HomeMy WebLinkAboutDDW-2024-008922
195 North 1950 West • Salt Lake City, UT
Mailing Address: P.O. Box 144830 • Salt Lake City, UT 84114-4830
Telephone (801) 536-4200 • Fax (801) 536-4211 • T.D.D. (801) 536-4284
www.deq.utah.gov
Printed on 100% recycled paper
State of Utah
Drinking Water Board
Kristi Bell, Chair
Eric Franson, P.E., Vice-Chair
Dawn Ramsey
Justin Maughan
Corinna Harris
Jeff Coombs
Shazelle Terry
Blake Tullis, Ph.D.
Kimberly D. Shelley
Nathan Lunstad
Executive Secretary
SPENCER J. COX
Governor
DEIDRE HENDERSON
Lieutenant Governor
Department of
Environmental Quality
Kimberly D. Shelley
Executive Director
DIVISION OF DRINKING WATER
Nathan Lunstad
Director
Stephen Brown, President realtorstevebrown@gmail.com
Foothill Water Users Association
2268 North Cottontail Dr.
Cedar City, Utah 84721
Subject: Federal SRF Loan Authorization; Foothill Water Users Association, System #11099,
Loan #3F2006
Dear Steve Brown:
On November 7, 2023, the Drinking Water Board authorized a loan of $603,030, with $181,030 in
principal forgiveness, for a net repayable amount of $422,000 for 40 years at 0% interest to
Foothill Water Users Association for the construction of a new 250,000-gallon tank, resolve well
deficiencies, and to install water meters and fire hydrant risers (hereinafter called the "Project").
On June 25, 2024, the Drinking Water Board authorized an additional $188,554 to the previously
authorized construction loan for a new loan total of $791,554 for 40 years at 0% interest with
$237,554 in principal forgiveness, for a net repayable amount of $554,000, to Foothill Water
Users Association. The financial assistance is subject to the same conditions and requirements as
stated in the authorization letter dated November 28, 2023, to Foothill Water Users Association.
With the signing of the Bipartisan Infrastructure Law on November 15, 2021, there is a new
requirement for Federal SRF projects. The Build America Buy America Act (BABAA) goes into
effect on May 14, 2022. All federal financial assistance recipients that close their assistance
agreement on or after this date will be required to comply. The Utah DWSRF Program has created
an interim Build America Buy America Requirements sheet for your reference. Please note, this
sheet should be included in construction contract documents before a project is advertised for
bids. Also, please be aware that these requirements may change once the Office of Management
and Budget issues final guidance on implementing BABAA requirements.
July 11, 2024
Steven Brown, Foothill
Page 2
If you have any questions, please contact Kjori Shelley at (385) 227-1638 or me at (801) 674-2563.
Sincerely,
DRINKING WATER BOARD
Michael J. Grange, P.E.
Assistant Executive Secretary
MJG/ks/lr
Enclosures
cc: William Prater, Esq., William L. Prater, LLC, P.O. Box 71368, SLC, UT 84171, bill@billprater.com
Curtis Nielson, Ensign Engineering & Land Surveying, cnielson@ensignutah.com
Richard Chamberlain, Chamberlain Associates, rchamberlain13@gmail.com
Kjori Shelley, Division of Drinking Water, kashelley@utah.gov
Paul Wright, DEQ District Engineer, pwright@utah.gov
DDW Finance
July 11, 2024