2), R309-500-6, R309-500-9, R309-500-9(2)
and (3) | Rule requires complete plans & specification for all public drinking water
projects to be approved in writing by the Director. Any facility found that has not
started DDW review shall be considered unapproved. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
281 Ladders, ladder guards, platform railings, or safely located entrance hatches are
provided.
MIN | 15pts | FW | V004 | R309-545-18 | Rule requires ladders, ladder guards,
platform railings, and safely located entrance hatches where applicable for water
storage tanks and requires safety practices to conform to pertinent laws and
regulations of the Utah Occupational Safety and Health Division.
C
282 Tank is vented.
SIG | 25pts | FW | VL02 | R309-545-15 | Rule requires drinking water storage tanks to
be vented. Overflows cannot be considered or used as vents. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
C
283 Are air vents present? ... if yes, answer the following question(s)Y
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 44 of 97
283A
Vent is either down-turned or shielded from contaminants (at least 2 inches below the
bottom of the opening)
SIG | 25pts | FW | V005 | R309-545-15(1) | Rule requires inverted vents on water
storage tanks to be down-turned a minimum of 2 inches below any opening and
shielded to prevent the entrance of contaminants. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
283B
End of vent terminates at least 24 inches above earthen cover (buried tank) and is
located and sized to avoid blockage during winter.
MIN | 15pts | FW | V006 | R309-545-15(2) | For buried structures, the rule requires the
end of the vent discharge to be a minimum of 24 inches above the earthen covering.
C
283C
Vent covered with #14 or finer non-corrodible mesh screen.
SIG | 25pts | FW | V007 | R309-545-15(4) | Rule requires a water storage tank vent to
be fitted with #14 mesh or finer non-corrodible screen and vents 6-inches or greater in
diameter to be fitted with additional heavy gauge screen or substantial covering to
protect the #14 mesh screen from vandalism or damage. This significant deficiency
must be corrected within 120 days of notification or have a compliance action plan
approved by DDW.
C
283D
Vent 6-inch diameter and larger protected with additional heavy-gauge screen or
substantial covering.
MIN | 5pts | FW | V035 | R309-545-15(5) | Rule requires vents that are 6-inch diameter
or greater to be fitted with additional heavy gauge screen or substantial covering,
which will protect the No. 14 mesh screen against vandalism or damage.
C
284 Are access openings present? ... if yes, answer the following question(s)
MIN | 15pts | FW | VL03 | R309-545-14 and 14(1) | Rule requires drinking water
storage tanks to be designed with reasonably convenient access to the interior for
cleaning and maintenance.
Y
284A
Access opening framed at least 4 inches above roof surface or 18 inches above
earthen cover.
MIN | 15pts | FW | V008 | R309-545-14(1) | Rule requires tank access opening to be
framed at least 4 inches above the surface of the roof, or on a buried tank, to be at
least 18 inches above any earthen cover over the tank.
C
284B
Access opening shoe box type with at least 2 inches of overlap
SIG | 25pts | FW | V010 | R309-545-14(2) | Rule requires the frame of an access
opening to be provided with a close fitting solid shoebox type cover which extends
down around the frame at least two inches and is furnished with a gasket(s) between
the lid and frame. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
284C
Access opening lid properly gasketed
SIG | 25pts | FW | V009 | R309-545-14(2) | Rule requires the access opening to a tank
to be furnished with a gasket between the lid and frame. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 45 of 97
285 Access opening locked
SIG | 25pts | FW | V029 | R309-545-14(3) | Rule requires the lid to any access
opening to have a locking device. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
286 Roof or wall penetrations sealed
SIG | 100pts | FW | V017 | R309-545-6(1) and 545-9 | Rule requires openings in a
storage tank roof or top, designed to accommodate control apparatus or pump
columns, to be welded, gasketed, or curbed and sleeved and to have additional proper
shielding to prevent vandalism. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
287 Area surrounding ground-level or buried storage tank is graded to prevent surface
water from standing within 50 feet.
SIG | 25pts | TR | V001 | R309-545-7(4) | Rule requires the area surrounding a
ground-level or buried water storage tank be graded in a manner to prevent surface
water from standing within 50 feet of the tank. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
288 Storage tank roof is sloped to prevent ponding
MIN | 15pts | FW | V003 | R309-545-9(4) | Rule requires drainage of storage tank roofs
to eliminate water ponding.
D (Notes: Evidence of ponding on roof)
289 Are there cracks in the walls or roof of the storage tank? (if yes, select only one of the
following options)
N
290 Is a tank overflow present? ... if yes, answer the following question(s)
SIG | 25pts | FW | VL01 | R309-545-13 | Rule requires all storage tanks to be provided
with an overflow that discharges at an an elevation between 12 and 24 inches above
the ground surface or the rim of the receiving basin. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
Y
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 46 of 97
ST002 - UPPER HIDDEN COVE TANK - Active
290A
Overflow line discharges at least 12 inches above ground or the flood rim of receiving
basin?
Exception Granted: R309-545-13 Overflow clearance | On October 12, 2015, the
Division of Drinking Water (the Division) received your request for exceptions to Rule
R309-550-13(5), Overflows connected to sewers and R309-550-13, Tank Overflow
clearance.
These rules specifically state that:
•Overflow pipes shall not be connected to, or discharge into any sewer system.
•All water storage tanks shall be provided with an overflow that discharged at an
elevation between 12 and 24 inches above the ground surface of the rim of the
receiving basin.
The overflow pipe for the Lower Hidden Cove Tank does not have 12 inches of
clearance between the discharge and the ground surface. The overflow pipe is located
right next to the road and digging out the overflow would cause of safety issue with
passing vehicles. The grade of the surrounding area has sufficient slope away from
the drain such that water would not back up into the pipe. On this basis, an exception
to R309-550-13, Overflow pipe clearance Transmission, is hereby granted for the
Lower Hidden Cove Tank (ST001).
SIG | 25pts | FW | V011 | R309-545-13 | Rule requires all water storage tanks to be
provided with an overflow that discharges at an elevation between 12 and 24 inches
above the ground surface or the rim of the receiving basin.
C
290B
Overflow line covered with #4 mesh non-corrodible screen
SIG | 25pts | FW | V012 | R309-545-13(3) | Rule requires overflow pipes to be
screened with #4 mesh non-corrodible screens installed at a location least susceptible
to damage by vandalism. This significant deficiency must be corrected within 120 days
of notification or have a corrective action plan approved by DDW.
C
290C
Overflow line connected or discharges to a sanitary sewer drain?
SIG | 50pts | FW | V013 | R309-545-13(5) | Rule prohibits overflow pipes from
connecting to, or discharging into, a sanitary sewer system. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
291 Are the drain line and overflow combined?Y
292 Is this facility Active or Inactive?A
293 Storage tank capacity in gallons (from SDWIS; if different explain why in the
comments)
500000
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 47 of 97
294 There are no undocumented drinking water facilities (i.e. tanks, pump stations,
treatment facilities, etc.) or recent modifications that have not gone through DDW
review
SIG | 50pts | SM | G001 | R309-100-5(2), R309-500-6, R309-500-9, R309-500-9(2)
and (3) | Rule requires complete plans & specification for all public drinking water
projects to be approved in writing by the Director. Any facility found that has not
started DDW review shall be considered unapproved. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
295 Ladders, ladder guards, platform railings, or safely located entrance hatches are
provided.
MIN | 15pts | FW | V004 | R309-545-18 | Rule requires ladders, ladder guards,
platform railings, and safely located entrance hatches where applicable for water
storage tanks and requires safety practices to conform to pertinent laws and
regulations of the Utah Occupational Safety and Health Division.
C
296 Tank is vented.
SIG | 25pts | FW | VL02 | R309-545-15 | Rule requires drinking water storage tanks to
be vented. Overflows cannot be considered or used as vents. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
C
297 Are air vents present? ... if yes, answer the following question(s)Y
297A
Vent is either down-turned or shielded from contaminants (at least 2 inches below the
bottom of the opening)
SIG | 25pts | FW | V005 | R309-545-15(1) | Rule requires inverted vents on water
storage tanks to be down-turned a minimum of 2 inches below any opening and
shielded to prevent the entrance of contaminants. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
297B
End of vent terminates at least 24 inches above earthen cover (buried tank) and is
located and sized to avoid blockage during winter.
MIN | 15pts | FW | V006 | R309-545-15(2) | For buried structures, the rule requires the
end of the vent discharge to be a minimum of 24 inches above the earthen covering.
C
297C
Vent covered with #14 or finer non-corrodible mesh screen.
SIG | 25pts | FW | V007 | R309-545-15(4) | Rule requires a water storage tank vent to
be fitted with #14 mesh or finer non-corrodible screen and vents 6-inches or greater in
diameter to be fitted with additional heavy gauge screen or substantial covering to
protect the #14 mesh screen from vandalism or damage. This significant deficiency
must be corrected within 120 days of notification or have a compliance action plan
approved by DDW.
C
297D
Vent 6-inch diameter and larger protected with additional heavy-gauge screen or
substantial covering.
MIN | 5pts | FW | V035 | R309-545-15(5) | Rule requires vents that are 6-inch diameter
or greater to be fitted with additional heavy gauge screen or substantial covering,
which will protect the No. 14 mesh screen against vandalism or damage.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 48 of 97
298 Are access openings present? ... if yes, answer the following question(s)
MIN | 15pts | FW | VL03 | R309-545-14 and 14(1) | Rule requires drinking water
storage tanks to be designed with reasonably convenient access to the interior for
cleaning and maintenance.
Y
298A
Access opening framed at least 4 inches above roof surface or 18 inches above
earthen cover.
MIN | 15pts | FW | V008 | R309-545-14(1) | Rule requires tank access opening to be
framed at least 4 inches above the surface of the roof, or on a buried tank, to be at
least 18 inches above any earthen cover over the tank.
C
298B
Access opening shoe box type with at least 2 inches of overlap
SIG | 25pts | FW | V010 | R309-545-14(2) | Rule requires the frame of an access
opening to be provided with a close fitting solid shoebox type cover which extends
down around the frame at least two inches and is furnished with a gasket(s) between
the lid and frame. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
298C
Access opening lid properly gasketed
SIG | 25pts | FW | V009 | R309-545-14(2) | Rule requires the access opening to a tank
to be furnished with a gasket between the lid and frame. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
299 Access opening locked
SIG | 25pts | FW | V029 | R309-545-14(3) | Rule requires the lid to any access
opening to have a locking device. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
300 Roof or wall penetrations sealed
SIG | 100pts | FW | V017 | R309-545-6(1) and 545-9 | Rule requires openings in a
storage tank roof or top, designed to accommodate control apparatus or pump
columns, to be welded, gasketed, or curbed and sleeved and to have additional proper
shielding to prevent vandalism. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
301 Area surrounding ground-level or buried storage tank is graded to prevent surface
water from standing within 50 feet.
SIG | 25pts | TR | V001 | R309-545-7(4) | Rule requires the area surrounding a
ground-level or buried water storage tank be graded in a manner to prevent surface
water from standing within 50 feet of the tank. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
302 Storage tank roof is sloped to prevent ponding
MIN | 15pts | FW | V003 | R309-545-9(4) | Rule requires drainage of storage tank roofs
to eliminate water ponding.
D (Notes: Evidence of ponding on roof)
303 Are there cracks in the walls or roof of the storage tank? (if yes, select only one of the
following options)
N
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 49 of 97
ST003 - PLAT 5 TANK - Active
304 Is a tank overflow present? ... if yes, answer the following question(s)
SIG | 25pts | FW | VL01 | R309-545-13 | Rule requires all storage tanks to be provided
with an overflow that discharges at an an elevation between 12 and 24 inches above
the ground surface or the rim of the receiving basin. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
Y
304A
Overflow line discharges at least 12 inches above ground or the flood rim of receiving
basin?
Exception Granted: R309-545-13 Overflow clearance | On October 12, 2015, the
Division of Drinking Water (the Division) received your request for exceptions to Rule
R309-550-13(5), Overflows connected to sewers and R309-550-13, Tank Overflow
clearance.
These rules specifically state that:
•Overflow pipes shall not be connected to, or discharge into any sewer system.
•All water storage tanks shall be provided with an overflow that discharged at an
elevation between 12 and 24 inches above the ground surface of the rim of the
receiving basin.
Summit Water Distribution Company’s Trailside Tank (ST006), Upper Hidden Cove
Tank (ST002), Plat 5 Tank (ST003) and Red Hawk Tank (ST010) have overflow pipes
that are directly connected to the storm sewer system. In all cases the elevation of the
connection to the storm drain is below the elevation of the bottom of the tank
preventing water from backing up into the tank. On this basis, an exception to R309-
545-13(5), Overflows connected to sewers, is hereby granted for the Trailside Tank
(ST006), Upper Hidden Cove Tank (ST002), Plat 5 Tank (ST003) and the Red Hawk
Tank (ST010))
SIG | 25pts | FW | V011 | R309-545-13 | Rule requires all water storage tanks to be
provided with an overflow that discharges at an elevation between 12 and 24 inches
above the ground surface or the rim of the receiving basin.
C
304B
Overflow line covered with #4 mesh non-corrodible screen
SIG | 25pts | FW | V012 | R309-545-13(3) | Rule requires overflow pipes to be
screened with #4 mesh non-corrodible screens installed at a location least susceptible
to damage by vandalism. This significant deficiency must be corrected within 120 days
of notification or have a corrective action plan approved by DDW.
C
304C
Overflow line connected or discharges to a sanitary sewer drain?
SIG | 50pts | FW | V013 | R309-545-13(5) | Rule prohibits overflow pipes from
connecting to, or discharging into, a sanitary sewer system. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
305 Are the drain line and overflow combined?Y
306 Is this facility Active or Inactive?A
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 50 of 97
307 Storage tank capacity in gallons (from SDWIS; if different explain why in the
comments)
500000
308 There are no undocumented drinking water facilities (i.e. tanks, pump stations,
treatment facilities, etc.) or recent modifications that have not gone through DDW
review
SIG | 50pts | SM | G001 | R309-100-5(2), R309-500-6, R309-500-9, R309-500-9(2)
and (3) | Rule requires complete plans & specification for all public drinking water
projects to be approved in writing by the Director. Any facility found that has not
started DDW review shall be considered unapproved. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
309 Ladders, ladder guards, platform railings, or safely located entrance hatches are
provided.
MIN | 15pts | FW | V004 | R309-545-18 | Rule requires ladders, ladder guards,
platform railings, and safely located entrance hatches where applicable for water
storage tanks and requires safety practices to conform to pertinent laws and
regulations of the Utah Occupational Safety and Health Division.
C
310 Tank is vented.
SIG | 25pts | FW | VL02 | R309-545-15 | Rule requires drinking water storage tanks to
be vented. Overflows cannot be considered or used as vents. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
C
311 Are air vents present? ... if yes, answer the following question(s)Y
311A
Vent is either down-turned or shielded from contaminants (at least 2 inches below the
bottom of the opening)
SIG | 25pts | FW | V005 | R309-545-15(1) | Rule requires inverted vents on water
storage tanks to be down-turned a minimum of 2 inches below any opening and
shielded to prevent the entrance of contaminants. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
311B
End of vent terminates at least 24 inches above earthen cover (buried tank) and is
located and sized to avoid blockage during winter.
MIN | 15pts | FW | V006 | R309-545-15(2) | For buried structures, the rule requires the
end of the vent discharge to be a minimum of 24 inches above the earthen covering.
C
311C
Vent covered with #14 or finer non-corrodible mesh screen.
