May 6, 2024
Mr. Mark Crim
Utah Department of Environmental Quality
Division of Environmental Response and Remediation
195 North 1950 West
Salt Lake City, Utah 84114-4840
SUBJECT: Proposed Work Plan and Price for Quarterly Groundwater Monitoring and Reporting
Palmer Tire
395 South 200 East
Roosevelt, Utah
Facility ID #9000371
UST Release Site MLS
Work Assignment MLS-22
UDEQ Technical Services Contract #216364
Dear Mr. Crim:
Please find attached a copy of the Proposed Work Plan and Price to conduct quarterly
groundwater monitoring and reporting at the above referenced site.
Our services consist of professional opinions and recommendations made in accordance with
generally accepted geotechnical and environmental engineering principles and practices. This
warranty is in lieu of all other warranties either expressed or implied.
Should you have any questions, please do not hesitate to call me at 801-971-1064.
Sincerely,
Atlas
Jim Coletta, P.G.
Branch Manager
Utah Certified UST Consultant
Palmer Tire MLS-22
Atlas
PROPOSED WORK PLAN
QUARTERLY GROUNDWATER MONITORING
AND REPORTING
PALMER TIRE
395 SOUTH 200 EAST
ROOSEVELT, UTAH
FACILITY ID #9000371
UST RELEASE SITE MLS
WORK ASSIGNMENT MLS-22
UDEQ TECHNICAL SERVICES CONTRACT #216364
May 6, 2024
Prepared for:
Mr. Mark Crim
State of Utah
Department of Environmental Quality
Division of Environmental Response and Remediation
195 North 1950 West
Salt Lake City, Utah 84114
Prepared by:
Atlas
358 South 700 East, B518
Salt Lake City, Utah 84102
Palmer Tire MLS-22
Atlas
TABLE OF CONTENTS
Letter of Transmittal
Title Page
Table of Contents
1. INTRODUCTION ................................................................................................................................... 1
2. SCOPE OF SERVICES ........................................................................................................................ 1
2.1 Task 1 – June 2024 Groundwater Monitoring and Reporting .................................................... 1
2.2 Task 2 – September 2024 Groundwater Monitoring and Reporting ......................................... 2
2.3 Task 3 – December 2024 Groundwater Monitoring and Reporting ........................................... 2
2.4 Task 4 – March 2025 Groundwater Monitoring and Reporting ................................................. 2
2.5 Task 5 – June 2025 Groundwater Monitoring and Reporting .................................................... 2
2.6 Task 6 – September 2025 Groundwater Monitoring and Reporting ......................................... 2
3. DELIVERABLES .................................................................................................................................. 3
4. PROPOSED PROJECT SCHEDULE ................................................................................................... 3
5. PERSONNEL ........................................................................................................................................ 3
6. SUBCONTRACTORS ........................................................................................................................... 3
7. EXCEPTIONS, ANTICIPATED PROBLEMS, OR SPECIAL REQUIREMENTS ................................. 3
8. CONFLICT OF INTEREST ................................................................................................................... 3
9. COST ESTIMATE ................................................................................................................................. 4
Figure 1 – Site Map
Table 1 - Proposed Project Schedule
Table 2 - Cost Estimate
Appendix A – Contract Required Paperwork and Bid Documentation
Palmer Tire MLS-22
Atlas
1
PROPOSED WORK PLAN
QUARTERLY GROUNDWATER MONITORING
AND REPORTING
PALMER TIRE
395 SOUTH 200 EAST
ROOSEVELT, UTAH
FACILITY ID #9000371
UST RELEASE SITE MLS
WORK ASSIGNMENT MLS-22
UDEQ TECHNICAL SERVICES CONTRACT #216364
1. INTRODUCTION
Under Work Assignments MLS-22, the Utah Department of Environmental Quality, Division of Environmental Response and Remediation (UDEQ) requested Atlas Technical Consultants (Atlas) prepare a Work Plan and price to conduct quarterly groundwater monitoring and reporting for a one year period at the above referenced site. A site map showing well locations is presented as Figure 1. This following proposed Work Plan presents a brief description of the tasks to be performed including a schedule (Table 1) for completing the activities described herein and a detailed cost breakdown (Table 2).
