HomeMy WebLinkAboutDSHW-2014-012929 - 0901a06880499618Division of
Solid and Hazardous Waste
September 29, 2014
SEP 2 9 2014
Mr. Scott T. Anderson, Director
Utah Division of Solid and Hazardous Waste
P.O. Box 144880
Salt Lake City, UT 84114-4880
Re: Five-Year Permit Anniversary Closure Cost Estimate; Closure Notice for Buildings M-47 and M-
603; ATK Launch Systems Inc., Promontory; UTD009081357
Dear Mr. Anderson:
Promontory permit module II.P.3 requires that ATK Launch Systems Inc. (ATK) conduct a detailed
evaluation of the closure cost estimates for the regulated unit, and determine if the annual adjustments for
inflation have been adequate to update the closure cost estimates. A detailed cost estimate has been
completed, and is attached. The closure cost is currently estimated at $692,109 compared to $670,383
reported in our May 2014 annual update.
Permit Module II.0.4 requires that ATK notify the Director prior to closing a facility. This
correspondence also serves notice of ATK's intent to close buildings M-47 and M-603. We are unable to
use these facilities for storage, and ATK will work with the Division to close them and replace them with a
single building which will be identified at a later date.
ATK will work with the Division to update Attachment 5, Closure Plan and Financial Requirements, to
reflect the updated cost estimate along with finalizing the closure plans for the storage facilities and
updating our insurance policies for closure costs. Please refer questions on this correspondence to Blah-
Palmer at (435)863-2430.
/ certify under penalty of law that this document and all attachments were prepared under my direction or
supervision in accordance with a system designed to assure that qualified personnel properly gather and
evaluate the information submitted. Based on my inquiry of the person or persons who manage the system,
or those persons directly responsible for gathering the information, the information submitted is, to the
best of my knowledge and belief true, accurate, and complete. I am aware that there are significant
penalties for submitting false information, including the possibility offine and imprisonment for knowing
violations.
Manager, Environmental Services
cc: Brad Maulding, DSHW
JeffVandel DSHW
David McCleary DSHW
Blair Palmer, ATK
Sincerely,
EarthFax Engineering Group, LLC
Cost Estimate
Project: ATK - Promontory E-501 closure cost estimate
Project*: UC-1023-18
Estimator: RB White
Date: 16-Sep-14
Costs: Means 2005 Environmental Remediation Cost Data, adjusted for inflation, except as otherwise noted
Assume Level C PPE
Item No. Description Means No./Source Units Est. Quan. Unit Price Total Price
1
2
3
4
5
6
7
8
9
10
11
Site prep (CIH)
Site prep (technician)
Load drums
Haul drums to Clean Harbors
Landfill disposal
State disposal fee
Truck washout/decon
Steam clean pad
Rinsate sample collection
Sample analyses, metals
Sample analyses, explosives
33-22-0111 x 2
33-22-0112x2
33-19-0103
33-19-0243
33-19-7214
Utah DEQ
33-19-0311
33-17-0812
Site crew
Chemtech-Ford
Chemtech-Ford
hr
hr
ea
truck-mi
drum
ton
ea
sf
hr
ea
ea
4
8
160
700
160
40
1
1,760
4
1
1
83.44
31.58
3.05
2.26
145.00
28.00
158.00
0.39
65.00
210.00
210.00
SUBTOTAL
Inflation adjustment (see Means 2014 Heavy Construction Cost Data) 1.337
28,501
38,106
Misc. costs as a percent of the inflation-adjusted subtotal:
Mob/demob 5% 1,905
Engineering/permitting 10% 3,811
DSHW oversight 10% 3,811
Contingency 10 % 3,811
TOTAL ESTIMATED COST 51,443
EarthFax Engineering Group, LLC
Cost Estimate
Project: ATK - Promontory M-47 closure cost estimate
Project*: UC-1023-18
Estimator: RB White
Date: 16-Sep-14
Costs: Means 2005 Environmental Remediation Cost Data, adjusted for inflation, except as otherwise noted