SIG | 25pts | FW | V007 | R309-545-15(4) | Rule requires a water storage tank vent to
be fitted with #14 mesh or finer non-corrodible screen and vents 6-inches or greater in
diameter to be fitted with additional heavy gauge screen or substantial covering to
protect the #14 mesh screen from vandalism or damage. This significant deficiency
must be corrected within 120 days of notification or have a compliance action plan
approved by DDW.
C
311D
Vent 6-inch diameter and larger protected with additional heavy-gauge screen or
substantial covering.
MIN | 5pts | FW | V035 | R309-545-15(5) | Rule requires vents that are 6-inch diameter
or greater to be fitted with additional heavy gauge screen or substantial covering,
which will protect the No. 14 mesh screen against vandalism or damage.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 51 of 97
312 Are access openings present? ... if yes, answer the following question(s)
MIN | 15pts | FW | VL03 | R309-545-14 and 14(1) | Rule requires drinking water
storage tanks to be designed with reasonably convenient access to the interior for
cleaning and maintenance.
Y
312A
Access opening framed at least 4 inches above roof surface or 18 inches above
earthen cover.
MIN | 15pts | FW | V008 | R309-545-14(1) | Rule requires tank access opening to be
framed at least 4 inches above the surface of the roof, or on a buried tank, to be at
least 18 inches above any earthen cover over the tank.
C
312B
Access opening shoe box type with at least 2 inches of overlap
SIG | 25pts | FW | V010 | R309-545-14(2) | Rule requires the frame of an access
opening to be provided with a close fitting solid shoebox type cover which extends
down around the frame at least two inches and is furnished with a gasket(s) between
the lid and frame. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
312C
Access opening lid properly gasketed
SIG | 25pts | FW | V009 | R309-545-14(2) | Rule requires the access opening to a tank
to be furnished with a gasket between the lid and frame. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
313 Access opening locked
SIG | 25pts | FW | V029 | R309-545-14(3) | Rule requires the lid to any access
opening to have a locking device. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
314 Roof or wall penetrations sealed
SIG | 100pts | FW | V017 | R309-545-6(1) and 545-9 | Rule requires openings in a
storage tank roof or top, designed to accommodate control apparatus or pump
columns, to be welded, gasketed, or curbed and sleeved and to have additional proper
shielding to prevent vandalism. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
315 Area surrounding ground-level or buried storage tank is graded to prevent surface
water from standing within 50 feet.
SIG | 25pts | TR | V001 | R309-545-7(4) | Rule requires the area surrounding a
ground-level or buried water storage tank be graded in a manner to prevent surface
water from standing within 50 feet of the tank. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
316 Storage tank roof is sloped to prevent ponding
MIN | 15pts | FW | V003 | R309-545-9(4) | Rule requires drainage of storage tank roofs
to eliminate water ponding.
C
317 Are there cracks in the walls or roof of the storage tank? (if yes, select only one of the
following options)
N
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 52 of 97
ST004 - TOMBSTONE TANK - Active
318 Is a tank overflow present? ... if yes, answer the following question(s)
SIG | 25pts | FW | VL01 | R309-545-13 | Rule requires all storage tanks to be provided
with an overflow that discharges at an an elevation between 12 and 24 inches above
the ground surface or the rim of the receiving basin. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
Y
318A
Overflow line discharges at least 12 inches above ground or the flood rim of receiving
basin?
Exception Granted: R309-545-13 Overflow clearance | On October 12, 2015, the
Division of Drinking Water (the Division) received your request for exceptions to Rule
R309-550-13(5), Overflows connected to sewers and R309-550-13, Tank Overflow
clearance.
These rules specifically state that:
•Overflow pipes shall not be connected to, or discharge into any sewer system.
•All water storage tanks shall be provided with an overflow that discharged at an
elevation between 12 and 24 inches above the ground surface of the rim of the
receiving basin.
Summit Water Distribution Company’s Trailside Tank (ST006), Upper Hidden Cove
Tank (ST002), Plat 5 Tank (ST003) and Red Hawk Tank (ST010) have overflow pipes
that are directly connected to the storm sewer system. In all cases the elevation of the
connection to the storm drain is below the elevation of the bottom of the tank
preventing water from backing up into the tank. On this basis, an exception to R309-
545-13(5), Overflows connected to sewers, is hereby granted for the Trailside Tank
(ST006), Upper Hidden Cove Tank (ST002), Plat 5 Tank (ST003) and the Red Hawk
Tank (ST010))
SIG | 25pts | FW | V011 | R309-545-13 | Rule requires all water storage tanks to be
provided with an overflow that discharges at an elevation between 12 and 24 inches
above the ground surface or the rim of the receiving basin.
C
318B
Overflow line covered with #4 mesh non-corrodible screen
SIG | 25pts | FW | V012 | R309-545-13(3) | Rule requires overflow pipes to be
screened with #4 mesh non-corrodible screens installed at a location least susceptible
to damage by vandalism. This significant deficiency must be corrected within 120 days
of notification or have a corrective action plan approved by DDW.
C
318C
Overflow line connected or discharges to a sanitary sewer drain?
SIG | 50pts | FW | V013 | R309-545-13(5) | Rule prohibits overflow pipes from
connecting to, or discharging into, a sanitary sewer system. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
319 Are the drain line and overflow combined?Y
320 Is this facility Active or Inactive?A
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 53 of 97
321 Storage tank capacity in gallons (from SDWIS; if different explain why in the
comments)
100000
322 There are no undocumented drinking water facilities (i.e. tanks, pump stations,
treatment facilities, etc.) or recent modifications that have not gone through DDW
review
SIG | 50pts | SM | G001 | R309-100-5(2), R309-500-6, R309-500-9, R309-500-9(2)
and (3) | Rule requires complete plans & specification for all public drinking water
projects to be approved in writing by the Director. Any facility found that has not
started DDW review shall be considered unapproved. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
323 Ladders, ladder guards, platform railings, or safely located entrance hatches are
provided.
MIN | 15pts | FW | V004 | R309-545-18 | Rule requires ladders, ladder guards,
platform railings, and safely located entrance hatches where applicable for water
storage tanks and requires safety practices to conform to pertinent laws and
regulations of the Utah Occupational Safety and Health Division.
C
324 Tank is vented.
SIG | 25pts | FW | VL02 | R309-545-15 | Rule requires drinking water storage tanks to
be vented. Overflows cannot be considered or used as vents. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
C
325 Are air vents present? ... if yes, answer the following question(s)Y
325A
Vent is either down-turned or shielded from contaminants (at least 2 inches below the
bottom of the opening)
SIG | 25pts | FW | V005 | R309-545-15(1) | Rule requires inverted vents on water
storage tanks to be down-turned a minimum of 2 inches below any opening and
shielded to prevent the entrance of contaminants. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
325B
End of vent terminates at least 24 inches above earthen cover (buried tank) and is
located and sized to avoid blockage during winter.
MIN | 15pts | FW | V006 | R309-545-15(2) | For buried structures, the rule requires the
end of the vent discharge to be a minimum of 24 inches above the earthen covering.
C
325C
Vent covered with #14 or finer non-corrodible mesh screen.
SIG | 25pts | FW | V007 | R309-545-15(4) | Rule requires a water storage tank vent to
be fitted with #14 mesh or finer non-corrodible screen and vents 6-inches or greater in
diameter to be fitted with additional heavy gauge screen or substantial covering to
protect the #14 mesh screen from vandalism or damage. This significant deficiency
must be corrected within 120 days of notification or have a compliance action plan
approved by DDW.
C
325D
Vent 6-inch diameter and larger protected with additional heavy-gauge screen or
substantial covering.
MIN | 5pts | FW | V035 | R309-545-15(5) | Rule requires vents that are 6-inch diameter
or greater to be fitted with additional heavy gauge screen or substantial covering,
which will protect the No. 14 mesh screen against vandalism or damage.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 54 of 97
326 Are access openings present? ... if yes, answer the following question(s)
MIN | 15pts | FW | VL03 | R309-545-14 and 14(1) | Rule requires drinking water
storage tanks to be designed with reasonably convenient access to the interior for
cleaning and maintenance.
Y
326A
Access opening framed at least 4 inches above roof surface or 18 inches above
earthen cover.
MIN | 15pts | FW | V008 | R309-545-14(1) | Rule requires tank access opening to be
framed at least 4 inches above the surface of the roof, or on a buried tank, to be at
least 18 inches above any earthen cover over the tank.
C
326B
Access opening shoe box type with at least 2 inches of overlap
SIG | 25pts | FW | V010 | R309-545-14(2) | Rule requires the frame of an access
opening to be provided with a close fitting solid shoebox type cover which extends
down around the frame at least two inches and is furnished with a gasket(s) between
the lid and frame. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
326C
Access opening lid properly gasketed
SIG | 25pts | FW | V009 | R309-545-14(2) | Rule requires the access opening to a tank
to be furnished with a gasket between the lid and frame. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
327 Access opening locked
SIG | 25pts | FW | V029 | R309-545-14(3) | Rule requires the lid to any access
opening to have a locking device. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
328 Roof or wall penetrations sealed
SIG | 100pts | FW | V017 | R309-545-6(1) and 545-9 | Rule requires openings in a
storage tank roof or top, designed to accommodate control apparatus or pump
columns, to be welded, gasketed, or curbed and sleeved and to have additional proper
shielding to prevent vandalism. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
329 Area surrounding ground-level or buried storage tank is graded to prevent surface
water from standing within 50 feet.
SIG | 25pts | TR | V001 | R309-545-7(4) | Rule requires the area surrounding a
ground-level or buried water storage tank be graded in a manner to prevent surface
water from standing within 50 feet of the tank. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
330 Storage tank roof is sloped to prevent ponding
MIN | 15pts | FW | V003 | R309-545-9(4) | Rule requires drainage of storage tank roofs
to eliminate water ponding.
C
331 Are there cracks in the walls or roof of the storage tank? (if yes, select only one of the
following options)
N
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 55 of 97
ST005 - RANCH PLACE TANK - Active
332 Is a tank overflow present? ... if yes, answer the following question(s)
SIG | 25pts | FW | VL01 | R309-545-13 | Rule requires all storage tanks to be provided
with an overflow that discharges at an an elevation between 12 and 24 inches above
the ground surface or the rim of the receiving basin. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
Y
332A
Overflow line discharges at least 12 inches above ground or the flood rim of receiving
basin?
SIG | 25pts | FW | V011 | R309-545-13 | Rule requires all water storage tanks to be
provided with an overflow that discharges at an elevation between 12 and 24 inches
above the ground surface or the rim of the receiving basin.
C
332B
Overflow line covered with #4 mesh non-corrodible screen
SIG | 25pts | FW | V012 | R309-545-13(3) | Rule requires overflow pipes to be
screened with #4 mesh non-corrodible screens installed at a location least susceptible
to damage by vandalism. This significant deficiency must be corrected within 120 days
of notification or have a corrective action plan approved by DDW.
C
332C
Overflow line connected or discharges to a sanitary sewer drain?
SIG | 50pts | FW | V013 | R309-545-13(5) | Rule prohibits overflow pipes from
connecting to, or discharging into, a sanitary sewer system. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
333 Are the drain line and overflow combined?Y
334 Is this facility Active or Inactive?A
335 Storage tank capacity in gallons (from SDWIS; if different explain why in the
comments)
750000
336 There are no undocumented drinking water facilities (i.e. tanks, pump stations,
treatment facilities, etc.) or recent modifications that have not gone through DDW
review
SIG | 50pts | SM | G001 | R309-100-5(2), R309-500-6, R309-500-9, R309-500-9(2)
and (3) | Rule requires complete plans & specification for all public drinking water
projects to be approved in writing by the Director. Any facility found that has not
started DDW review shall be considered unapproved. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
337 Ladders, ladder guards, platform railings, or safely located entrance hatches are
provided.
MIN | 15pts | FW | V004 | R309-545-18 | Rule requires ladders, ladder guards,
platform railings, and safely located entrance hatches where applicable for water
storage tanks and requires safety practices to conform to pertinent laws and
regulations of the Utah Occupational Safety and Health Division.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 56 of 97
338 Tank is vented.
SIG | 25pts | FW | VL02 | R309-545-15 | Rule requires drinking water storage tanks to
be vented. Overflows cannot be considered or used as vents. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
C
339 Are air vents present? ... if yes, answer the following question(s)Y
339A
Vent is either down-turned or shielded from contaminants (at least 2 inches below the
bottom of the opening)
SIG | 25pts | FW | V005 | R309-545-15(1) | Rule requires inverted vents on water
storage tanks to be down-turned a minimum of 2 inches below any opening and
shielded to prevent the entrance of contaminants. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
339B
End of vent terminates at least 24 inches above earthen cover (buried tank) and is
located and sized to avoid blockage during winter.
MIN | 15pts | FW | V006 | R309-545-15(2) | For buried structures, the rule requires the
end of the vent discharge to be a minimum of 24 inches above the earthen covering.
C
339C
Vent covered with #14 or finer non-corrodible mesh screen.
SIG | 25pts | FW | V007 | R309-545-15(4) | Rule requires a water storage tank vent to
be fitted with #14 mesh or finer non-corrodible screen and vents 6-inches or greater in
diameter to be fitted with additional heavy gauge screen or substantial covering to
protect the #14 mesh screen from vandalism or damage. This significant deficiency
must be corrected within 120 days of notification or have a compliance action plan
approved by DDW.
C
339D
Vent 6-inch diameter and larger protected with additional heavy-gauge screen or
substantial covering.
MIN | 5pts | FW | V035 | R309-545-15(5) | Rule requires vents that are 6-inch diameter
or greater to be fitted with additional heavy gauge screen or substantial covering,
which will protect the No. 14 mesh screen against vandalism or damage.
C
340 Are access openings present? ... if yes, answer the following question(s)
MIN | 15pts | FW | VL03 | R309-545-14 and 14(1) | Rule requires drinking water
storage tanks to be designed with reasonably convenient access to the interior for
cleaning and maintenance.
Y
340A
Access opening framed at least 4 inches above roof surface or 18 inches above
earthen cover.
MIN | 15pts | FW | V008 | R309-545-14(1) | Rule requires tank access opening to be
framed at least 4 inches above the surface of the roof, or on a buried tank, to be at
least 18 inches above any earthen cover over the tank.
C
340B
Access opening shoe box type with at least 2 inches of overlap
SIG | 25pts | FW | V010 | R309-545-14(2) | Rule requires the frame of an access
opening to be provided with a close fitting solid shoebox type cover which extends
down around the frame at least two inches and is furnished with a gasket(s) between
the lid and frame. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 57 of 97
340C
Access opening lid properly gasketed
SIG | 25pts | FW | V009 | R309-545-14(2) | Rule requires the access opening to a tank
to be furnished with a gasket between the lid and frame. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
341 Access opening locked
SIG | 25pts | FW | V029 | R309-545-14(3) | Rule requires the lid to any access
opening to have a locking device. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
342 Roof or wall penetrations sealed
SIG | 100pts | FW | V017 | R309-545-6(1) and 545-9 | Rule requires openings in a
storage tank roof or top, designed to accommodate control apparatus or pump
columns, to be welded, gasketed, or curbed and sleeved and to have additional proper
shielding to prevent vandalism. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
343 Area surrounding ground-level or buried storage tank is graded to prevent surface
water from standing within 50 feet.
SIG | 25pts | TR | V001 | R309-545-7(4) | Rule requires the area surrounding a
ground-level or buried water storage tank be graded in a manner to prevent surface
water from standing within 50 feet of the tank. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
344 Storage tank roof is sloped to prevent ponding
MIN | 15pts | FW | V003 | R309-545-9(4) | Rule requires drainage of storage tank roofs
to eliminate water ponding.