2. SCOPE OF SERVICES
The objective of this proposed Work Plan is to conduct four quarterly rounds of groundwater sampling and to prepare summary reports for each groundwater sampling event. Each task is described in greater detail in the following sections. Utah Certified Soil and Groundwater Samplers would perform the groundwater sampling activities described below under the direction of a Utah Certified UST Consultant.
2.1 Task 1 – June 2024 Groundwater Monitoring and Reporting
The procedures described in the following paragraphs would be used to sample monitoring wells MW -11, MW -14, MW -15, MW -17, MW -18, MW -19, MW -21, and MW -22. In addition, free product and groundwater elevation data will be collected from MW -10. Initially, the groundwater depth and free product thickness (if present) would be measured at each well location. These measurements would be taken with a down-hole water level/free product interface probe. The water level/free product probe would be decontaminated between each well with an Alconox detergent wash and tap water rinse. The wells to be sampled would then be developed/purged of a minimum of three well casing volumes or until dry using new disposable bailers. The water interface probe would be decontaminated between each well using an Alconox detergent wash and tap water rinse. If free product is measured in a well, that well would not be sampled. The purge and decontamination water would be poured on the asphalt surface and allowed to evaporate.
The groundwater sampling event would include the wells listed above. A field blank and trip blank would also be submitted for quality assurance purposes. The wells that do not contain free product would be analyzed for MBTEXN and TPH-GRO sing USEPA Method 8260; and for TPH-DRO using USEPA Method 8015.
A groundwater monitoring report would be prepared under Task 1. The report will include:
• Data tables for historic and newly obtained analytic data;
• Measurements for depth to water and free product;
Palmer Tire MLS-22
Atlas
2
• A site location map showing the monitoring wells
• A groundwater gradient map;
• Iso-concentration contours maps for dissolved phase benzene, TPH-GRO, and TPH-
DRO;
• QA/QC for sample collection;
• Actual laboratory reports and chain of custody forms; and
• Field observations including standard operating procedures for well purging and
sampling.
One copy of the report will be provided to the UDEQ.
2.2 Task 2 – September 2024 Groundwater Monitoring and Reporting
A groundwater sampling event would be conducted in September 2024 and would follow the
sample protocols and included the sample locations as described in Section 2.1 above with the
exception of the collection of the free product samples. Upon completion of the sampling event
a Groundwater Monitoring Report would be prepared and will include the components listed
above under Section 2.1.
2.3 Task 3 – December 2024 Groundwater Monitoring and Reporting
A groundwater sampling event would be conducted in December 2024 and would follow the
sample protocols and included the sample locations as described in Section 2.1 above with the
exception of the collection of the free product samples. Upon completion of the sampling event
a Groundwater Monitoring Report would be prepared and will include the components listed
above under Section 2.1.
2.4 Task 4 – March 2025 Groundwater Monitoring and Reporting
A groundwater sampling event would be conducted in March 2025 and would follow the sample
protocols and included the sample locations as described in Section 2.1 above with the
exception of the collection of the free product samples. Upon completion of the sampling event
a Groundwater Monitoring Report would be prepared and will include the components listed
above under Section 2.1.
2.5 Task 5 – June 2025 Groundwater Monitoring and Reporting
A groundwater sampling event would be conducted in June 2025 and would follow the sample
protocols and included the sample locations as described in Section 2.1 above with the
exception of the collection of the free product samples. Upon completion of the sampling event
a Groundwater Monitoring Report would be prepared and will include the components listed
above under Section 2.1.
2.6 Task 6 – September 2025 Groundwater Monitoring and Reporting
A groundwater sampling event would be conducted in September 2025 and would follow the
sample protocols and included the sample locations as described in Section 2.1 above with the
exception of the collection of the free product samples. Upon completion of the sampling event
a Groundwater Monitoring Report would be prepared and will include the components listed
above under Section 2.1.