Assume Level C PPE
Item No. Description Means No./Source Units Est. Quan. Unit Price Total Price
1
2
3
4
5
6
9
10
11
12
13
14
15
16
17
18
Materials prep (CIH)
Materials prep (technician)
Load waste motor (crane)
Haul motor to burning ground
Off-load motor
Handling evaluation/planning
Motor handling
Disposal at burning ground
Sweep area
Steam clean floor
Load rinsate/sweepings
Load drums
Haul to Clean Harbors
State disposal fee
Sample collection
Sample analyses, metals/exp
33-22-0111 x2
33-22-0112x2
Crew SIWSM
Crew COET2
Crew SIWSM
Site personnel
Site personnel
ATK
33-22-0112x2
33-17-0812
33-19-0103
33-19-0103
33-19-0243
Utah DEQ
33-22-0112x2
Chemtech-Ford
hr
hr
hr
hr
hr
hr
hr
Ib
hr
sf
drum
ea
truck-mi
ton
hr
ea
12
20
8
16
8
80
40
300,000
8
5,680
10
10
350
1
4
2
83.44
31.58
393.57
93.31
393.57
65.00
65.00
0.25
31.58
0.39
4.87
3.05
2.26
28.00
31.58
210.00
1,001
632
3,149
1,493
3,149
5,200
2,600
75,000
253
2,215
49
31
791
28
126
420
SUBTOTAL
Inflation adjustment (see Means 2014 Heavy Construction Cost Data) 1.337
96,135
128,533
Misc. costs as a percent of the inflation-adjusted subtotal:
Mob/demob
Engineering/permitting
DSHW oversight
Contingency
10
6,427
12,853
12,853
12,853
TOTAL ESTIMATED COST 173,519
EarthFax Engineering Group, LLC
Cost Estimate
Project: ATK - Promontory M-136 closure cost estimate
Project* UC-1022-01
Estimator: RB White
Date: 16-Sep-14
Costs: Means 2005 Environmental Remediation Cost Data, adjusted for inflation, except as otherwise noted
Assume Level C PPE
Item No. Description Means No./Source Units Est. Quan. Unit Price Total Price
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
Site prep (CIH)
Site prep (technican)
Treat remaining waste
Excavate contaminated soil
Load soil and burned waste
Haul waste and soil to Clean Harbors
Landfill disposal, waste and soil
State disposal fee, waste and soil
Steam clean burn pans
Load rinsate
Haul rinsate to Clean Harbors
Landfill disposal, rinsate
State disposal fee, rinsate
Demolish pans
Load pan debris
Haul pan debris to Clean Harbors
Landfill disposal, pan debris
State disposal fee, pan debris
Sample collection
Sample analyses, metals
Sample analyses, explosives
Sample analyses, volatiles
33-22-0111 x2
33-22-0112x2
ATK
17-03-0231
17-03-0222
33-19-0221
33-19-7214
Utah DEQ
33-17-0812
33-19-0103
33-19-0243
33-19-7214
Utah DEQ
17-02-0105
17-03-0222
33-19-0221
33-19-7263
Utah DEQ
Site crew
Chemtech-Ford
Chemtech-Ford
Chemtech-Ford
hr
hr
Ib
hr
hr
truck-mi
ton
ton
sf
drum
truck-mi
drum
ton
cf
hr
truck-mi
ton
ton
hr
ea
ea
ea
20
40
106,000
20
8
1,050
50
50
1,000
5
350
5
1
2,000
4
350
50
50
40
20
20
20
83.44
50.96
0.25
105.63
68.13
2.50
169.45
32.50
0.39
4.87
2.26
145.00
28.00
0.14
68.13
2.50
169.45
32.50
65.00
210.00
210.00
250.00
1,669
2,038
26,500
2,113
545
2,625
8,473
1,625
390
24
791
725
28
280
273
875
8,473
1,625
2,600
4,200
4,200
5,000
75,071 SUBTOTAL
Inflation adjustment (see Means 2014 Heavy Construction Cost Data) 1.337 100,370
Misc. costs as a percent of the inflation-adjusted subtotal:
Mob/demob
Engineering/permitting
DSHW oversight
Contingency
5 %
10 %
10 %
10 %
5,018
10,037
10,037
10,037
TOTAL ESTIMATED COST 135,499
EarthFax Engineering Group, LLC
Cost Estimate
Project: ATK - Promontory M-186 closure cost estimate
Project*: UC-1023-18
Estimator: RB White
Date: 16-Sep-14
Costs: Means 2005 Environmental Remediation Cost Data, adjusted for inflation, except as otherwise noted
Assume Level C PPE
Item No. Description Means No./Source Units Est. Quan. Unit Price Total Price
1
2
3
4
5
6
7
8
9
10
11
Site prep (CIH)
Site prep (technician)
Load drums
Haul drums to Clean Harbors
Landfill disposal
State disposal fee
Truck washout/decon
Steam clean floor
Rinsate sample collection
Sample analyses, metals