C
345 Are there cracks in the walls or roof of the storage tank? (if yes, select only one of the
following options)
N
346 Is a tank overflow present? ... if yes, answer the following question(s)
SIG | 25pts | FW | VL01 | R309-545-13 | Rule requires all storage tanks to be provided
with an overflow that discharges at an an elevation between 12 and 24 inches above
the ground surface or the rim of the receiving basin. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
Y
346A
Overflow line discharges at least 12 inches above ground or the flood rim of receiving
basin?
SIG | 25pts | FW | V011 | R309-545-13 | Rule requires all water storage tanks to be
provided with an overflow that discharges at an elevation between 12 and 24 inches
above the ground surface or the rim of the receiving basin.
C
346B
Overflow line covered with #4 mesh non-corrodible screen
SIG | 25pts | FW | V012 | R309-545-13(3) | Rule requires overflow pipes to be
screened with #4 mesh non-corrodible screens installed at a location least susceptible
to damage by vandalism. This significant deficiency must be corrected within 120 days
of notification or have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 58 of 97
ST006 - TRAILSIDE TANK - Active
346C
Overflow line connected or discharges to a sanitary sewer drain?
SIG | 50pts | FW | V013 | R309-545-13(5) | Rule prohibits overflow pipes from
connecting to, or discharging into, a sanitary sewer system. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
347 Are the drain line and overflow combined?Y
348 Is this facility Active or Inactive?A
349 Storage tank capacity in gallons (from SDWIS; if different explain why in the
comments)
1500000
350 There are no undocumented drinking water facilities (i.e. tanks, pump stations,
treatment facilities, etc.) or recent modifications that have not gone through DDW
review
SIG | 50pts | SM | G001 | R309-100-5(2), R309-500-6, R309-500-9, R309-500-9(2)
and (3) | Rule requires complete plans & specification for all public drinking water
projects to be approved in writing by the Director. Any facility found that has not
started DDW review shall be considered unapproved. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
351 Ladders, ladder guards, platform railings, or safely located entrance hatches are
provided.
MIN | 15pts | FW | V004 | R309-545-18 | Rule requires ladders, ladder guards,
platform railings, and safely located entrance hatches where applicable for water
storage tanks and requires safety practices to conform to pertinent laws and
regulations of the Utah Occupational Safety and Health Division.
C
352 Tank is vented.
SIG | 25pts | FW | VL02 | R309-545-15 | Rule requires drinking water storage tanks to
be vented. Overflows cannot be considered or used as vents. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
C
353 Are air vents present? ... if yes, answer the following question(s)Y
353A
Vent is either down-turned or shielded from contaminants (at least 2 inches below the
bottom of the opening)
SIG | 25pts | FW | V005 | R309-545-15(1) | Rule requires inverted vents on water
storage tanks to be down-turned a minimum of 2 inches below any opening and
shielded to prevent the entrance of contaminants. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
353B
End of vent terminates at least 24 inches above earthen cover (buried tank) and is
located and sized to avoid blockage during winter.
MIN | 15pts | FW | V006 | R309-545-15(2) | For buried structures, the rule requires the
end of the vent discharge to be a minimum of 24 inches above the earthen covering.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 59 of 97
353C
Vent covered with #14 or finer non-corrodible mesh screen.
SIG | 25pts | FW | V007 | R309-545-15(4) | Rule requires a water storage tank vent to
be fitted with #14 mesh or finer non-corrodible screen and vents 6-inches or greater in
diameter to be fitted with additional heavy gauge screen or substantial covering to
protect the #14 mesh screen from vandalism or damage. This significant deficiency
must be corrected within 120 days of notification or have a compliance action plan
approved by DDW.
C
353D
Vent 6-inch diameter and larger protected with additional heavy-gauge screen or
substantial covering.
MIN | 5pts | FW | V035 | R309-545-15(5) | Rule requires vents that are 6-inch diameter
or greater to be fitted with additional heavy gauge screen or substantial covering,
which will protect the No. 14 mesh screen against vandalism or damage.
C
354 Are access openings present? ... if yes, answer the following question(s)
MIN | 15pts | FW | VL03 | R309-545-14 and 14(1) | Rule requires drinking water
storage tanks to be designed with reasonably convenient access to the interior for
cleaning and maintenance.
Y
354A
Access opening framed at least 4 inches above roof surface or 18 inches above
earthen cover.
MIN | 15pts | FW | V008 | R309-545-14(1) | Rule requires tank access opening to be
framed at least 4 inches above the surface of the roof, or on a buried tank, to be at
least 18 inches above any earthen cover over the tank.
C
354B
Access opening shoe box type with at least 2 inches of overlap
SIG | 25pts | FW | V010 | R309-545-14(2) | Rule requires the frame of an access
opening to be provided with a close fitting solid shoebox type cover which extends
down around the frame at least two inches and is furnished with a gasket(s) between
the lid and frame. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
354C
Access opening lid properly gasketed
SIG | 25pts | FW | V009 | R309-545-14(2) | Rule requires the access opening to a tank
to be furnished with a gasket between the lid and frame. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
355 Access opening locked
SIG | 25pts | FW | V029 | R309-545-14(3) | Rule requires the lid to any access
opening to have a locking device. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
356 Roof or wall penetrations sealed
SIG | 100pts | FW | V017 | R309-545-6(1) and 545-9 | Rule requires openings in a
storage tank roof or top, designed to accommodate control apparatus or pump
columns, to be welded, gasketed, or curbed and sleeved and to have additional proper
shielding to prevent vandalism. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 60 of 97
357 Area surrounding ground-level or buried storage tank is graded to prevent surface
water from standing within 50 feet.
SIG | 25pts | TR | V001 | R309-545-7(4) | Rule requires the area surrounding a
ground-level or buried water storage tank be graded in a manner to prevent surface
water from standing within 50 feet of the tank. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
358 Storage tank roof is sloped to prevent ponding
MIN | 15pts | FW | V003 | R309-545-9(4) | Rule requires drainage of storage tank roofs
to eliminate water ponding.
C
359 Are there cracks in the walls or roof of the storage tank? (if yes, select only one of the
following options)
N
360 Is a tank overflow present? ... if yes, answer the following question(s)
SIG | 25pts | FW | VL01 | R309-545-13 | Rule requires all storage tanks to be provided
with an overflow that discharges at an an elevation between 12 and 24 inches above
the ground surface or the rim of the receiving basin. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
Y
360A
Overflow line discharges at least 12 inches above ground or the flood rim of receiving
basin?
Exception Granted: R309-545-13 Overflow clearance | On October 12, 2015, the
Division of Drinking Water (the Division) received your request for exceptions to Rule
R309-550-13(5), Overflows connected to sewers and R309-550-13, Tank Overflow
clearance.
These rules specifically state that:
•Overflow pipes shall not be connected to, or discharge into any sewer system.
•All water storage tanks shall be provided with an overflow that discharged at an
elevation between 12 and 24 inches above the ground surface of the rim of the
receiving basin.
Summit Water Distribution Company’s Trailside Tank (ST006), Upper Hidden Cove
Tank (ST002), Plat 5 Tank (ST003) and Red Hawk Tank (ST010) have overflow pipes
that are directly connected to the storm system. In all cases the elevation of the
connection to the storm drain is below the elevation of the bottom of the tank
preventing water from backing up into the tank. On this basis, an exception to R309-
545-13(5), Overflows connected to sewers, is hereby granted for the Trailside Tank
(ST006), Upper Hidden Cove Tank (ST002), Plat 5 Tank (ST003) and the Red Hawk
Tank (ST010))
SIG | 25pts | FW | V011 | R309-545-13 | Rule requires all water storage tanks to be
provided with an overflow that discharges at an elevation between 12 and 24 inches
above the ground surface or the rim of the receiving basin.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 61 of 97
ST007 - SECTION 27 TANK - Active
360B
Overflow line covered with #4 mesh non-corrodible screen
SIG | 25pts | FW | V012 | R309-545-13(3) | Rule requires overflow pipes to be
screened with #4 mesh non-corrodible screens installed at a location least susceptible
to damage by vandalism. This significant deficiency must be corrected within 120 days
of notification or have a corrective action plan approved by DDW.
C
360C
Overflow line connected or discharges to a sanitary sewer drain?
SIG | 50pts | FW | V013 | R309-545-13(5) | Rule prohibits overflow pipes from
connecting to, or discharging into, a sanitary sewer system. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
361 Are the drain line and overflow combined?Y
362 Is this facility Active or Inactive?A
363 Storage tank capacity in gallons (from SDWIS; if different explain why in the
comments)
750000
364 There are no undocumented drinking water facilities (i.e. tanks, pump stations,
treatment facilities, etc.) or recent modifications that have not gone through DDW
review
SIG | 50pts | SM | G001 | R309-100-5(2), R309-500-6, R309-500-9, R309-500-9(2)
and (3) | Rule requires complete plans & specification for all public drinking water
projects to be approved in writing by the Director. Any facility found that has not
started DDW review shall be considered unapproved. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
365 Ladders, ladder guards, platform railings, or safely located entrance hatches are
provided.
MIN | 15pts | FW | V004 | R309-545-18 | Rule requires ladders, ladder guards,
platform railings, and safely located entrance hatches where applicable for water
storage tanks and requires safety practices to conform to pertinent laws and
regulations of the Utah Occupational Safety and Health Division.
C
366 Tank is vented.
SIG | 25pts | FW | VL02 | R309-545-15 | Rule requires drinking water storage tanks to
be vented. Overflows cannot be considered or used as vents. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
C
367 Are air vents present? ... if yes, answer the following question(s)Y
367A
Vent is either down-turned or shielded from contaminants (at least 2 inches below the
bottom of the opening)
SIG | 25pts | FW | V005 | R309-545-15(1) | Rule requires inverted vents on water
storage tanks to be down-turned a minimum of 2 inches below any opening and
shielded to prevent the entrance of contaminants. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 62 of 97
367B
End of vent terminates at least 24 inches above earthen cover (buried tank) and is
located and sized to avoid blockage during winter.
MIN | 15pts | FW | V006 | R309-545-15(2) | For buried structures, the rule requires the
end of the vent discharge to be a minimum of 24 inches above the earthen covering.
C
367C
Vent covered with #14 or finer non-corrodible mesh screen.
SIG | 25pts | FW | V007 | R309-545-15(4) | Rule requires a water storage tank vent to
be fitted with #14 mesh or finer non-corrodible screen and vents 6-inches or greater in
diameter to be fitted with additional heavy gauge screen or substantial covering to
protect the #14 mesh screen from vandalism or damage. This significant deficiency
must be corrected within 120 days of notification or have a compliance action plan
approved by DDW.
C
367D
Vent 6-inch diameter and larger protected with additional heavy-gauge screen or
substantial covering.
MIN | 5pts | FW | V035 | R309-545-15(5) | Rule requires vents that are 6-inch diameter
or greater to be fitted with additional heavy gauge screen or substantial covering,
which will protect the No. 14 mesh screen against vandalism or damage.
C
368 Are access openings present? ... if yes, answer the following question(s)
MIN | 15pts | FW | VL03 | R309-545-14 and 14(1) | Rule requires drinking water
storage tanks to be designed with reasonably convenient access to the interior for
cleaning and maintenance.
Y
368A
Access opening framed at least 4 inches above roof surface or 18 inches above
earthen cover.
MIN | 15pts | FW | V008 | R309-545-14(1) | Rule requires tank access opening to be
framed at least 4 inches above the surface of the roof, or on a buried tank, to be at
least 18 inches above any earthen cover over the tank.
C
368B
Access opening shoe box type with at least 2 inches of overlap
SIG | 25pts | FW | V010 | R309-545-14(2) | Rule requires the frame of an access
opening to be provided with a close fitting solid shoebox type cover which extends
down around the frame at least two inches and is furnished with a gasket(s) between
the lid and frame. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
368C
Access opening lid properly gasketed
SIG | 25pts | FW | V009 | R309-545-14(2) | Rule requires the access opening to a tank
to be furnished with a gasket between the lid and frame. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
369 Access opening locked
SIG | 25pts | FW | V029 | R309-545-14(3) | Rule requires the lid to any access
opening to have a locking device. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 63 of 97
ST008 - MOOSE HOLLOW TANK - Active
370 Roof or wall penetrations sealed
SIG | 100pts | FW | V017 | R309-545-6(1) and 545-9 | Rule requires openings in a
storage tank roof or top, designed to accommodate control apparatus or pump
columns, to be welded, gasketed, or curbed and sleeved and to have additional proper
shielding to prevent vandalism. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
371 Area surrounding ground-level or buried storage tank is graded to prevent surface
water from standing within 50 feet.
SIG | 25pts | TR | V001 | R309-545-7(4) | Rule requires the area surrounding a
ground-level or buried water storage tank be graded in a manner to prevent surface
water from standing within 50 feet of the tank. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
372 Storage tank roof is sloped to prevent ponding
MIN | 15pts | FW | V003 | R309-545-9(4) | Rule requires drainage of storage tank roofs
to eliminate water ponding.
C
373 Are there cracks in the walls or roof of the storage tank? (if yes, select only one of the
following options)
N
374 Is a tank overflow present? ... if yes, answer the following question(s)
SIG | 25pts | FW | VL01 | R309-545-13 | Rule requires all storage tanks to be provided
with an overflow that discharges at an an elevation between 12 and 24 inches above
the ground surface or the rim of the receiving basin. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
Y
374A
Overflow line discharges at least 12 inches above ground or the flood rim of receiving
basin?
SIG | 25pts | FW | V011 | R309-545-13 | Rule requires all water storage tanks to be
provided with an overflow that discharges at an elevation between 12 and 24 inches
above the ground surface or the rim of the receiving basin.
C
374B
Overflow line covered with #4 mesh non-corrodible screen
SIG | 25pts | FW | V012 | R309-545-13(3) | Rule requires overflow pipes to be
screened with #4 mesh non-corrodible screens installed at a location least susceptible
to damage by vandalism. This significant deficiency must be corrected within 120 days
of notification or have a corrective action plan approved by DDW.
C
374C
Overflow line connected or discharges to a sanitary sewer drain?
SIG | 50pts | FW | V013 | R309-545-13(5) | Rule prohibits overflow pipes from
connecting to, or discharging into, a sanitary sewer system. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
375 Are the drain line and overflow combined?Y
376 Is this facility Active or Inactive?A
377 Storage tank capacity in gallons (from SDWIS; if different explain why in the
comments)
200000
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 64 of 97
378 There are no undocumented drinking water facilities (i.e. tanks, pump stations,
treatment facilities, etc.) or recent modifications that have not gone through DDW
review
SIG | 50pts | SM | G001 | R309-100-5(2), R309-500-6, R309-500-9, R309-500-9(2)
and (3) | Rule requires complete plans & specification for all public drinking water
projects to be approved in writing by the Director. Any facility found that has not
started DDW review shall be considered unapproved. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
379 Ladders, ladder guards, platform railings, or safely located entrance hatches are
provided.
MIN | 15pts | FW | V004 | R309-545-18 | Rule requires ladders, ladder guards,
platform railings, and safely located entrance hatches where applicable for water
storage tanks and requires safety practices to conform to pertinent laws and
regulations of the Utah Occupational Safety and Health Division.