Palmer Tire MLS-22
Atlas
3
3. DELIVERABLES
The anticipated deliverables for the work identified in this proposed Work Plan include the
following:
• June, September, and December, 2024; and March, June, and September 2025
Groundwater Monitoring Reports;
• Contract required forms.
4. PROPOSED PROJECT SCHEDULE
The proposed schedule for the activities described herein is presented in Table 1.
5. PERSONNEL
The key personnel for the proposed activities are as follows:
• Atlas Senior Project Manager: Jim Coletta (P101)
• Atlas Professional Geologist: Jim Coletta (P102)
• Atlas Project Manager: Jim Coletta (P103)
• Atlas Senior Technician: Olaf Questereit (P105)
6. SUBCONTRACTORS
The following subcontractors would be used in the performance of the above scope of work:
• PACE Laboratory - would provide state certified laboratory services.
Based on information provided by each selected subcontractor, the following contract
requirements have been met:
• The selected subcontractor is not currently debarred pursuant to Utah Code Section 63-56-
48 or EPA’s most recent “Master List of Debarred or Suspended Facilities”;
• The selected subcontractor has no apparent conflict of interest; and
• The selected subcontractor is not a minority or women owned business enterprises.
7. EXCEPTIONS, ANTICIPATED PROBLEMS, OR SPECIAL REQUIREMENTS
At this time, no exceptions or special requirements to the proposed Work Plan are anticipated
with the exception of the grant of access agreement. In the event exceptions or special
conditions arise, Atlas would amend this proposed Work Plan or submit a new Work Plan for
UDEQ approval before initiating any work outside the scope of services described herein.
8. CONFLICT OF INTEREST
Based on Atlas’s present knowledge of the site location and conditions, no personal or
corporate conflict of interest has been identified for the performance of the scope of services
described in this proposed Work Plan. Atlas would contact UDEQ immediately if a potential
conflict of interest is identified during the performance of this proposed Work Plan.
Palmer Tire MLS-22
Atlas
4
9. COST ESTIMATE
The estimated cost for implementation of this proposed Work Plan is presented in Table 2. The
estimated budget would require adjustment if the scope of services identified herein is modified
or any assumptions are incorrect. Exhibit 3 from the UDEQ Technical Services contract is
presented in Appendix A.
20
0
E
A
S
T
MOVIE
GALLERY
(LCL OIL)
PALMER
TIRE
ELECTRICAL
SEEP
RESIDENTIAL
RESIDENTIAL
RESIDENTIAL
DISPENSOR
ISLANDS
ELECTRICAL LINE
SEEP AREA
FENCE
G
G
G
G
G
G
G
G
G
G
G
G G NATURAL GAS
ST
E
E
P
S
L
O
P
E
STEEP
SLOPE
TP
TP TELEPHONE POLE
W
W
W
W
W
W
W
S
WATER LINE (Approximate Depth = 5')
SEWER LINE (Approximate Depth = 8')
US
H
W
Y
4
0
INSTALLED JANUARY 2008
MONITORING WELL LOCATION
INSTALLED OCTOBER 2008
IRRIGATION WATER LINE
271EM00757PROJECT NUMBER:DATE:10-26-21
1
FIGURE
DRAWN BY:JCAPPROVED BY:BIX
W
W
W
W
W
W
W
W
W
S
S
W
W
W W
WESTERN
PETROLEUM
W
W
W
W
W
W
W
W
W
W
S
S
S
S
S
S
MONITORING WELL LOCATION (02-14)
W
W
W
W
W
W
G G G
G
G
G
G
G
G
NEW MONITORING WELL LOCATION (05-17)
W
W
W
W
W
W
ABANDONED OR DESTROYED WELL
358 South 700 East, B518
Salt Lake City, Utah 84102
801-935-4917
Palmer Tire MLS-22
Atlas
TABLE 1 PROPOSED PROJECT SCHEDULE
TASK
MONTH
June
2024
July
2024
Sept.
2024
Oct.
2024
Dec.
2024
Jan.