Sample analyses, explosives
33-22-0111 x2
33-22-0112x2
33-19-0103
33-19-0243
33-19-7214
Utah DEQ
33-19-0311
33-17-0812
Site crew
Chemtech-Ford
Chemtech-Ford
hr
hr
ea
truck-mi
drum
ton
ea
sf
hr
ea
ea
8
24
400
1,750
400
100
1
1,930
4
1
1
83.44
31.58
3.05
2.26
145.00
28.00
158.00
0.39
65.00
210.00
210.00
668
758
1,220
3,955
58,000
2,800
158
753
260
210
210
SUBTOTAL
Inflation adjustment (see Means 2014 Heavy Construction Cost Data) 1.337
68,991
92,241
Misc. costs as a percent of the inflation-adjusted subtotal:
Mob/demob
Engineering/permitting
DSHW oversight
Contingency 10
4,612
9,224
9,224
9,224
TOTAL ESTIMATED COST 124,526
EarthFax Engineering Group, LLC
Cost Estimate
Project: ATK - Promontory M-225 closure cost estimate
Project*: UC-1022-01
Estimator: RB White
Date: 16-Sep-14
Costs: Means 2005 Environmental Remediation Cost Data, adjusted for inflation, except as otherwise noted
Assume Level C PPE
Item No. Description Means No./Source Units Est. Quan. Unit Price Total Price
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
Site prep (CIH)
Site prep (technican)
Treat remaining waste
Excavate contaminated soil
Load soil and burned waste
Haul waste and soil to Clean Harbors
Landfill disposal, waste and soil
State disposal fee, waste and soil
Steam clean burn pans
Load rinsate
Haul rinsate to Clean Harbors
Landfill disposal, rinsate
State disposal fee, rinsate
Demolish pans
Load pan debris
Haul pan debris to Clean Harbors
Landfill disposal, pan debris
State disposal fee, pan debris
Sample collection
Sample analyses, metals
Sample analyses, explosives
Sample analyses, volatiles
33-22-0111 x2
33-22-0112x2
ATK
17-03-0231
17-03-0222
33-19-0221
33-19-7214
Utah DEQ
33-17-0812
33-19-0103
33-19-0243
33-19-7214
Utah DEQ
17-02-0105
17-03-0222
33-19-0221
33-19-7263
Utah DEQ
Site crew
Chemtech-Ford
Chemtech-Ford
Chemtech-Ford
hr
hr
Ib
hr
hr
truck-mi
ton
ton
sf
drum
truck-mi
drum
ton
cf
hr
truck-mi
ton
ton
hr
ea
ea
ea
8
20
55,000
12
4
350
25
25
400
3
350
3
1
800
4
350
20
20
20
5
5
5
83.44
50.96
0.25
105.63
68.13
2.50
169.45
32.50
0.39
4.87
2.26
145.00
28.00
0.14
68.13
2.50
169.45
32.50
65.00
210.00
210.00
250.00
668
1,019
13,750
1,268
273
875
4,236
813
156
15
791
435
28
112
273
875
3,389
650
1,300
1,050
1,050
1,250
SUBTOTAL
Inflation adjustment (see Means 2014 Heavy Construction Cost Data) 1.337
34,274
45,824
Misc. costs as a percent of the inflation-adjusted subtotal:
Mob/demob
Engineering/permitting
DSHW oversight
Contingency
5 %
10 %
10 %
10 %
2,291
4,582
4,582
4,582
TOTAL ESTIMATED COST 61,862
EarthFax Engineering Group, LLC
Cost Estimate
Project: ATK - Promontory M-603 closure cost estimate
Project*: UC-1023-18
Estimator: RB White
Date: 16-Sep-14
Costs: Means 2005 Environmental Remediation Cost Data, adjusted for inflation, except as otherwise noted
Assume Level C PPE
Item No. Description Means No./Source Units Est. Quan. Unit Price Total Price
1
2
3
4
5
6
9
10
11
12
13
14
15
16
17
18
Materials prep (CIH)
Materials prep (technician)
Load waste motor (crane)
Haul motor to burning ground
Off-load motor
Handling evaluation/planning
Motor handling
Disposal at burning ground
Sweep area
Steam clean floor
Load rinsate/sweepings
Load drums
Haul to Clean Harbors
State disposal fee
Sample collection
Sample analyses, metals/exp
33-22-0111 x2
33-22-0112x2
Crew SIWSM
Crew COET2
Crew SIWSM
Site personnel
Site personnel
ATK
33-22-0112x2
33-17-0812
33-19-0103
33-19-0103
33-19-0243
Utah DEQ
33-22-0112x2
Chemtech-Ford
hr
hr
hr
hr
hr
hr
hr
Ib
hr
sf
drum
ea
truck-mi
ton
hr
ea
8
12
8
12
8
40
20
120,000
8
1,830
4
4
350
1
4
2
83.44
31.58
393.57
93.31
393.57
65.00
65.00
0.25
31.58
0.39
4.87
3.05
2.26
28.00
31.58
210.00
668
379
3,149
1,120
3,149
2,600
1,300
30,000
253
714
19
12
791
28
126
420
SUBTOTAL