C
380 Tank is vented.
SIG | 25pts | FW | VL02 | R309-545-15 | Rule requires drinking water storage tanks to
be vented. Overflows cannot be considered or used as vents. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
C
381 Are air vents present? ... if yes, answer the following question(s)Y
381A
Vent is either down-turned or shielded from contaminants (at least 2 inches below the
bottom of the opening)
SIG | 25pts | FW | V005 | R309-545-15(1) | Rule requires inverted vents on water
storage tanks to be down-turned a minimum of 2 inches below any opening and
shielded to prevent the entrance of contaminants. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
381B
End of vent terminates at least 24 inches above earthen cover (buried tank) and is
located and sized to avoid blockage during winter.
MIN | 15pts | FW | V006 | R309-545-15(2) | For buried structures, the rule requires the
end of the vent discharge to be a minimum of 24 inches above the earthen covering.
C
381C
Vent covered with #14 or finer non-corrodible mesh screen.
SIG | 25pts | FW | V007 | R309-545-15(4) | Rule requires a water storage tank vent to
be fitted with #14 mesh or finer non-corrodible screen and vents 6-inches or greater in
diameter to be fitted with additional heavy gauge screen or substantial covering to
protect the #14 mesh screen from vandalism or damage. This significant deficiency
must be corrected within 120 days of notification or have a compliance action plan
approved by DDW.
C
381D
Vent 6-inch diameter and larger protected with additional heavy-gauge screen or
substantial covering.
MIN | 5pts | FW | V035 | R309-545-15(5) | Rule requires vents that are 6-inch diameter
or greater to be fitted with additional heavy gauge screen or substantial covering,
which will protect the No. 14 mesh screen against vandalism or damage.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 65 of 97
382 Are access openings present? ... if yes, answer the following question(s)
MIN | 15pts | FW | VL03 | R309-545-14 and 14(1) | Rule requires drinking water
storage tanks to be designed with reasonably convenient access to the interior for
cleaning and maintenance.
Y
382A
Access opening framed at least 4 inches above roof surface or 18 inches above
earthen cover.
MIN | 15pts | FW | V008 | R309-545-14(1) | Rule requires tank access opening to be
framed at least 4 inches above the surface of the roof, or on a buried tank, to be at
least 18 inches above any earthen cover over the tank.
C
382B
Access opening shoe box type with at least 2 inches of overlap
SIG | 25pts | FW | V010 | R309-545-14(2) | Rule requires the frame of an access
opening to be provided with a close fitting solid shoebox type cover which extends
down around the frame at least two inches and is furnished with a gasket(s) between
the lid and frame. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
382C
Access opening lid properly gasketed
SIG | 25pts | FW | V009 | R309-545-14(2) | Rule requires the access opening to a tank
to be furnished with a gasket between the lid and frame. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
383 Access opening locked
SIG | 25pts | FW | V029 | R309-545-14(3) | Rule requires the lid to any access
opening to have a locking device. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
384 Roof or wall penetrations sealed
SIG | 100pts | FW | V017 | R309-545-6(1) and 545-9 | Rule requires openings in a
storage tank roof or top, designed to accommodate control apparatus or pump
columns, to be welded, gasketed, or curbed and sleeved and to have additional proper
shielding to prevent vandalism. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
385 Area surrounding ground-level or buried storage tank is graded to prevent surface
water from standing within 50 feet.
SIG | 25pts | TR | V001 | R309-545-7(4) | Rule requires the area surrounding a
ground-level or buried water storage tank be graded in a manner to prevent surface
water from standing within 50 feet of the tank. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
386 Storage tank roof is sloped to prevent ponding
MIN | 15pts | FW | V003 | R309-545-9(4) | Rule requires drainage of storage tank roofs
to eliminate water ponding.
C
387 Are there cracks in the walls or roof of the storage tank? (if yes, select only one of the
following options)
N
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 66 of 97
ST009 - RED PINE TANK - Active
388 Is a tank overflow present? ... if yes, answer the following question(s)
SIG | 25pts | FW | VL01 | R309-545-13 | Rule requires all storage tanks to be provided
with an overflow that discharges at an an elevation between 12 and 24 inches above
the ground surface or the rim of the receiving basin. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
Y
388A
Overflow line discharges at least 12 inches above ground or the flood rim of receiving
basin?
SIG | 25pts | FW | V011 | R309-545-13 | Rule requires all water storage tanks to be
provided with an overflow that discharges at an elevation between 12 and 24 inches
above the ground surface or the rim of the receiving basin.
C
388B
Overflow line covered with #4 mesh non-corrodible screen
SIG | 25pts | FW | V012 | R309-545-13(3) | Rule requires overflow pipes to be
screened with #4 mesh non-corrodible screens installed at a location least susceptible
to damage by vandalism. This significant deficiency must be corrected within 120 days
of notification or have a corrective action plan approved by DDW.
C
388C
Overflow line connected or discharges to a sanitary sewer drain?
SIG | 50pts | FW | V013 | R309-545-13(5) | Rule prohibits overflow pipes from
connecting to, or discharging into, a sanitary sewer system. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
389 Are the drain line and overflow combined?Y
390 Is this facility Active or Inactive?A
391 Storage tank capacity in gallons (from SDWIS; if different explain why in the
comments)
50000
392 There are no undocumented drinking water facilities (i.e. tanks, pump stations,
treatment facilities, etc.) or recent modifications that have not gone through DDW
review
SIG | 50pts | SM | G001 | R309-100-5(2), R309-500-6, R309-500-9, R309-500-9(2)
and (3) | Rule requires complete plans & specification for all public drinking water
projects to be approved in writing by the Director. Any facility found that has not
started DDW review shall be considered unapproved. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
393 Ladders, ladder guards, platform railings, or safely located entrance hatches are
provided.
MIN | 15pts | FW | V004 | R309-545-18 | Rule requires ladders, ladder guards,
platform railings, and safely located entrance hatches where applicable for water
storage tanks and requires safety practices to conform to pertinent laws and
regulations of the Utah Occupational Safety and Health Division.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 67 of 97
394 Tank is vented.
SIG | 25pts | FW | VL02 | R309-545-15 | Rule requires drinking water storage tanks to
be vented. Overflows cannot be considered or used as vents. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
C
395 Are air vents present? ... if yes, answer the following question(s)Y
395A
Vent is either down-turned or shielded from contaminants (at least 2 inches below the
bottom of the opening)
SIG | 25pts | FW | V005 | R309-545-15(1) | Rule requires inverted vents on water
storage tanks to be down-turned a minimum of 2 inches below any opening and
shielded to prevent the entrance of contaminants. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
395B
End of vent terminates at least 24 inches above earthen cover (buried tank) and is
located and sized to avoid blockage during winter.
MIN | 15pts | FW | V006 | R309-545-15(2) | For buried structures, the rule requires the
end of the vent discharge to be a minimum of 24 inches above the earthen covering.
C
395C
Vent covered with #14 or finer non-corrodible mesh screen.
SIG | 25pts | FW | V007 | R309-545-15(4) | Rule requires a water storage tank vent to
be fitted with #14 mesh or finer non-corrodible screen and vents 6-inches or greater in
diameter to be fitted with additional heavy gauge screen or substantial covering to
protect the #14 mesh screen from vandalism or damage. This significant deficiency
must be corrected within 120 days of notification or have a compliance action plan
approved by DDW.
C
395D
Vent 6-inch diameter and larger protected with additional heavy-gauge screen or
substantial covering.
MIN | 5pts | FW | V035 | R309-545-15(5) | Rule requires vents that are 6-inch diameter
or greater to be fitted with additional heavy gauge screen or substantial covering,
which will protect the No. 14 mesh screen against vandalism or damage.
C
396 Are access openings present? ... if yes, answer the following question(s)
MIN | 15pts | FW | VL03 | R309-545-14 and 14(1) | Rule requires drinking water
storage tanks to be designed with reasonably convenient access to the interior for
cleaning and maintenance.
Y
396A
Access opening framed at least 4 inches above roof surface or 18 inches above
earthen cover.
MIN | 15pts | FW | V008 | R309-545-14(1) | Rule requires tank access opening to be
framed at least 4 inches above the surface of the roof, or on a buried tank, to be at
least 18 inches above any earthen cover over the tank.
C
396B
Access opening shoe box type with at least 2 inches of overlap
SIG | 25pts | FW | V010 | R309-545-14(2) | Rule requires the frame of an access
opening to be provided with a close fitting solid shoebox type cover which extends
down around the frame at least two inches and is furnished with a gasket(s) between
the lid and frame. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 68 of 97
396C
Access opening lid properly gasketed
SIG | 25pts | FW | V009 | R309-545-14(2) | Rule requires the access opening to a tank
to be furnished with a gasket between the lid and frame. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
397 Access opening locked
SIG | 25pts | FW | V029 | R309-545-14(3) | Rule requires the lid to any access
opening to have a locking device. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
398 Roof or wall penetrations sealed
SIG | 100pts | FW | V017 | R309-545-6(1) and 545-9 | Rule requires openings in a
storage tank roof or top, designed to accommodate control apparatus or pump
columns, to be welded, gasketed, or curbed and sleeved and to have additional proper
shielding to prevent vandalism. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
399 Area surrounding ground-level or buried storage tank is graded to prevent surface
water from standing within 50 feet.
SIG | 25pts | TR | V001 | R309-545-7(4) | Rule requires the area surrounding a
ground-level or buried water storage tank be graded in a manner to prevent surface
water from standing within 50 feet of the tank. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
400 Storage tank roof is sloped to prevent ponding
MIN | 15pts | FW | V003 | R309-545-9(4) | Rule requires drainage of storage tank roofs
to eliminate water ponding.
C
401 Are there cracks in the walls or roof of the storage tank? (if yes, select only one of the
following options)
N
402 Is a tank overflow present? ... if yes, answer the following question(s)
SIG | 25pts | FW | VL01 | R309-545-13 | Rule requires all storage tanks to be provided
with an overflow that discharges at an an elevation between 12 and 24 inches above
the ground surface or the rim of the receiving basin. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
Y
402A
Overflow line discharges at least 12 inches above ground or the flood rim of receiving
basin?
SIG | 25pts | FW | V011 | R309-545-13 | Rule requires all water storage tanks to be
provided with an overflow that discharges at an elevation between 12 and 24 inches
above the ground surface or the rim of the receiving basin.
C
402B
Overflow line covered with #4 mesh non-corrodible screen
SIG | 25pts | FW | V012 | R309-545-13(3) | Rule requires overflow pipes to be
screened with #4 mesh non-corrodible screens installed at a location least susceptible
to damage by vandalism. This significant deficiency must be corrected within 120 days
of notification or have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 69 of 97
ST010 - RED HAWK TANK - Active
402C
Overflow line connected or discharges to a sanitary sewer drain?
SIG | 50pts | FW | V013 | R309-545-13(5) | Rule prohibits overflow pipes from
connecting to, or discharging into, a sanitary sewer system. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
403 Are the drain line and overflow combined?Y
404 Is this facility Active or Inactive?A
405 Storage tank capacity in gallons (from SDWIS; if different explain why in the
comments)
1100000
406 There are no undocumented drinking water facilities (i.e. tanks, pump stations,
treatment facilities, etc.) or recent modifications that have not gone through DDW
review
SIG | 50pts | SM | G001 | R309-100-5(2), R309-500-6, R309-500-9, R309-500-9(2)
and (3) | Rule requires complete plans & specification for all public drinking water
projects to be approved in writing by the Director. Any facility found that has not
started DDW review shall be considered unapproved. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
407 Ladders, ladder guards, platform railings, or safely located entrance hatches are
provided.
MIN | 15pts | FW | V004 | R309-545-18 | Rule requires ladders, ladder guards,
platform railings, and safely located entrance hatches where applicable for water
storage tanks and requires safety practices to conform to pertinent laws and
regulations of the Utah Occupational Safety and Health Division.
C
408 Tank is vented.
SIG | 25pts | FW | VL02 | R309-545-15 | Rule requires drinking water storage tanks to
be vented. Overflows cannot be considered or used as vents. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
C
409 Are air vents present? ... if yes, answer the following question(s)Y
409A
Vent is either down-turned or shielded from contaminants (at least 2 inches below the
bottom of the opening)
SIG | 25pts | FW | V005 | R309-545-15(1) | Rule requires inverted vents on water
storage tanks to be down-turned a minimum of 2 inches below any opening and
shielded to prevent the entrance of contaminants. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
409B
End of vent terminates at least 24 inches above earthen cover (buried tank) and is
located and sized to avoid blockage during winter.
MIN | 15pts | FW | V006 | R309-545-15(2) | For buried structures, the rule requires the
end of the vent discharge to be a minimum of 24 inches above the earthen covering.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 70 of 97
409C
Vent covered with #14 or finer non-corrodible mesh screen.
SIG | 25pts | FW | V007 | R309-545-15(4) | Rule requires a water storage tank vent to
be fitted with #14 mesh or finer non-corrodible screen and vents 6-inches or greater in
diameter to be fitted with additional heavy gauge screen or substantial covering to
protect the #14 mesh screen from vandalism or damage. This significant deficiency
must be corrected within 120 days of notification or have a compliance action plan
approved by DDW.
C
409D
Vent 6-inch diameter and larger protected with additional heavy-gauge screen or
substantial covering.
MIN | 5pts | FW | V035 | R309-545-15(5) | Rule requires vents that are 6-inch diameter
or greater to be fitted with additional heavy gauge screen or substantial covering,
which will protect the No. 14 mesh screen against vandalism or damage.
C
410 Are access openings present? ... if yes, answer the following question(s)
MIN | 15pts | FW | VL03 | R309-545-14 and 14(1) | Rule requires drinking water
storage tanks to be designed with reasonably convenient access to the interior for
cleaning and maintenance.
Y
410A
Access opening framed at least 4 inches above roof surface or 18 inches above
earthen cover.
MIN | 15pts | FW | V008 | R309-545-14(1) | Rule requires tank access opening to be
framed at least 4 inches above the surface of the roof, or on a buried tank, to be at
least 18 inches above any earthen cover over the tank.
C
410B
Access opening shoe box type with at least 2 inches of overlap
SIG | 25pts | FW | V010 | R309-545-14(2) | Rule requires the frame of an access
opening to be provided with a close fitting solid shoebox type cover which extends
down around the frame at least two inches and is furnished with a gasket(s) between
the lid and frame. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
410C
Access opening lid properly gasketed
SIG | 25pts | FW | V009 | R309-545-14(2) | Rule requires the access opening to a tank
to be furnished with a gasket between the lid and frame. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
411 Access opening locked
SIG | 25pts | FW | V029 | R309-545-14(3) | Rule requires the lid to any access
opening to have a locking device. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
412 Roof or wall penetrations sealed
SIG | 100pts | FW | V017 | R309-545-6(1) and 545-9 | Rule requires openings in a
storage tank roof or top, designed to accommodate control apparatus or pump
columns, to be welded, gasketed, or curbed and sleeved and to have additional proper
shielding to prevent vandalism. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 71 of 97
413 Area surrounding ground-level or buried storage tank is graded to prevent surface
water from standing within 50 feet.
SIG | 25pts | TR | V001 | R309-545-7(4) | Rule requires the area surrounding a
ground-level or buried water storage tank be graded in a manner to prevent surface
water from standing within 50 feet of the tank. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
414 Storage tank roof is sloped to prevent ponding
MIN | 15pts | FW | V003 | R309-545-9(4) | Rule requires drainage of storage tank roofs
to eliminate water ponding.
C
415 Are there cracks in the walls or roof of the storage tank? (if yes, select only one of the
following options)
N
416 Is a tank overflow present? ... if yes, answer the following question(s)
SIG | 25pts | FW | VL01 | R309-545-13 | Rule requires all storage tanks to be provided
with an overflow that discharges at an an elevation between 12 and 24 inches above
the ground surface or the rim of the receiving basin. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
Y
416A
Overflow line discharges at least 12 inches above ground or the flood rim of receiving
basin?
