HomeMy WebLinkAboutDDW-2024-008784July 9, 2024
Jamie Grandpre
Tooele City
90 North Main Street
Tooele City, Utah 84074
Subject:Plan Approval, 3100 North and SR-36 Backbone Water Line (DS001);
Tooele City, System #23004, File #15419
Dear Jamie Grandpre:The Division of Drinking Water (the Division) received the plans and specifications for the proposed 3100 North and SR-36 Backbone Water Line (DS001) from you on
June 27, 2024.This project has met the conditions for receiving a plan approval.
Our understanding of the project includes the following:
The project includes the installation of approximately 22 fire hydrants, 2,600 feet of 8-inch and 16-inch diameter C900 PVC, and other appurtenances. This part of the project will not
be connected to the drinking water system until a later phase is completed. This is the first phase of a multi-phase project to connect this area to the Tooele City public water system.
The project is anticipated to add approximately 311 ERCs during the initial phase. The entire Perry Development is estimated to add 6,470 ERCs plus another 2,627 ERCs in other areas
for 9,097 ERCs. Additional source capacity, storage capacity, and transmission will be required to serve these connections into full build-out while meeting minimum requirements.
A hydraulic modeling analysis certification stamped and signed by Katie Gibson Jacobsen, P.E., dated May 29, 2024, was received for this project.
The water lines are identified as DS001 in the Division’s database.
We have completed our review of the plans and specifications, stamped, and signed byThomas M. Romney, P.E., dated May 13, 2024,and find they basically comply with the applicable portions
of Utah’s Administrative Rules for Public Drinking Water Systems in R309. On this basis, the plans for 3100 North and SR-36 Backbone Water Line (DS001) are hereby approved.
This approval pertains to construction only. An Operating Permit must be obtained from the Director before 3100 North and SR-36 Backbone Water Line (DS001) may be put into service. A
checklist outlining the items required for operating permit issuance is enclosed for your information.Approvals or permits from the local authority or the county may be necessary before
beginning construction of this project. As the project proceeds, notice of any changes in the approved design, as well as any change affecting the quantity or quality of the delivered
water, must be submitted to the Division. We may also conduct interim and final inspections of this project. Please notify us when actual construction begins so that these inspections
can be scheduled.
This approval must be renewed if construction has not begun or if substantial equipment has not been ordered within one year of the date of this letter.
If you have any questions regarding this approval, please contact Chris Martin, P.E., of this office, at (385) 271-7040, or me at (385) 515-1464.
Sincerely,
Michael Newberry, P.E.
Permitting and Engineering Support Manager
CM/mrn/mdbEnclosures –Operating Permit Checklistcc:Bryan Slade, Tooele County Health Department, bslade@tooelehealth.orgThomas Romney, Focus Engineering and Surveying, tromney@focus-es.comJamie
Grandpre, Tooele City, jamieg@tooelecity.govPaul Hansen, Tooele City, PaulH@tooelecity.govChris Martin, P.E., Division of Drinking Water, cmartin@utah.gov
Brent Arns, Division of Drinking Water, barns@utah.govCMartin 23004 15419 PA - 3100 North and SR-36 Backbone Water Line
Utah Division of Drinking Water ― Checklist for Issuing Operating PermitsWater System Name:System Number: Project Description:File Number:
Items 1 through 8 below must be submitted to the Division and found to be acceptable prior to operating permit issuance (unless a water line project meets the requirements of R309-500-7
and is not required to obtain an Operating Permit).
Distribution lines (not including in-line booster pump stations) requiring Plan Approval may be placed into service prior to submitting all of the following items and receipt of Operating
Permit if the water system has received items 1 and 4 below.☐1.Certification of Rule Conformance by a professional engineer (P.E.) that all conditions of Plan Approval were accomplished,
and if applicable, changes made during construction were in conformance with rules R309-500 through 550☐2.As-built or record drawings incorporating all changes to approved plans and
specifications (unless no changes were made to the previously approved plans during construction)☐3.Confirmation that as-built or record drawings have been received by the water system☐4.Satisfactory
bacteriological samples as evidence of proper disinfection and flushing in accordance with the appropriate ANSI/AWWA standards:
☐ANSI/AWWA C651-14 AWWA Standard for Disinfecting Water MainsTwo consecutive sample sets at least 16 hours apart, none positive (e.g., every 1,200 feet, end-of-line, each branch)☐ANSI/AWWA
C652-11 AWWA Standard for Disinfection of Water-Storage FacilitiesOne or more samples, none positive☐ANSI/AWWA C653-13 AWWA Standard for Disinfection of Water Treatment PlantsTwo consecutive
samples per unit, none positive, no less than 30 minutes apart☐ANSI/AWWA C654-13 AWWA Standard for Disinfection of WellsTwo consecutive samples, none positive, no less than 30 minutes
apart☐5.Water quality data, where appropriate [For example, include raw and finished water data that demonstrate satisfactory performance of the treatment facility; sample should be
taken from a storage tank for residual volatile organic compounds after tank interior re-coating; etc.]☐6.If applicable, all other documentation that may have been required during the
plan review process☐7.If applicable, confirmation that the water system owner has received the O&M manual for the new facility☐8.If applicable, location data of new storage tank, treatment
facility, or source