2025
March
2025
April
2025
June
2025
July
2025
Sept.
2025
Oct.
2025
Task 1 – June 2024
Groundwater Monitoring
and Reporting (July 2024)
X
X
Task 2 – Sept. 2024
Groundwater Monitoring
and Reporting (Oct. 2024)
X
X
Task 3 – Dec. 2024
Groundwater Monitoring
and Reporting (Jan.
2024)
X
X
Task 4 – March 2025
Groundwater Monitoring
and Reporting (April
2025)
X
X
Task 5 – June 2025
Groundwater Monitoring
and Reporting (July 2025)
X
X
Task 6 – Sept. 2025
Groundwater Monitoring
and Reporting (Oct. 2025)
X
X
Work Assignment MLS-22 1 of 6
Task 1 - Groundwater Monitoring - June 2024 (Sample MW-11, 14 , 15, 17, 18, 19, 21, and 22 - Free Product and WT Ele.)
Labor
Category Staff Quantity Hourly Rate Subtotal Subtotal Totals
P101 Senior Project Manager - Setup new project and project
coordination
3 152.00$ 456.00$ 456.00$
P103 Project Manager - Coordinate with laboratory and
coordination of sampling effort, and preparation of
payment request
4 118.00$ 472.00$ 472.00$
P105 Senior Technician - Preparation and coordination 1.5 90.00$ 135.00$ 135.00$
P105 Senior Technician - Travel (round trip)5 90.00$ 450.00$ 450.00$
P105 Senior Technician - Collect groundwater elevation
(includes MW-10) and free product data, and sample wells
9.5 90.00$ 855.00$ 855.00$
P108 Administrative Assistant - Amendment processing 1 62.00$ 62.00$ 62.00$
Labor Subtotal 2,430.00$ #REF!
Direct Costs
Equipment/Materials/Supplies
Water Level/Free Product Interface Probe 2 55.00$ 110.00$ 110.00$
Sampling Supplies 2 25.00$ 50.00$ 50.00$
Traffic Safety Equipment 2 15.00$ 30.00$ 30.00$
Submersible Pump 0 30.00$ -$ -$
Flexible Tubing 0 0.50$ -$ -$
Free Product Absorbent Sock (MW-17 & MW-18)0 15.00$ -$ -$
Disposable Bailers 8 9.00$ 72.00$ 72.00$
Outside Services
10 94.00$ 940.00$ 940.00$
0 50.00$ -$ -$
Per Diem
Mileage 310 0.655$ 203.05$ 203.05$
Lodging 1 120.00$ 120.00$ 120.00$
Meals 2 40.00$ 80.00$ 80.00$
Direct Costs Subtotal 1,605.05$
Groundwater Monitoring Report
Labor
Category Staff Quantity Hourly Rate Subtotal Subtotal Totals
P101 Senior Project Manager - Coordination, review, invoicing 2 152.00$ 304.00$ 304.00$
P102 Professional Geologist - Preparation of the groundwater
gradient map and three isoconcentration maps
8 147.00$ 1,176.00$ 1,176.00$
P103 Project Manager - Report review and preparation, and
payment request submittal
3 118.00$ 354.00$ 354.00$
P105 Senior Technician - Data entry and report preparation 11 90.00$ 990.00$ 990.00$
P107 Drafter - Prepare gradient map and three isoconcentration
maps 8 85.00$ 680.00$ 680.00$
P108 Administrative Assistant - Clerical and invoicing 2 62.00$ 124.00$ 124.00$
Labor Subtotal 3,628.00$ #REF!
Task 1 Total:7,663.05$
Laboratory - MBTEXN/TPH-GRO & DRO, Field Blank and Trip Blank -
includes 10% markup
Disposal of Absorbent Socks
TABLE 2
Palmer Tire
395 South 200 East
Roosevelt, Utah
Quarterly Groundwater Sampling
Work Assignment MLS-22
Work Assignment MLS-22 2 of 6
TABLE 2
Palmer Tire
395 South 200 East
Roosevelt, Utah
Quarterly Groundwater Sampling
Work Assignment MLS-22
Task 2 - Groundwater Monitoring - September 2024 (Sample MW-11, 14 , 15, 17, 18, 19, 21, and 22 - Free Product and WT Ele.)