Exception Granted: R309-545-13 Overflow clearance | On October 12, 2015, the
Division of Drinking Water (the Division) received your request for exceptions to Rule
R309-545-13(5), Overflows connected to sewers and R309-545-13, Tank Overflow
clearance.
These rules specifically state that:
•Overflow pipes shall not be connected to, or discharge into any sewer system.
•All water storage tanks shall be provided with an overflow that discharged at an
elevation between 12 and 24 inches above the ground surface of the rim of the
receiving basin.
Summit Water Distribution Company’s Trailside Tank (ST006), Upper Hidden Cove
Tank (ST002), Plat 5 Tank (ST003) and Red Hawk Tank (ST010) have overflow pipes
that are directly connected to the storm system. In all cases the elevation of the
connection to the storm drain is below the elevation of the bottom of the tank
preventing water from backing up into the tank. On this basis, an exception to R309-
545-13(5), Overflows connected to sewers, is hereby granted for the Trailside Tank
(ST006), Upper Hidden Cove Tank (ST002), Plat 5 Tank (ST003) and the Red Hawk
Tank (ST010))
SIG | 25pts | FW | V011 | R309-545-13 | Rule requires all water storage tanks to be
provided with an overflow that discharges at an elevation between 12 and 24 inches
above the ground surface or the rim of the receiving basin.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 72 of 97
ST012 - SPRING CREEK SPRINGS STORAGE - Active
416B
Overflow line covered with #4 mesh non-corrodible screen
SIG | 25pts | FW | V012 | R309-545-13(3) | Rule requires overflow pipes to be
screened with #4 mesh non-corrodible screens installed at a location least susceptible
to damage by vandalism. This significant deficiency must be corrected within 120 days
of notification or have a corrective action plan approved by DDW.
C
416C
Overflow line connected or discharges to a sanitary sewer drain?
SIG | 50pts | FW | V013 | R309-545-13(5) | Rule prohibits overflow pipes from
connecting to, or discharging into, a sanitary sewer system. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
417 Are the drain line and overflow combined?Y
418 Is this facility Active or Inactive?A
419 Storage tank capacity in gallons (from SDWIS; if different explain why in the
comments)
50000
420 There are no undocumented drinking water facilities (i.e. tanks, pump stations,
treatment facilities, etc.) or recent modifications that have not gone through DDW
review
SIG | 50pts | SM | G001 | R309-100-5(2), R309-500-6, R309-500-9, R309-500-9(2)
and (3) | Rule requires complete plans & specification for all public drinking water
projects to be approved in writing by the Director. Any facility found that has not
started DDW review shall be considered unapproved. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
421 Ladders, ladder guards, platform railings, or safely located entrance hatches are
provided.
MIN | 15pts | FW | V004 | R309-545-18 | Rule requires ladders, ladder guards,
platform railings, and safely located entrance hatches where applicable for water
storage tanks and requires safety practices to conform to pertinent laws and
regulations of the Utah Occupational Safety and Health Division.
C
422 Tank is vented.
SIG | 25pts | FW | VL02 | R309-545-15 | Rule requires drinking water storage tanks to
be vented. Overflows cannot be considered or used as vents. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
C
423 Are air vents present? ... if yes, answer the following question(s)Y
423A
Vent is either down-turned or shielded from contaminants (at least 2 inches below the
bottom of the opening)
SIG | 25pts | FW | V005 | R309-545-15(1) | Rule requires inverted vents on water
storage tanks to be down-turned a minimum of 2 inches below any opening and
shielded to prevent the entrance of contaminants. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 73 of 97
423B
End of vent terminates at least 24 inches above earthen cover (buried tank) and is
located and sized to avoid blockage during winter.
MIN | 15pts | FW | V006 | R309-545-15(2) | For buried structures, the rule requires the
end of the vent discharge to be a minimum of 24 inches above the earthen covering.
C
423C
Vent covered with #14 or finer non-corrodible mesh screen.
SIG | 25pts | FW | V007 | R309-545-15(4) | Rule requires a water storage tank vent to
be fitted with #14 mesh or finer non-corrodible screen and vents 6-inches or greater in
diameter to be fitted with additional heavy gauge screen or substantial covering to
protect the #14 mesh screen from vandalism or damage. This significant deficiency
must be corrected within 120 days of notification or have a compliance action plan
approved by DDW.
C
423D
Vent 6-inch diameter and larger protected with additional heavy-gauge screen or
substantial covering.
MIN | 5pts | FW | V035 | R309-545-15(5) | Rule requires vents that are 6-inch diameter
or greater to be fitted with additional heavy gauge screen or substantial covering,
which will protect the No. 14 mesh screen against vandalism or damage.
C
424 Are access openings present? ... if yes, answer the following question(s)
MIN | 15pts | FW | VL03 | R309-545-14 and 14(1) | Rule requires drinking water
storage tanks to be designed with reasonably convenient access to the interior for
cleaning and maintenance.
Y
424A
Access opening framed at least 4 inches above roof surface or 18 inches above
earthen cover.
MIN | 15pts | FW | V008 | R309-545-14(1) | Rule requires tank access opening to be
framed at least 4 inches above the surface of the roof, or on a buried tank, to be at
least 18 inches above any earthen cover over the tank.
C
424B
Access opening shoe box type with at least 2 inches of overlap
SIG | 25pts | FW | V010 | R309-545-14(2) | Rule requires the frame of an access
opening to be provided with a close fitting solid shoebox type cover which extends
down around the frame at least two inches and is furnished with a gasket(s) between
the lid and frame. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
424C
Access opening lid properly gasketed
SIG | 25pts | FW | V009 | R309-545-14(2) | Rule requires the access opening to a tank
to be furnished with a gasket between the lid and frame. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
425 Access opening locked
SIG | 25pts | FW | V029 | R309-545-14(3) | Rule requires the lid to any access
opening to have a locking device. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 74 of 97
PF001 - MOOSE HOLLOW PUMP STATION -- Pump Stations - Active
426 Roof or wall penetrations sealed
SIG | 100pts | FW | V017 | R309-545-6(1) and 545-9 | Rule requires openings in a
storage tank roof or top, designed to accommodate control apparatus or pump
columns, to be welded, gasketed, or curbed and sleeved and to have additional proper
shielding to prevent vandalism. This significant deficiency must be corrected within
120 days of notification or have a corrective action plan approved by DDW.
C
427 Area surrounding ground-level or buried storage tank is graded to prevent surface
water from standing within 50 feet.
SIG | 25pts | TR | V001 | R309-545-7(4) | Rule requires the area surrounding a
ground-level or buried water storage tank be graded in a manner to prevent surface
water from standing within 50 feet of the tank. This significant deficiency must be
corrected within 120 days of notification or have a corrective action plan approved by
DDW.
C
428 Storage tank roof is sloped to prevent ponding
MIN | 15pts | FW | V003 | R309-545-9(4) | Rule requires drainage of storage tank roofs
to eliminate water ponding.
C
429 Are there cracks in the walls or roof of the storage tank? (if yes, select only one of the
following options)
N
430 Is a tank overflow present? ... if yes, answer the following question(s)
SIG | 25pts | FW | VL01 | R309-545-13 | Rule requires all storage tanks to be provided
with an overflow that discharges at an an elevation between 12 and 24 inches above
the ground surface or the rim of the receiving basin. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
Y
430A
Overflow line discharges at least 12 inches above ground or the flood rim of receiving
basin?
SIG | 25pts | FW | V011 | R309-545-13 | Rule requires all water storage tanks to be
provided with an overflow that discharges at an elevation between 12 and 24 inches
above the ground surface or the rim of the receiving basin.
C
430B
Overflow line covered with #4 mesh non-corrodible screen
SIG | 25pts | FW | V012 | R309-545-13(3) | Rule requires overflow pipes to be
screened with #4 mesh non-corrodible screens installed at a location least susceptible
to damage by vandalism. This significant deficiency must be corrected within 120 days
of notification or have a corrective action plan approved by DDW.
C
430C
Overflow line connected or discharges to a sanitary sewer drain?
SIG | 50pts | FW | V013 | R309-545-13(5) | Rule prohibits overflow pipes from
connecting to, or discharging into, a sanitary sewer system. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
431 Are the drain line and overflow combined?Y
432 Is this facility Active or Inactive?A
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 75 of 97
433 There are no undocumented drinking water facilities (i.e. tanks, pump stations,
treatment facilities, etc.) or recent modifications that have not gone through DDW
review
SIG | 50pts | SM | G001 | R309-100-5(2), R309-500-6, R309-500-9, R309-500-9(2)
and (3) | Rule requires complete plans & specification for all public drinking water
projects to be approved in writing by the Director. Any facility found that has not
started DDW review shall be considered unapproved. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
434 Pump Type (Centrifugal, Hand pump, Jet, Positive Displacement, Screw, Submersible,
Vertical turbine)
Vertical turbine
435 If the pump station is used to pressurize the distribution system, does it have at least
two functioning pumping units? ... if yes, answer the following question(s)
SIG | 25pts | PU | PS18 | R309-540-5(4)(b) | Rule states inline booster pumps,
withdrawing water directly from distribution lines without storage and feeding water
directly into distribution lines, shall have at least two pumping units. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
Y
435A
Demand is met by remaining pump(s) when largest pumping unit out of service
SIG | 25pts | PU | PS19 | R309-540-3(a) | Inline booster pumps shall have at least two
pumping units (such that with any one pump out of service, the remaining pump or
pumps shall be capable of providing the peak day demand of the specific portion of
the system serviced). This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
436 Pump station building and equipment are protected from flooding.
MIN | 15pts | PU | PS13 | R309-540-5(1)(a)(ii), R309-540-5(2)(a)(iii) | Pump station
access shall be 6" above surrounding ground and located at least 3’ above 100-year
flood elevation or highest recorded flood elevation; station is accessible at all times
unless it can be taken out of service when inaccessible.
C
437 There are no unprotected cross-connections in the pump station.
SIG | 50pts | PU | PS15 | R309-105-12(1) | Cross connections are not allowed unless
controlled by an approved and properly operating backflow prevention assembly or
device. This significant deficiency must be corrected within 120 days of notification or
have a corrective action plan approved by DDW.
C
438 Discharge piping has a pressure gauge.
MIN | 15pts | PU | PS03 | R309-540-5 (6)(c)(i) | Rule requires that a standard pressure
gauge be installed on the pump discharge line.
C
439 Does the pumping facility have an air relief valve located on the discharge piping? ... if
yes, answer the following question(s)
Y
439A
End of air relief piping downturned
SIG | 25pts | PU | PS12 | R309-550-6(6)(b), R309-540-6(2) | The open end of the air
relief vent pipe from automatic valves shall be provided with a downward elbow. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 76 of 97
PF002 - HIDDEN COVE PUMP STATION -- Pump Stations - Active
439B
End of air relief piping covered with #14 mesh screen
SIG | 25pts | PU | PS10 | R309-550-6(6)(b), R309-540-6(2) | The open end of the air
relief vent pipe from automatic valves shall be provided with a #14 mesh, non-
corrodible screen. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
439C
End of air relief piping terminates at least 6 inches above floor
SIG | 25pts | PU | PS11 | R309-550-6(6)(b), R309-540-6(2) | Rule requires that an air
release valve discharge line terminate a minimum of 6 inches above the floor.
C
440 Pump station properly secured
MIN | 15pts | PU | PS33 | R309-540-5(1)(a)(v) | The pump station is protected to
prevent vandalism and entrance by animals or unauthorized persons.
C
441 Is this facility Active or Inactive?A
442 There are no undocumented drinking water facilities (i.e. tanks, pump stations,
treatment facilities, etc.) or recent modifications that have not gone through DDW
review
SIG | 50pts | SM | G001 | R309-100-5(2), R309-500-6, R309-500-9, R309-500-9(2)
and (3) | Rule requires complete plans & specification for all public drinking water
projects to be approved in writing by the Director. Any facility found that has not
started DDW review shall be considered unapproved. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
443 Pump Type (Centrifugal, Hand pump, Jet, Positive Displacement, Screw, Submersible,
Vertical turbine)
Vertical turbine
444 If the pump station is used to pressurize the distribution system, does it have at least
two functioning pumping units? ... if yes, answer the following question(s)
SIG | 25pts | PU | PS18 | R309-540-5(4)(b) | Rule states inline booster pumps,
withdrawing water directly from distribution lines without storage and feeding water
directly into distribution lines, shall have at least two pumping units. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
Y
444A
Demand is met by remaining pump(s) when largest pumping unit out of service
SIG | 25pts | PU | PS19 | R309-540-3(a) | Inline booster pumps shall have at least two
pumping units (such that with any one pump out of service, the remaining pump or
pumps shall be capable of providing the peak day demand of the specific portion of
the system serviced). This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
445 Pump station building and equipment are protected from flooding.
MIN | 15pts | PU | PS13 | R309-540-5(1)(a)(ii), R309-540-5(2)(a)(iii) | Pump station
access shall be 6" above surrounding ground and located at least 3’ above 100-year
flood elevation or highest recorded flood elevation; station is accessible at all times
unless it can be taken out of service when inaccessible.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 77 of 97
PF003 - PLAT 5 PUMP STATION -- Pump Stations - Active
446 There are no unprotected cross-connections in the pump station.
SIG | 50pts | PU | PS15 | R309-105-12(1) | Cross connections are not allowed unless
controlled by an approved and properly operating backflow prevention assembly or
device. This significant deficiency must be corrected within 120 days of notification or
have a corrective action plan approved by DDW.
C
447 Discharge piping has a pressure gauge.
MIN | 15pts | PU | PS03 | R309-540-5 (6)(c)(i) | Rule requires that a standard pressure
gauge be installed on the pump discharge line.
C
448 Does the pumping facility have an air relief valve located on the discharge piping? ... if
yes, answer the following question(s)
Y
448A
End of air relief piping downturned
SIG | 25pts | PU | PS12 | R309-550-6(6)(b), R309-540-6(2) | The open end of the air
relief vent pipe from automatic valves shall be provided with a downward elbow. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
448B
End of air relief piping covered with #14 mesh screen
SIG | 25pts | PU | PS10 | R309-550-6(6)(b), R309-540-6(2) | The open end of the air
relief vent pipe from automatic valves shall be provided with a #14 mesh, non-
corrodible screen. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
448C
End of air relief piping terminates at least 6 inches above floor
SIG | 25pts | PU | PS11 | R309-550-6(6)(b), R309-540-6(2) | Rule requires that an air
release valve discharge line terminate a minimum of 6 inches above the floor.
C
449 Pump station properly secured
MIN | 15pts | PU | PS33 | R309-540-5(1)(a)(v) | The pump station is protected to
prevent vandalism and entrance by animals or unauthorized persons.
