HomeMy WebLinkAboutDERR-2024-010186 SITE VISIT REPORT DATE: 8/21/2024 SITE: Redwood Road Dump VCP #121 SITE ADDRESS: 1850 West Indiana Avenue, Salt Lake City, UT PREPARED BY: Allison Stanley Utah Department of Environmental Quality Division of Environmental Response and Remediation 195 North 1950 West Salt Lake City, UT 84116 ATTENDEES: Allison Stanley (DERR) ARRIVAL TIME: 2:45 PM - DEPARTURE TIME: 3:30 PM Is the work being performed in a manner consistent with the accepted workplan? Yes SUMMARY: This was a routine site visit by the DERR to check on the status of the cleanup and construction happening at the Site. The asphalt pad has been removed and work was underway to dig up the underlying soil. The operator excavating the soil confirmed that the soil was not being moved but instead stockpiled in place until sampling can confirm that the material is clean and can be moved to the west adjoining property. At the time of the visit, not all of the soil had been excavated yet. Due to the removal of the asphalt pad, the entrance to the Site was moved slightly to the east. Stormwater control measures were in place such as an adequate vehicle track-out leaving the Site and a water truck actively spraying down the soil. The VIMS installation is complete at the Pavilion and crews were actively putting up the frame of the building. This is the only building at the Site currently. To the south-east, crews were digging trenches along the boarder of the Site for utilities. Most of the Site is graded and at the appropriate elevation, with some areas still needing to be addressed. For the north-east corner adjacent to the Alvie Carter Trust property, more fill material is needed to reach the final Site grade; however, the fill already in place is at least a few feet above the adjoining property. A final grade at an elevation above adjoining properties will help prevent impacts to the Site via stormwater runoff, debris, and sediment migration. PHOTO LOG: Photo 1: Track-out leaving the Site. Photo 2: Removal of soil underneath the asphalt pad. Photo 3: The excavated soil from underneath the asphalt pad is stockpiled in place while it is sampled. Photo 4: Installation of the VIMS is complete at the Pavilion and crews are putting up the frame of the building. Photo 5: Water truck is spraying down the soil at the Site. Photo 6: North-east corner of the Site where final grade still needs to be completed. Photo 7: Trench along the east corner (looking south). Photo 8: The final grade of the Site will be at an elevation higher than the adjoining properties (Alvie Carter Trust property to the right). Photo 9: Most of the Site is at the final grade with some areas needing additional fill. Photo 10: Westernmost detention basin near the entrance of the Site. Photo 11: Stockpiled soil from the westernmost detention basin.