Labor
Category Staff Quantity Hourly Rate Subtotal Subtotal Totals
P101 Senior Project Manager - Project coordination 2 152.00$ 304.00$ 304.00$
P103 Project Manager - Coordinate with laboratory and
coordination of sampling effort, and preparation of
payment request
4 118.00$ 472.00$ 472.00$
P105 Senior Technician - Preparation and coordination 1.5 90.00$ 135.00$ 135.00$
P105 Senior Technician - Travel (round trip)5 90.00$ 450.00$ 450.00$
P105 Senior Technician - Collect groundwater elevation
(includes MW-10) and free product data, and sample wells
9.5 90.00$ 855.00$ 855.00$
P108 Administrative Assistant - Amendment processing 1 62.00$ 62.00$ 62.00$
Labor Subtotal 2,278.00$ #REF!
Direct Costs
Equipment/Materials/Supplies
Water Level/Free Product Interface Probe 2 55.00$ 110.00$ 110.00$
Sampling Supplies 2 25.00$ 50.00$ 50.00$
Traffic Safety Equipment 2 15.00$ 30.00$ 30.00$
Submersible Pump 0 30.00$ -$ -$
Flexible Tubing 0 0.50$ -$ -$
Free Product Absorbent Sock (MW-17 & MW-18)0 15.00$ -$ -$
Disposable Bailers 8 9.00$ 72.00$ 72.00$
Outside Services
10 94.00$ 940.00$ 940.00$
0 50.00$ -$ -$
Per Diem
Mileage 310 0.655$ 203.05$ 203.05$
Lodging 1 120.00$ 120.00$ 120.00$
Meals 2 40.00$ 80.00$ 80.00$
Direct Costs Subtotal 1,605.05$
Groundwater Monitoring Report
Labor
Category Staff Quantity Hourly Rate Subtotal Subtotal Totals
P101 Senior Project Manager - Coordination, review, invoicing 2 152.00$ 304.00$ 304.00$
P102 Professional Geologist - Preparation of the groundwater
gradient map and three isoconcentration maps
8 147.00$ 1,176.00$ 1,176.00$
P103 Project Manager - Report review and preparation, and
payment request submittal
3 118.00$ 354.00$ 354.00$
P105 Senior Technician - Data entry and report preparation 11 90.00$ 990.00$ 990.00$
P107 Drafter - Prepare gradient map and three isoconcentration
maps 8 85.00$ 680.00$ 680.00$
P108 Administrative Assistant - Clerical and invoicing 2 62.00$ 124.00$ 124.00$
Labor Subtotal 3,628.00$ #REF!
Task 2 Total:7,511.05$
Laboratory - MBTEXN/TPH-GRO & DRO, Field Blank and Trip Blank -
includes 10% markup
Disposal of Absorbent Socks
Work Assignment MLS-22 3 of 6
TABLE 2
Palmer Tire
395 South 200 East
Roosevelt, Utah
Quarterly Groundwater Sampling
Work Assignment MLS-22
Task 3 - Groundwater Monitoring - December 2024 (Sample MW-11, 14 , 15, 17, 18, 19, 21, and 22 - Free Product and WT Ele.)
Labor
Category Staff Quantity Hourly Rate Subtotal Subtotal Totals
P101 Senior Project Manager - Project coordination 2 152.00$ 304.00$ 304.00$
P103 Project Manager - Coordinate with laboratory and
coordination of sampling effort, and preparation of
payment request
4 118.00$ 472.00$ 472.00$
P105 Senior Technician - Preparation and coordination 1.5 90.00$ 135.00$ 135.00$
P105 Senior Technician - Travel (round trip)5 90.00$ 450.00$ 450.00$
P105 Senior Technician - Collect groundwater elevation
(includes MW-10) and free product data, and sample wells
9.5 90.00$ 855.00$ 855.00$
P108 Administrative Assistant - Amendment processing 1 62.00$ 62.00$ 62.00$
Labor Subtotal 2,278.00$ #REF!