C
450 Is this facility Active or Inactive?A
451 There are no undocumented drinking water facilities (i.e. tanks, pump stations,
treatment facilities, etc.) or recent modifications that have not gone through DDW
review
SIG | 50pts | SM | G001 | R309-100-5(2), R309-500-6, R309-500-9, R309-500-9(2)
and (3) | Rule requires complete plans & specification for all public drinking water
projects to be approved in writing by the Director. Any facility found that has not
started DDW review shall be considered unapproved. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
452 Pump Type (Centrifugal, Hand pump, Jet, Positive Displacement, Screw, Submersible,
Vertical turbine)
Vertical turbine
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 78 of 97
453 If the pump station is used to pressurize the distribution system, does it have at least
two functioning pumping units? ... if yes, answer the following question(s)
SIG | 25pts | PU | PS18 | R309-540-5(4)(b) | Rule states inline booster pumps,
withdrawing water directly from distribution lines without storage and feeding water
directly into distribution lines, shall have at least two pumping units. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
Y
453A
Demand is met by remaining pump(s) when largest pumping unit out of service
SIG | 25pts | PU | PS19 | R309-540-3(a) | Inline booster pumps shall have at least two
pumping units (such that with any one pump out of service, the remaining pump or
pumps shall be capable of providing the peak day demand of the specific portion of
the system serviced). This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
454 Pump station building and equipment are protected from flooding.
MIN | 15pts | PU | PS13 | R309-540-5(1)(a)(ii), R309-540-5(2)(a)(iii) | Pump station
access shall be 6" above surrounding ground and located at least 3’ above 100-year
flood elevation or highest recorded flood elevation; station is accessible at all times
unless it can be taken out of service when inaccessible.
C
455 There are no unprotected cross-connections in the pump station.
SIG | 50pts | PU | PS15 | R309-105-12(1) | Cross connections are not allowed unless
controlled by an approved and properly operating backflow prevention assembly or
device. This significant deficiency must be corrected within 120 days of notification or
have a corrective action plan approved by DDW.
C
456 Discharge piping has a pressure gauge.
MIN | 15pts | PU | PS03 | R309-540-5 (6)(c)(i) | Rule requires that a standard pressure
gauge be installed on the pump discharge line.
C
457 Does the pumping facility have an air relief valve located on the discharge piping? ... if
yes, answer the following question(s)
Y
457A
End of air relief piping downturned
SIG | 25pts | PU | PS12 | R309-550-6(6)(b), R309-540-6(2) | The open end of the air
relief vent pipe from automatic valves shall be provided with a downward elbow. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
457B
End of air relief piping covered with #14 mesh screen
SIG | 25pts | PU | PS10 | R309-550-6(6)(b), R309-540-6(2) | The open end of the air
relief vent pipe from automatic valves shall be provided with a #14 mesh, non-
corrodible screen. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
457C
End of air relief piping terminates at least 6 inches above floor
SIG | 25pts | PU | PS11 | R309-550-6(6)(b), R309-540-6(2) | Rule requires that an air
release valve discharge line terminate a minimum of 6 inches above the floor.
C
458 Pump station properly secured
MIN | 15pts | PU | PS33 | R309-540-5(1)(a)(v) | The pump station is protected to
prevent vandalism and entrance by animals or unauthorized persons.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 79 of 97
PF004 - TRAILSIDE PUMP STATION -- Pump Stations - Active
459 Is this facility Active or Inactive?A
460 There are no undocumented drinking water facilities (i.e. tanks, pump stations,
treatment facilities, etc.) or recent modifications that have not gone through DDW
review
SIG | 50pts | SM | G001 | R309-100-5(2), R309-500-6, R309-500-9, R309-500-9(2)
and (3) | Rule requires complete plans & specification for all public drinking water
projects to be approved in writing by the Director. Any facility found that has not
started DDW review shall be considered unapproved. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
461 Pump Type (Centrifugal, Hand pump, Jet, Positive Displacement, Screw, Submersible,
Vertical turbine)
Vertical turbine
462 If the pump station is used to pressurize the distribution system, does it have at least
two functioning pumping units? ... if yes, answer the following question(s)
SIG | 25pts | PU | PS18 | R309-540-5(4)(b) | Rule states inline booster pumps,
withdrawing water directly from distribution lines without storage and feeding water
directly into distribution lines, shall have at least two pumping units. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
Y
462A
Demand is met by remaining pump(s) when largest pumping unit out of service
SIG | 25pts | PU | PS19 | R309-540-3(a) | Inline booster pumps shall have at least two
pumping units (such that with any one pump out of service, the remaining pump or
pumps shall be capable of providing the peak day demand of the specific portion of
the system serviced). This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
463 Pump station building and equipment are protected from flooding.
MIN | 15pts | PU | PS13 | R309-540-5(1)(a)(ii), R309-540-5(2)(a)(iii) | Pump station
access shall be 6" above surrounding ground and located at least 3’ above 100-year
flood elevation or highest recorded flood elevation; station is accessible at all times
unless it can be taken out of service when inaccessible.
C
464 There are no unprotected cross-connections in the pump station.
SIG | 50pts | PU | PS15 | R309-105-12(1) | Cross connections are not allowed unless
controlled by an approved and properly operating backflow prevention assembly or
device. This significant deficiency must be corrected within 120 days of notification or
have a corrective action plan approved by DDW.
C
465 Discharge piping has a pressure gauge.
MIN | 15pts | PU | PS03 | R309-540-5 (6)(c)(i) | Rule requires that a standard pressure
gauge be installed on the pump discharge line.
C
466 Does the pumping facility have an air relief valve located on the discharge piping? ... if
yes, answer the following question(s)
Y
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 80 of 97
PF005 - RANCH PLACE PUMP STATION -- Pump Stations - Active
466A
End of air relief piping downturned
SIG | 25pts | PU | PS12 | R309-550-6(6)(b), R309-540-6(2) | The open end of the air
relief vent pipe from automatic valves shall be provided with a downward elbow. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
466B
End of air relief piping covered with #14 mesh screen
SIG | 25pts | PU | PS10 | R309-550-6(6)(b), R309-540-6(2) | The open end of the air
relief vent pipe from automatic valves shall be provided with a #14 mesh, non-
corrodible screen. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
466C
End of air relief piping terminates at least 6 inches above floor
SIG | 25pts | PU | PS11 | R309-550-6(6)(b), R309-540-6(2) | Rule requires that an air
release valve discharge line terminate a minimum of 6 inches above the floor.
C
467 Pump station properly secured
MIN | 15pts | PU | PS33 | R309-540-5(1)(a)(v) | The pump station is protected to
prevent vandalism and entrance by animals or unauthorized persons.
C
468 Is this facility Active or Inactive?A
469 There are no undocumented drinking water facilities (i.e. tanks, pump stations,
treatment facilities, etc.) or recent modifications that have not gone through DDW
review
SIG | 50pts | SM | G001 | R309-100-5(2), R309-500-6, R309-500-9, R309-500-9(2)
and (3) | Rule requires complete plans & specification for all public drinking water
projects to be approved in writing by the Director. Any facility found that has not
started DDW review shall be considered unapproved. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
470 Pump Type (Centrifugal, Hand pump, Jet, Positive Displacement, Screw, Submersible,
Vertical turbine)
Vertical turbine
471 If the pump station is used to pressurize the distribution system, does it have at least
two functioning pumping units? ... if yes, answer the following question(s)
SIG | 25pts | PU | PS18 | R309-540-5(4)(b) | Rule states inline booster pumps,
withdrawing water directly from distribution lines without storage and feeding water
directly into distribution lines, shall have at least two pumping units. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
Y
471A
Demand is met by remaining pump(s) when largest pumping unit out of service
SIG | 25pts | PU | PS19 | R309-540-3(a) | Inline booster pumps shall have at least two
pumping units (such that with any one pump out of service, the remaining pump or
pumps shall be capable of providing the peak day demand of the specific portion of
the system serviced). This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 81 of 97
PF006 - IHC PUMP STATION -- Pump Stations - Active
472 Pump station building and equipment are protected from flooding.
MIN | 15pts | PU | PS13 | R309-540-5(1)(a)(ii), R309-540-5(2)(a)(iii) | Pump station
access shall be 6" above surrounding ground and located at least 3’ above 100-year
flood elevation or highest recorded flood elevation; station is accessible at all times
unless it can be taken out of service when inaccessible.
C
473 There are no unprotected cross-connections in the pump station.
SIG | 50pts | PU | PS15 | R309-105-12(1) | Cross connections are not allowed unless
controlled by an approved and properly operating backflow prevention assembly or
device. This significant deficiency must be corrected within 120 days of notification or
have a corrective action plan approved by DDW.
C
474 Discharge piping has a pressure gauge.
MIN | 15pts | PU | PS03 | R309-540-5 (6)(c)(i) | Rule requires that a standard pressure
gauge be installed on the pump discharge line.
C
475 Does the pumping facility have an air relief valve located on the discharge piping? ... if
yes, answer the following question(s)
Y
475A
End of air relief piping downturned
SIG | 25pts | PU | PS12 | R309-550-6(6)(b), R309-540-6(2) | The open end of the air
relief vent pipe from automatic valves shall be provided with a downward elbow. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
475B
End of air relief piping covered with #14 mesh screen
SIG | 25pts | PU | PS10 | R309-550-6(6)(b), R309-540-6(2) | The open end of the air
relief vent pipe from automatic valves shall be provided with a #14 mesh, non-
corrodible screen. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
475C
End of air relief piping terminates at least 6 inches above floor
SIG | 25pts | PU | PS11 | R309-550-6(6)(b), R309-540-6(2) | Rule requires that an air
release valve discharge line terminate a minimum of 6 inches above the floor.
C
476 Pump station properly secured
MIN | 15pts | PU | PS33 | R309-540-5(1)(a)(v) | The pump station is protected to
prevent vandalism and entrance by animals or unauthorized persons.
C
477 Is this facility Active or Inactive?A
478 There are no undocumented drinking water facilities (i.e. tanks, pump stations,
treatment facilities, etc.) or recent modifications that have not gone through DDW
review
SIG | 50pts | SM | G001 | R309-100-5(2), R309-500-6, R309-500-9, R309-500-9(2)
and (3) | Rule requires complete plans & specification for all public drinking water
projects to be approved in writing by the Director. Any facility found that has not
started DDW review shall be considered unapproved. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
479 Pump Type (Centrifugal, Hand pump, Jet, Positive Displacement, Screw, Submersible,
Vertical turbine)
Vertical turbine
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 82 of 97
480 If the pump station is used to pressurize the distribution system, does it have at least
two functioning pumping units? ... if yes, answer the following question(s)
SIG | 25pts | PU | PS18 | R309-540-5(4)(b) | Rule states inline booster pumps,
withdrawing water directly from distribution lines without storage and feeding water
directly into distribution lines, shall have at least two pumping units. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
Y
480A
Demand is met by remaining pump(s) when largest pumping unit out of service
SIG | 25pts | PU | PS19 | R309-540-3(a) | Inline booster pumps shall have at least two
pumping units (such that with any one pump out of service, the remaining pump or
pumps shall be capable of providing the peak day demand of the specific portion of
the system serviced). This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
481 Pump station building and equipment are protected from flooding.
MIN | 15pts | PU | PS13 | R309-540-5(1)(a)(ii), R309-540-5(2)(a)(iii) | Pump station
access shall be 6" above surrounding ground and located at least 3’ above 100-year
flood elevation or highest recorded flood elevation; station is accessible at all times
unless it can be taken out of service when inaccessible.
C
482 There are no unprotected cross-connections in the pump station.
SIG | 50pts | PU | PS15 | R309-105-12(1) | Cross connections are not allowed unless
controlled by an approved and properly operating backflow prevention assembly or
device. This significant deficiency must be corrected within 120 days of notification or
have a corrective action plan approved by DDW.
C
483 Discharge piping has a pressure gauge.
MIN | 15pts | PU | PS03 | R309-540-5 (6)(c)(i) | Rule requires that a standard pressure
gauge be installed on the pump discharge line.
C
484 Does the pumping facility have an air relief valve located on the discharge piping? ... if
yes, answer the following question(s)
Y
484A
End of air relief piping downturned
SIG | 25pts | PU | PS12 | R309-550-6(6)(b), R309-540-6(2) | The open end of the air
relief vent pipe from automatic valves shall be provided with a downward elbow. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
484B
End of air relief piping covered with #14 mesh screen
SIG | 25pts | PU | PS10 | R309-550-6(6)(b), R309-540-6(2) | The open end of the air
relief vent pipe from automatic valves shall be provided with a #14 mesh, non-
corrodible screen. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
484C
End of air relief piping terminates at least 6 inches above floor
SIG | 25pts | PU | PS11 | R309-550-6(6)(b), R309-540-6(2) | Rule requires that an air
release valve discharge line terminate a minimum of 6 inches above the floor.
C
485 Pump station properly secured
MIN | 15pts | PU | PS33 | R309-540-5(1)(a)(v) | The pump station is protected to
prevent vandalism and entrance by animals or unauthorized persons.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 83 of 97
PF007 - RED PINE PUMP STATION -- Pump Stations - Active
486 Is this facility Active or Inactive?A
487 There are no undocumented drinking water facilities (i.e. tanks, pump stations,
treatment facilities, etc.) or recent modifications that have not gone through DDW
review
SIG | 50pts | SM | G001 | R309-100-5(2), R309-500-6, R309-500-9, R309-500-9(2)
and (3) | Rule requires complete plans & specification for all public drinking water
projects to be approved in writing by the Director. Any facility found that has not
started DDW review shall be considered unapproved. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
488 Pump Type (Centrifugal, Hand pump, Jet, Positive Displacement, Screw, Submersible,
Vertical turbine)
Vertical turbine
489 If the pump station is used to pressurize the distribution system, does it have at least
two functioning pumping units? ... if yes, answer the following question(s)
SIG | 25pts | PU | PS18 | R309-540-5(4)(b) | Rule states inline booster pumps,
withdrawing water directly from distribution lines without storage and feeding water
directly into distribution lines, shall have at least two pumping units. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
Y
489A
Demand is met by remaining pump(s) when largest pumping unit out of service
SIG | 25pts | PU | PS19 | R309-540-3(a) | Inline booster pumps shall have at least two
pumping units (such that with any one pump out of service, the remaining pump or
pumps shall be capable of providing the peak day demand of the specific portion of
the system serviced). This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
490 Pump station building and equipment are protected from flooding.
MIN | 15pts | PU | PS13 | R309-540-5(1)(a)(ii), R309-540-5(2)(a)(iii) | Pump station
access shall be 6" above surrounding ground and located at least 3’ above 100-year
flood elevation or highest recorded flood elevation; station is accessible at all times
unless it can be taken out of service when inaccessible.
C
491 There are no unprotected cross-connections in the pump station.
SIG | 50pts | PU | PS15 | R309-105-12(1) | Cross connections are not allowed unless
controlled by an approved and properly operating backflow prevention assembly or
device. This significant deficiency must be corrected within 120 days of notification or
have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 84 of 97
PF008 - SPRINGS PUMP STATION -- Pump Stations - Active
492 Discharge piping has a pressure gauge.
Exception Granted: R309-540-5(6)(c)(i) | The Red Pine Lift Station (PF007) is located
in zone 3 of the system’s network and pumps to Red Pine Storage Tank (ST009) )
which is a 50,000 gallon storage tank open to atmosphere. The system stated a
history of attempting to maintain a pressure gauge on the discharge line, but due to
the high pressures (450 psi) on the line at that point the system, “had many issues
with the discharge piping failing, including the pressure gauge and tee.” The system
had the line re-plumbed recently with high pressure hose to eliminate these types of
failures and has not had a concern since the replacement. When the line was re-
plumb a pressure gauge was not installed.
MIN | 15pts | PU | PS03 | R309-540-5 (6)(c)(i) | Rule requires that a standard pressure
gauge be installed on the pump discharge line.
