Water Line Extension to Clear Sky Resort;
Cannonville Town Water System
System #09003, File #13341
July 24, 2024
PWS System As-built Certification:
Field verification of the water line extension on July 22-July 24, 2024 verified that Clear
Sky Resorts constructed 8,000 lineal feet of 8-inch diameter PVC C900 pipe to provide
service to a new resort called Clear Sky Resort. Isolation valves and air relief valves
were installed at the stationing shown on C-117 and C-118.
A 4’’ water meter was installed by the Town of Cannonville at the end of the water main
extension at STA 8+000. A flushing valve for sampling has also been provided.
The water main alignment was modified from the plan approval along the alignment
shown on C-117 and C-118 with the approval of the Town of Cannonville Water System
and the private landowners.
Megalug restrained joints were utilized for the thrust restraining system per the
Cannonville Town Water System standard specifications. Minimum soil cover of 4 feet
was maintained along the entire length of the water main extension.
The watermain was disinfected with the continuous feed method utilizing calcium
hypochlorite granules placed at 200-foot intervals with a 24-hour holding time prior to
flushing.
Two consecutive bacteriological samples were collected more than 16 hours apart on
and analyzed by Southern Utah University Water Laboratory. Both samples were absent
from total coliform.
Pressure testing of the water main extension was conducted in January of 2024 by E&L
Design Build at 200 psi by isolating sections using the installed isolation valves. No
leakage was detected.
The water main construction included one underground water course crossing under the
Paria River Channel. The underwater crossing was constructed using megalug
restrained joints. Isolation valves and sample taps have been provided on both sides of
the water crossing at locations not subject to high ground water or flooding.
Cannonville Town Water System – Main extension
State of Utah Department of Environmental Quality Division of Drinking Water
Page 2 of 2
I, William Anderson, PE, provisionally certify that the Water Line Extension to Clear Sky
Resort, Cannonville Town Water System been installed per the approved plans, with
modifications as noted here in and completion of the punch list items noted in my July
18, 2024 provisional certification.
7/23/2024
Attachments:
• Revised sheets C-117 and C-118
• Field Observation Photos July 22-23, 2024