Inflation adjustment (see Means 2014 Heavy Construction Cost Data) 1.337
44,727
59,800
Misc. costs as a percent of the inflation-adjusted subtotal:
Mob/demob
Engineering/permitting
DSHW oversight
Contingency 10
2,990
5,980
5,980
5,980
TOTAL ESTIMATED COST 80,729
EarthFax Engineering Group, LLC
Cost Estimate
Project: ATK - Promontory M-705S closure cost estimate
Project*: UC-1023-18
Estimator: RB White
Date: 16-Sep-14
Costs: Means 2005 Environmental Remediation Cost Data, adjusted for inflation, except as otherwise noted
Assume Level C PPE
Item No. Description Means No./Source Units Est. Quan. Unit Price Total Price
1
2
3
4
5
6
7
8
9
10
11
Site prep (CIH)
Site prep (technician)
Load drums
Haul drums to Clean Harbors
Landfill disposal
State disposal fee
Truck washout/decon
Steam clean floor
Rinsate sample collection
Sample analyses, metals
Sample analyses, explosives
33-22-0111 x2
33-22-0112x2
33-19-0103
33-19-0243
33-19-7214
Utah DEQ
33-19-0311
33-17-0812
Site crew
Chemtech-Ford
Chemtech-Ford
hr
hr
ea
truck-mi
drum
ton
ea
sf
hr
ea
ea
4
8
32
350
32
8
1
1,850
4
1
1
83.44
31.58
3.05
2.26
145.00
28.00
158.00
0.39
65.00
210.00
210.00
334
253
98
791
4,640
224
158
722
260
210
210
SUBTOTAL
Inflation adjustment (see Means 2014 Heavy Construction Cost Data) 1.337
7,899
10,560
Misc. costs as a percent of the inflation-adjusted subtotal:
Mob/demob
Engineering/permitting
DSHW oversight
Contingency 10
528
1,056
1,056
1,056
TOTAL ESTIMATED COST 14,256
EarthFax Engineering Group, LLC
Cost Estimate
Project: ATK - Promontory S-633 closure cost estimate
Project*: UC-1023-18
Estimator: RB White
Date: 17-Sep-14
Costs: Means 2005 Environmental Remediation Cost Data, adjusted for inflation, except as otherwise noted
Assume Level C PPE
Item No. Description Means No./Source Units Est. Quan. Unit Price Total Price
1
2
3
4
5
6
7
Materials prep (CIH)
Materials prep (technician)
Disposal at burning ground
Sample collection
Sample analyses, metals
33-22-0111 x2
33-22-0112x2
ATK
Site crew
Chemtech-Ford
hr
hr
Ib
hr
ea
4
8
75,000
8
8
83.44
31.58
0.25
65.00
210.00
334
253
18,750
520
1,680
Sample analyses, explosives Chemtech-Ford ea 8 210.00 1,680
Sample analyses, volatiles Chemtech-Ford ea 8 210.00 1,680
SUBTOTAL
Inflation adjustment (see Means 2014 Heavy Construction Cost Data) 1.337
24,896
33,286
Misc. costs as a percent of the inflation-adjusted subtotal:
Mob/demob
Engineering/permitting
DSHW oversight
Contingency 10
1,664
3,329
3,329
3,329
TOTAL ESTIMATED COST 44,937
EarthFax Engineering Group, LLC
Cost Estimate
Project: ATK - Promontory T-29B closure cost estimate
Project*: UC-1023-18
Estimator: RB White
Date: 16-Sep-14
Costs: Means 2005 Environmental Remediation Cost Data, adjusted for inflation, except as otherwise noted
Assume Level C PPE
Item No. Description Means No./Source Units Est. Quan. Unit Price Total Price
1
2
3
4
5
6
7
8
9
10
11
12
13
Site prep (CIH)
Site prep (technician)
Extra drum for dilution
Transfer and dilute hydrazine
Load drums
Haul drums to Clean Harbors
Landfill disposal
State disposal fee
Truck washout/decon
Steam clean floor
Rinsate sample collection
Sample analyses, metals
Sample analyses, explosives
33-22-0111 x2
33-22-0112x2
33-19-0402
Site crew
33-19-0103
33-19-0243
33-19-7214
Utah DEQ
33-19-0311
33-17-0812
Site crew
Chemtech-Ford
Chemtech-Ford
hr
hr
ea
hr
ea
truck-mi
drum
ton
ea
sf
hr
ea
ea
4
8
1
4
2
350
2
1
1
200
4
1
1
83.44
31.58
80.00
65.00
3.05
2.26
145.00
28.00
158.00
0.39
65.00
210.00
210.00
334
253
80
260
6
791
290
28
158
78
260
210
210
SUBTOTAL
Inflation adjustment (see Means 2014 Heavy Construction Cost Data) 1.337
2,958
3,954
Misc. costs as a percent of the inflation-adjusted subtotal:
Mob/demob
Engineering/permitting
DSHW oversight
Contingency
198
395
395
395
TOTAL ESTIMATED COST 5,338