C
493 Does the pumping facility have an air relief valve located on the discharge piping? ... if
yes, answer the following question(s)
Y
493A
End of air relief piping downturned
SIG | 25pts | PU | PS12 | R309-550-6(6)(b), R309-540-6(2) | The open end of the air
relief vent pipe from automatic valves shall be provided with a downward elbow. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
493B
End of air relief piping covered with #14 mesh screen
SIG | 25pts | PU | PS10 | R309-550-6(6)(b), R309-540-6(2) | The open end of the air
relief vent pipe from automatic valves shall be provided with a #14 mesh, non-
corrodible screen. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
493C
End of air relief piping terminates at least 6 inches above floor
SIG | 25pts | PU | PS11 | R309-550-6(6)(b), R309-540-6(2) | Rule requires that an air
release valve discharge line terminate a minimum of 6 inches above the floor.
C
494 Pump station properly secured
MIN | 15pts | PU | PS33 | R309-540-5(1)(a)(v) | The pump station is protected to
prevent vandalism and entrance by animals or unauthorized persons.
C
495 Is this facility Active or Inactive?A
496 There are no undocumented drinking water facilities (i.e. tanks, pump stations,
treatment facilities, etc.) or recent modifications that have not gone through DDW
review
SIG | 50pts | SM | G001 | R309-100-5(2), R309-500-6, R309-500-9, R309-500-9(2)
and (3) | Rule requires complete plans & specification for all public drinking water
projects to be approved in writing by the Director. Any facility found that has not
started DDW review shall be considered unapproved. This significant deficiency must
be corrected within 120 days of notification or have a corrective action plan approved
by DDW.
C
497 Pump Type (Centrifugal, Hand pump, Jet, Positive Displacement, Screw, Submersible,
Vertical turbine)
Vertical turbine
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 85 of 97
498 If the pump station is used to pressurize the distribution system, does it have at least
two functioning pumping units? ... if yes, answer the following question(s)
SIG | 25pts | PU | PS18 | R309-540-5(4)(b) | Rule states inline booster pumps,
withdrawing water directly from distribution lines without storage and feeding water
directly into distribution lines, shall have at least two pumping units. This significant
deficiency must be corrected within 120 days of notification or have a corrective action
plan approved by DDW.
Y
498A
Demand is met by remaining pump(s) when largest pumping unit out of service
SIG | 25pts | PU | PS19 | R309-540-3(a) | Inline booster pumps shall have at least two
pumping units (such that with any one pump out of service, the remaining pump or
pumps shall be capable of providing the peak day demand of the specific portion of
the system serviced). This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
499 Pump station building and equipment are protected from flooding.
MIN | 15pts | PU | PS13 | R309-540-5(1)(a)(ii), R309-540-5(2)(a)(iii) | Pump station
access shall be 6" above surrounding ground and located at least 3’ above 100-year
flood elevation or highest recorded flood elevation; station is accessible at all times
unless it can be taken out of service when inaccessible.
C
500 There are no unprotected cross-connections in the pump station.
SIG | 50pts | PU | PS15 | R309-105-12(1) | Cross connections are not allowed unless
controlled by an approved and properly operating backflow prevention assembly or
device. This significant deficiency must be corrected within 120 days of notification or
have a corrective action plan approved by DDW.
C
501 Discharge piping has a pressure gauge.
MIN | 15pts | PU | PS03 | R309-540-5 (6)(c)(i) | Rule requires that a standard pressure
gauge be installed on the pump discharge line.
C
502 Does the pumping facility have an air relief valve located on the discharge piping? ... if
yes, answer the following question(s)
Y
502A
End of air relief piping downturned
SIG | 25pts | PU | PS12 | R309-550-6(6)(b), R309-540-6(2) | The open end of the air
relief vent pipe from automatic valves shall be provided with a downward elbow. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
502B
End of air relief piping covered with #14 mesh screen
SIG | 25pts | PU | PS10 | R309-550-6(6)(b), R309-540-6(2) | The open end of the air
relief vent pipe from automatic valves shall be provided with a #14 mesh, non-
corrodible screen. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
502C
End of air relief piping terminates at least 6 inches above floor
SIG | 25pts | PU | PS11 | R309-550-6(6)(b), R309-540-6(2) | Rule requires that an air
release valve discharge line terminate a minimum of 6 inches above the floor.
C
503 Pump station properly secured
MIN | 15pts | PU | PS33 | R309-540-5(1)(a)(v) | The pump station is protected to
prevent vandalism and entrance by animals or unauthorized persons.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 86 of 97
TP006 - CHURCH WELL CHLORINATOR -- Treatment General
TP006 - CHURCH WELL CHLORINATOR -- Treatment - Chlorination General - Active
504 Is system required to provide primary disinfection of ground water source?N
505 Is free chlorine residual monitoring conducted using grab samples or online chlorine
analyzer?
ON
506 Chlorine residual measured at POE is always above minimum requirement (0.2
mg/L)?
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
507 Is online chlorine residual analyzer equipment checked for accuracy quarterly? R309-
525-25(4)
MIN | 15pts | TR | TD75 | Standard Method 334.0 Determination of Residual Chlorine
in Drinking Water Using an Online Chlorine Analyzer. [EPA 815-B-09-013 September
2009 11.1.1.2 Page 13] | Spare parts shall be provided and maintained for all
chlorinators to repair parts subject to wear and breakage.
C
508 Is this facility Active or Inactive?A
509 Is system required to provide primary disinfection? Prompt - If system knows they are
required to chlorinate based on water quality issues and/or knows they are required to
provide a minimum CT then follow-up by DDW is needed.
N
510 When chlorination is required, disinfection has operated uninterrupted during the past
year while supplying drinking water.
SIG | 50pts | TR | TD25 | R309-520-6 | Rule requires continuous disinfection of
groundwater sources that do not consistently meet bacteriological quality standards,
all surface water sources, and groundwater sources under the direct influence of
surface water. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
511 Chlorine (gas & hypochlorite solution, tablets, granules, ) and chemicals used to
generate chlorine solutions and chlorine dioxide meet ANSI/NSF 60.
SIG | 50pts | TR | TD90 | R309-525-11(5), R309-520-6(2) | All chemicals added to
drinking water, including chlorine, chloramines and chemicals used to generate
hypochlorite solutions and chlorine dioxide, shall be certified as complying with
ANSI/NSF Standard 60. This significant deficiency must be corrected within 120 days
of notification or have a corrective action plan approved by DDW.
C
512 If chemical dilution or dissolution is needed, cross-connection control is provided on
water lines feeding solution tanks.
SIG | 50pts | TR | TX07 | R309-525-11(2)(c), R309-525-11(9)(b)(i) to (iv) | Cross
connection control shall be provided on make-up water lines feeding solution tanks.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
513 Water flow rate is measured to control chemical feed?
SIG | 25pts | TR | TD79 | R309-525-11(7)(d)(ii) and (iii), R309-525-11(7)(a)(i) |
Chemical feed rates shall be proportional to flows and a means to measure water flow
rate shall be provided. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 87 of 97
514 Solution tanks and tank refilling line entry points are properly labeled to identify the
chemicals
MIN | 15pts | TR | TG03 | R309-525-11(8)(c)(vii) | Rule requires tanks to be properly
labeled to designate the chemical contained.
C
515 Free chlorine residual test equipment on-site or available?
MIN | 15pts | TR | TD78 | R309-520-7(1)(j) | Rule requires chlorine residual test
equipment available capable of measuring residuals to the nearest 0.1 mg/l in the
range below 0.5 mg/l, to the nearest 0.3 mg/l between 0.5 mg/l and 1.0 mg/l and to the
nearest 0.5 mg/l above 1.0 mg/l.
C
516 Spare parts are available to replace parts subject to wear and breakage
MIN | 15pts | TR | TD75 | Standard Method 334.0 Determination of Residual Chlorine
in Drinking Water Using an Online Chlorine Analyzer. [EPA 815-B-09-013 September
2009 11.1.1.2 Page 13] | Spare parts shall be provided and maintained for all
chlorinators to repair parts subject to wear and breakage.
C
517 Is chlorine chemical dose rate adjusted due to different water demand flow rates
and/or changing water quality?
N
518 Is there a designated chlorine Point of Entry (POE) sample location?
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
519 POE is before first connection/customer?
SIG | 25pts | TR | T028 | R309-215 | R309-215 & R309-520-6(4)(d)
C
520 Chlorine residual records are maintained and available... if yes answer following
SIG | 25pts | TR | T028 | R309-215 | R309-215 & R309-520-6(4)(d)
Y
520A
System is sampling distribution residuals throughout entire distribution system
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
520B
Distribution chlorine residuals meet minimum concentration requirement
SIG | 25pts | TR | T028 | R309-215 | R309-215 & R309-520-6(4)(d)
C
520C
"What is the maximum free chlorine residual measure? This value never exceeds 4.0
mg/L? "
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
520D
System collects at least three distribution chlorine residual samples a week?
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
520E
System is sampling distribution residuals in accordance with monitoring schedule
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
521 Treatment plant properly secured to protect the quality of the treated water. R309-520-
7(2)(f)
SIG | 25pts | SM | A050 | R309-400-11 | If the water system does not comply with the
directive, the Director may assess 25 to 200 points to the water system. Points shall
be assessed based upon the severity of the non-compliance, the threat to public
health and the underlying basis for the original directive.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 88 of 97
TP007 - STORAGE WELL CHLORINATOR -- Treatment - Chlorination General -
522 Daily operating records reflect chemical dosages and total quantities used
SIG | 25pts | MR | TG20 | R309-105-14(3)(a) | Rule requires all water system using
chemical addition or specialized equipment for the treatment of drinking water to
regularly complete operational reports. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
523 Is this facility Active or Inactive?I
523A
Explain why this facility is Inactive (Is this facility in stand-by mode?)stand-by mode
524 Is system required to provide primary disinfection? Prompt - If system knows they are
required to chlorinate based on water quality issues and/or knows they are required to
provide a minimum CT then follow-up by DDW is needed.
N
525 When chlorination is required, disinfection has operated uninterrupted during the past
year while supplying drinking water.
SIG | 50pts | TR | TD25 | R309-520-6 | Rule requires continuous disinfection of
groundwater sources that do not consistently meet bacteriological quality standards,
all surface water sources, and groundwater sources under the direct influence of
surface water. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
526 Chlorine (gas & hypochlorite solution, tablets, granules, ) and chemicals used to
generate chlorine solutions and chlorine dioxide meet ANSI/NSF 60.
SIG | 50pts | TR | TD90 | R309-525-11(5), R309-520-6(2) | All chemicals added to
drinking water, including chlorine, chloramines and chemicals used to generate
hypochlorite solutions and chlorine dioxide, shall be certified as complying with
ANSI/NSF Standard 60. This significant deficiency must be corrected within 120 days
of notification or have a corrective action plan approved by DDW.
C
527 If chemical dilution or dissolution is needed, cross-connection control is provided on
water lines feeding solution tanks.
SIG | 50pts | TR | TX07 | R309-525-11(2)(c), R309-525-11(9)(b)(i) to (iv) | Cross
connection control shall be provided on make-up water lines feeding solution tanks.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
528 Water flow rate is measured to control chemical feed?
SIG | 25pts | TR | TD79 | R309-525-11(7)(d)(ii) and (iii), R309-525-11(7)(a)(i) |
Chemical feed rates shall be proportional to flows and a means to measure water flow
rate shall be provided. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
529 Solution tanks and tank refilling line entry points are properly labeled to identify the
chemicals
MIN | 15pts | TR | TG03 | R309-525-11(8)(c)(vii) | Rule requires tanks to be properly
labeled to designate the chemical contained.
C
530 Free chlorine residual test equipment on-site or available?
MIN | 15pts | TR | TD78 | R309-520-7(1)(j) | Rule requires chlorine residual test
equipment available capable of measuring residuals to the nearest 0.1 mg/l in the
range below 0.5 mg/l, to the nearest 0.3 mg/l between 0.5 mg/l and 1.0 mg/l and to the
nearest 0.5 mg/l above 1.0 mg/l.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 89 of 97
TP010 - SPRINGS CHLORINATOR -- Treatment - Chlorination General -
531 Spare parts are available to replace parts subject to wear and breakage
MIN | 15pts | TR | TD75 | Standard Method 334.0 Determination of Residual Chlorine
in Drinking Water Using an Online Chlorine Analyzer. [EPA 815-B-09-013 September
2009 11.1.1.2 Page 13] | Spare parts shall be provided and maintained for all
chlorinators to repair parts subject to wear and breakage.
C
532 Is chlorine chemical dose rate adjusted due to different water demand flow rates
and/or changing water quality?
N
533 Is there a designated chlorine Point of Entry (POE) sample location?
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
534 POE is before first connection/customer?
SIG | 25pts | TR | T028 | R309-215 | R309-215 & R309-520-6(4)(d)
C
535 Chlorine residual records are maintained and available... if yes answer following
SIG | 25pts | TR | T028 | R309-215 | R309-215 & R309-520-6(4)(d)
Y
535A
System is sampling distribution residuals throughout entire distribution system
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
535B
Distribution chlorine residuals meet minimum concentration requirement
SIG | 25pts | TR | T028 | R309-215 | R309-215 & R309-520-6(4)(d)
C
535C
"What is the maximum free chlorine residual measure? This value never exceeds 4.0
mg/L? "
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
535D
System collects at least three distribution chlorine residual samples a week?
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
535E
System is sampling distribution residuals in accordance with monitoring schedule
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
536 Treatment plant properly secured to protect the quality of the treated water. R309-520-
7(2)(f)
SIG | 25pts | SM | A050 | R309-400-11 | If the water system does not comply with the
directive, the Director may assess 25 to 200 points to the water system. Points shall
be assessed based upon the severity of the non-compliance, the threat to public
health and the underlying basis for the original directive.
C
537 Daily operating records reflect chemical dosages and total quantities used
SIG | 25pts | MR | TG20 | R309-105-14(3)(a) | Rule requires all water system using
chemical addition or specialized equipment for the treatment of drinking water to
regularly complete operational reports. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
538 Is this facility Active or Inactive?I
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 90 of 97
538A
Explain why this facility is Inactive (Is this facility in stand-by mode?)stand-by mode
539 Is system required to provide primary disinfection? Prompt - If system knows they are
required to chlorinate based on water quality issues and/or knows they are required to
provide a minimum CT then follow-up by DDW is needed.
Y
539A
If yes, no new connections have been added prior to approved first connection that
would change the disinfection CT calculation.
SIG | 50pts | TR | TD26 | R309-505-7(2), R309-520-4 and 6(4) | Point of application of
disinfectants shall be at a location that will achieve the required disinfection CT prior to
the first service connection. This significant deficiency must be corrected within 120
days of notification or have a corrective action plan approved by DDW.
C
540 When chlorination is required, disinfection has operated uninterrupted during the past
year while supplying drinking water.
SIG | 50pts | TR | TD25 | R309-520-6 | Rule requires continuous disinfection of
groundwater sources that do not consistently meet bacteriological quality standards,
all surface water sources, and groundwater sources under the direct influence of
surface water. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
541 Chlorine (gas & hypochlorite solution, tablets, granules, ) and chemicals used to
generate chlorine solutions and chlorine dioxide meet ANSI/NSF 60.
SIG | 50pts | TR | TD90 | R309-525-11(5), R309-520-6(2) | All chemicals added to
drinking water, including chlorine, chloramines and chemicals used to generate
hypochlorite solutions and chlorine dioxide, shall be certified as complying with
ANSI/NSF Standard 60. This significant deficiency must be corrected within 120 days
of notification or have a corrective action plan approved by DDW.
C
542 If chemical dilution or dissolution is needed, cross-connection control is provided on
water lines feeding solution tanks.
SIG | 50pts | TR | TX07 | R309-525-11(2)(c), R309-525-11(9)(b)(i) to (iv) | Cross
connection control shall be provided on make-up water lines feeding solution tanks.
This significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
543 Water flow rate is measured to control chemical feed?
SIG | 25pts | TR | TD79 | R309-525-11(7)(d)(ii) and (iii), R309-525-11(7)(a)(i) |
Chemical feed rates shall be proportional to flows and a means to measure water flow
rate shall be provided. This significant deficiency must be corrected within 120 days of
notification or have a corrective action plan approved by DDW.
C
544 Solution tanks and tank refilling line entry points are properly labeled to identify the
chemicals
MIN | 15pts | TR | TG03 | R309-525-11(8)(c)(vii) | Rule requires tanks to be properly
labeled to designate the chemical contained.
C
545 Free chlorine residual test equipment on-site or available?
MIN | 15pts | TR | TD78 | R309-520-7(1)(j) | Rule requires chlorine residual test
equipment available capable of measuring residuals to the nearest 0.1 mg/l in the
range below 0.5 mg/l, to the nearest 0.3 mg/l between 0.5 mg/l and 1.0 mg/l and to the
nearest 0.5 mg/l above 1.0 mg/l.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 91 of 97
TP006 - CHURCH WELL CHLORINATOR -- Gaseous Chlorination - Active
546 Spare parts are available to replace parts subject to wear and breakage
MIN | 15pts | TR | TD75 | Standard Method 334.0 Determination of Residual Chlorine
in Drinking Water Using an Online Chlorine Analyzer. [EPA 815-B-09-013 September
2009 11.1.1.2 Page 13] | Spare parts shall be provided and maintained for all
chlorinators to repair parts subject to wear and breakage.
C
547 Is chlorine chemical dose rate adjusted due to different water demand flow rates
and/or changing water quality?
N
548 Is there a designated chlorine Point of Entry (POE) sample location?
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
549 POE is before first connection/customer?
SIG | 25pts | TR | T028 | R309-215 | R309-215 & R309-520-6(4)(d)
C
550 Chlorine residual records are maintained and available... if yes answer following
SIG | 25pts | TR | T028 | R309-215 | R309-215 & R309-520-6(4)(d)
Y
550A
System is sampling distribution residuals throughout entire distribution system
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
550B
Distribution chlorine residuals meet minimum concentration requirement
SIG | 25pts | TR | T028 | R309-215 | R309-215 & R309-520-6(4)(d)
C
550C
"What is the maximum free chlorine residual measure? This value never exceeds 4.0
mg/L? "
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
550D
System collects at least three distribution chlorine residual samples a week?
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
550E
System is sampling distribution residuals in accordance with monitoring schedule
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
551 Treatment plant properly secured to protect the quality of the treated water. R309-520-
7(2)(f)
SIG | 25pts | SM | A050 | R309-400-11 | If the water system does not comply with the
directive, the Director may assess 25 to 200 points to the water system. Points shall
be assessed based upon the severity of the non-compliance, the threat to public
health and the underlying basis for the original directive.
C
552 Daily operating records reflect chemical dosages and total quantities used
SIG | 25pts | MR | TG20 | R309-105-14(3)(a) | Rule requires all water system using
chemical addition or specialized equipment for the treatment of drinking water to
regularly complete operational reports. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
553 Is this facility Active or Inactive?A
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 92 of 97
554 If disinfection is required, standby chlorination equipment of sufficient capacity is
available to replace the largest unit.
SIG | 25pts | TR | TD22 | R309-520-7(1)(k)(ii) | Where chlorination is required for
disinfection of the water supply, the rule requires standby equipment of sufficient
capacity to be available to replace the largest unit in the event of its failure. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
555 Is the chlorinator room heated and has the ability to be protected from excessive heat?
MIN | 15pts | TR | TD08 | R309-520-7(1)(l) | Rule requires chlorinator buildings to be
heated, lighted, and ventilated as necessary to assure proper operation of the
equipment and safety of the operators.
C
556 If continuous disinfection is needed, automatic switch over of chlorine cylinders is
provided.
MIN | 15pts | TR | TD01 | R309-520-7(2)(a), R309-520-6(1) | Rule requires automatic
switch over of chlorine cylinders be provided if continuous disinfection is required.
C
557 Exhaust fan takes suction near the floor as far as practical from the door and air inlet,
and discharges outside away from air inlets.
MIN | 15pts | TR | TD09 | R309-520-7(2)(d)(iii) | Rule requires a chlorine room exhaust
fan to take suction inside the chlorine room near the floor, as far as practical from the
door and air inlet, and discharge air outside of the building away from air inlets.
C
558 Air inlets are located near the ceiling and fitted with louvers.
MIN | 15pts | TR | TD10 | R309-520-7(2)(d)(iv) | Rule requires chlorine room air inlets
to be through wall louvers near the ceiling.
C
559 Chlorine vent line discharges outside and above grade and is screened with #14 mesh
screen.
SIG | 25pts | TR | TD13 | R309-520-7(2)(e) | Rule requires the chlorine vent line to
discharge outside, above grade, at a point least susceptible to vandalism, and to have
the end covered with a #14 mesh non-corrodible screen. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
560 Separate switches for chlorine room fans and lights are located near the entrance to
the room (or are located outside the chlorine room if housed in a water treatment
plant).
MIN | 15pts | TR | TD12 | R309-520-7(2)(d)(v) | Rule requires separate switches for
the chlorine room fans and lights to be located near the entrance to the room and to
be protected from vandalism. The switches are required to be located outside the
chlorine room if housed in a water treatment plant.
C
561 Chlorine cylinder is restrained in position to prevent upset.
SIG | 25pts | TR | TD15 | R309-520-7(2)(h) | Rule requires chlorine cylinders to be
restrained in position to prevent upset. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
562 Chlorine cylinder is not stored in direct sunlight or exposed to excessive heat.
SIG | 25pts | TR | TD17 | R309-520-7(2)(f)(ii) | Rule prohibits chlorine cylinders from
being stored in direct sunlight or exposed to excessive heat. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 93 of 97
TP007 - STORAGE WELL CHLORINATOR -- Gaseous Chlorination -
563 Weight scale is provided for weighing chlorine gas cylinders/containers.
SIG | 25pts | TR | TD02 | R309-520-7(2)(i) | Rule requires scales to be provided for
determining chlorine cylinder weight. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
564 Is the chlorine cylinder 150 pounds in capacity? ... if yes, answer the following
question(s)
Y
564A
Leak response/repair plan available
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
564B
Bottle of ammonium hydroxide (56 % ammonia solution) is available for chlorine leak
detection
MIN | 15pts | TR | TD14 | R309-520-7(2)(l)(i) | Rule requires a bottle of ammonium
hydroxide (56% ammonia solution) to be available for leak detection.
C
564C
Immediate access to NIOSH respirator available
SIG | 25pts | TR | TD04 | R309-520-7(2)(k)(ii) | Where 150 pound chlorine cylinders
are used, a respirator recommended the National Institute of Occupational Safety and
Health must be available. This significant deficiency must be corrected within 120 days
of notification or have a corrective action plan approved by DDW.
C
565 Is the chlorine cylinder 1 ton in capacity? ... if yes, answer the following question(s)N
566 Is the (daily) scale weight or volume data recorded? Explain where in the comments...
SIG | 25pts | TR | TD02 | R309-520-7(2)(i) | Rule requires scales to be provided for
determining chlorine cylinder weight. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
567 Is this facility Active or Inactive?I
567A
Explain why this facility is Inactive (Is this facility in stand-by mode?)stand-by mode
568 If disinfection is required, standby chlorination equipment of sufficient capacity is
available to replace the largest unit.
SIG | 25pts | TR | TD22 | R309-520-7(1)(k)(ii) | Where chlorination is required for
disinfection of the water supply, the rule requires standby equipment of sufficient
capacity to be available to replace the largest unit in the event of its failure. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
569 Is the chlorinator room heated and has the ability to be protected from excessive heat?
MIN | 15pts | TR | TD08 | R309-520-7(1)(l) | Rule requires chlorinator buildings to be
heated, lighted, and ventilated as necessary to assure proper operation of the
equipment and safety of the operators.
C
570 If continuous disinfection is needed, automatic switch over of chlorine cylinders is
provided.
MIN | 15pts | TR | TD01 | R309-520-7(2)(a), R309-520-6(1) | Rule requires automatic
switch over of chlorine cylinders be provided if continuous disinfection is required.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 94 of 97
TP010 - SPRINGS CHLORINATOR -- Gaseous Chlorination -
571 Exhaust fan takes suction near the floor as far as practical from the door and air inlet,
and discharges outside away from air inlets.
MIN | 15pts | TR | TD09 | R309-520-7(2)(d)(iii) | Rule requires a chlorine room exhaust
fan to take suction inside the chlorine room near the floor, as far as practical from the
door and air inlet, and discharge air outside of the building away from air inlets.
C
572 Air inlets are located near the ceiling and fitted with louvers.
MIN | 15pts | TR | TD10 | R309-520-7(2)(d)(iv) | Rule requires chlorine room air inlets
to be through wall louvers near the ceiling.
C
573 Chlorine vent line discharges outside and above grade and is screened with #14 mesh
screen.
SIG | 25pts | TR | TD13 | R309-520-7(2)(e) | Rule requires the chlorine vent line to
discharge outside, above grade, at a point least susceptible to vandalism, and to have
the end covered with a #14 mesh non-corrodible screen. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
574 Separate switches for chlorine room fans and lights are located near the entrance to
the room (or are located outside the chlorine room if housed in a water treatment
plant).
MIN | 15pts | TR | TD12 | R309-520-7(2)(d)(v) | Rule requires separate switches for
the chlorine room fans and lights to be located near the entrance to the room and to
be protected from vandalism. The switches are required to be located outside the
chlorine room if housed in a water treatment plant.
C
575 Chlorine cylinder is restrained in position to prevent upset.
SIG | 25pts | TR | TD15 | R309-520-7(2)(h) | Rule requires chlorine cylinders to be
restrained in position to prevent upset. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
D (Notes: No chlorine cylinder in place)
576 Chlorine cylinder is not stored in direct sunlight or exposed to excessive heat.
SIG | 25pts | TR | TD17 | R309-520-7(2)(f)(ii) | Rule prohibits chlorine cylinders from
being stored in direct sunlight or exposed to excessive heat. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
NA (Notes: No chlorine cylinder in place)
577 Weight scale is provided for weighing chlorine gas cylinders/containers.
SIG | 25pts | TR | TD02 | R309-520-7(2)(i) | Rule requires scales to be provided for
determining chlorine cylinder weight. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
578 Is the chlorine cylinder 150 pounds in capacity? ... if yes, answer the following
question(s)
N
579 Is the chlorine cylinder 1 ton in capacity? ... if yes, answer the following question(s)N
580 Is the (daily) scale weight or volume data recorded? Explain where in the comments...
SIG | 25pts | TR | TD02 | R309-520-7(2)(i) | Rule requires scales to be provided for
determining chlorine cylinder weight. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
NA (Notes: No chlorine cylinder in place)
581 Is this facility Active or Inactive?I
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 95 of 97
581A
Explain why this facility is Inactive (Is this facility in stand-by mode?)stand-by mode
582 If disinfection is required, standby chlorination equipment of sufficient capacity is
available to replace the largest unit.
SIG | 25pts | TR | TD22 | R309-520-7(1)(k)(ii) | Where chlorination is required for
disinfection of the water supply, the rule requires standby equipment of sufficient
capacity to be available to replace the largest unit in the event of its failure. This
significant deficiency must be corrected within 120 days of notification or have a
corrective action plan approved by DDW.
C
583 Is the chlorinator room heated and has the ability to be protected from excessive heat?
MIN | 15pts | TR | TD08 | R309-520-7(1)(l) | Rule requires chlorinator buildings to be
heated, lighted, and ventilated as necessary to assure proper operation of the
equipment and safety of the operators.
C
584 If continuous disinfection is needed, automatic switch over of chlorine cylinders is
provided.
MIN | 15pts | TR | TD01 | R309-520-7(2)(a), R309-520-6(1) | Rule requires automatic
switch over of chlorine cylinders be provided if continuous disinfection is required.
C
585 Exhaust fan takes suction near the floor as far as practical from the door and air inlet,
and discharges outside away from air inlets.
MIN | 15pts | TR | TD09 | R309-520-7(2)(d)(iii) | Rule requires a chlorine room exhaust
fan to take suction inside the chlorine room near the floor, as far as practical from the
door and air inlet, and discharge air outside of the building away from air inlets.
C
586 Air inlets are located near the ceiling and fitted with louvers.
MIN | 15pts | TR | TD10 | R309-520-7(2)(d)(iv) | Rule requires chlorine room air inlets
to be through wall louvers near the ceiling.
C
587 Chlorine vent line discharges outside and above grade and is screened with #14 mesh
screen.
SIG | 25pts | TR | TD13 | R309-520-7(2)(e) | Rule requires the chlorine vent line to
discharge outside, above grade, at a point least susceptible to vandalism, and to have
the end covered with a #14 mesh non-corrodible screen. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
588 Separate switches for chlorine room fans and lights are located near the entrance to
the room (or are located outside the chlorine room if housed in a water treatment
plant).
MIN | 15pts | TR | TD12 | R309-520-7(2)(d)(v) | Rule requires separate switches for
the chlorine room fans and lights to be located near the entrance to the room and to
be protected from vandalism. The switches are required to be located outside the
chlorine room if housed in a water treatment plant.
C
589 Chlorine cylinder is restrained in position to prevent upset.
SIG | 25pts | TR | TD15 | R309-520-7(2)(h) | Rule requires chlorine cylinders to be
restrained in position to prevent upset. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 96 of 97
590 Chlorine cylinder is not stored in direct sunlight or exposed to excessive heat.
SIG | 25pts | TR | TD17 | R309-520-7(2)(f)(ii) | Rule prohibits chlorine cylinders from
being stored in direct sunlight or exposed to excessive heat. This significant deficiency
must be corrected within 120 days of notification or have a corrective action plan
approved by DDW.
C
591 Weight scale is provided for weighing chlorine gas cylinders/containers.
SIG | 25pts | TR | TD02 | R309-520-7(2)(i) | Rule requires scales to be provided for
determining chlorine cylinder weight. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
592 Is the chlorine cylinder 150 pounds in capacity? ... if yes, answer the following
question(s)
Y
592A
Leak response/repair plan available
MIN | 15pts | TR | TGR9 | R309-105-7, 8 & 18, R309-100 through 605 | Trigger for
regulatory followup to address concerns.
C
592B
Bottle of ammonium hydroxide (56 % ammonia solution) is available for chlorine leak
detection
MIN | 15pts | TR | TD14 | R309-520-7(2)(l)(i) | Rule requires a bottle of ammonium
hydroxide (56% ammonia solution) to be available for leak detection.
C
592C
Immediate access to NIOSH respirator available
SIG | 25pts | TR | TD04 | R309-520-7(2)(k)(ii) | Where 150 pound chlorine cylinders
are used, a respirator recommended the National Institute of Occupational Safety and
Health must be available. This significant deficiency must be corrected within 120 days
of notification or have a corrective action plan approved by DDW.
C
593 Is the chlorine cylinder 1 ton in capacity? ... if yes, answer the following question(s)N
594 Is the (daily) scale weight or volume data recorded? Explain where in the comments...
SIG | 25pts | TR | TD02 | R309-520-7(2)(i) | Rule requires scales to be provided for
determining chlorine cylinder weight. This significant deficiency must be corrected
within 120 days of notification or have a corrective action plan approved by DDW.
C
DEQ | Drinking Water
Run Date: 08/25/2024 14:57:44 | Rating: Approved UTAH22059 SUMMIT WATER DISTRIBUTION COMPANY page 97 of 97