Direct Costs
Equipment/Materials/Supplies
Water Level/Free Product Interface Probe 2 55.00$ 110.00$ 110.00$
Sampling Supplies 2 25.00$ 50.00$ 50.00$
Traffic Safety Equipment 2 15.00$ 30.00$ 30.00$
Submersible Pump 0 30.00$ -$ -$
Flexible Tubing 0 0.50$ -$ -$
Free Product Absorbent Sock (MW-17 & MW-18)0 15.00$ -$ -$
Disposable Bailers 8 9.00$ 72.00$ 72.00$
Outside Services
10 94.00$ 940.00$ 940.00$
0 50.00$ -$ -$
Per Diem
Mileage 310 0.655$ 203.05$ 203.05$
Lodging 1 120.00$ 120.00$ 120.00$
Meals 2 40.00$ 80.00$ 80.00$
Direct Costs Subtotal 1,605.05$
Groundwater Monitoring Report
Labor
Category Staff Quantity Hourly Rate Subtotal Subtotal Totals
P101 Senior Project Manager - Coordination, review, invoicing 2 152.00$ 304.00$ 304.00$
P102 Professional Geologist - Preparation of the groundwater
gradient map and three isoconcentration maps
8 147.00$ 1,176.00$ 1,176.00$
P103 Project Manager - Report review and preparation, and
payment request submittal
3 118.00$ 354.00$ 354.00$
P105 Senior Technician - Data entry and report preparation 11 90.00$ 990.00$ 990.00$
P107 Drafter - Prepare gradient map and three isoconcentration
maps 8 85.00$ 680.00$ 680.00$
P108 Administrative Assistant - Clerical and invoicing 2 62.00$ 124.00$ 124.00$
Labor Subtotal 3,628.00$ #REF!
Task 3 Total:7,511.05$
Laboratory - MBTEXN/TPH-GRO & DRO, Field Blank and Trip Blank -
includes 10% markup
Disposal of Absorbent Socks
Work Assignment MLS-22 4 of 6
TABLE 2
Palmer Tire
395 South 200 East
Roosevelt, Utah
Quarterly Groundwater Sampling
Work Assignment MLS-22
Task 4 - Groundwater Monitoring - March 2025 (Sample MW-11, 14 , 15, 17, 18, 19, 21, and 22 - Free Product and WT Ele.)
Labor
Category Staff Quantity Hourly Rate Subtotal Subtotal Totals
P101 Senior Project Manager - Project coordination 2 152.00$ 304.00$ 304.00$
P103 Project Manager - Coordinate with laboratory and
coordination of sampling effort, and preparation of
payment request
4 118.00$ 472.00$ 472.00$
P105 Senior Technician - Preparation and coordination 1.5 90.00$ 135.00$ 135.00$
P105 Senior Technician - Travel (round trip)5 90.00$ 450.00$ 450.00$
P105 Senior Technician - Collect groundwater elevation
(includes MW-10) and free product data, and sample wells
9.5 90.00$ 855.00$ 855.00$
P108 Administrative Assistant - Amendment processing 1 62.00$ 62.00$ 62.00$
Labor Subtotal 2,278.00$ #REF!
Direct Costs
Equipment/Materials/Supplies
Water Level/Free Product Interface Probe 2 55.00$ 110.00$ 110.00$
Sampling Supplies 2 25.00$ 50.00$ 50.00$
Traffic Safety Equipment 2 15.00$ 30.00$ 30.00$
Submersible Pump 0 30.00$ -$ -$
Flexible Tubing 0 0.50$ -$ -$
Free Product Absorbent Sock (MW-17 & MW-18)0 15.00$ -$ -$
Disposable Bailers 8 9.00$ 72.00$ 72.00$
Outside Services
10 94.00$ 940.00$ 940.00$
0 50.00$ -$ -$
Per Diem
Mileage 310 0.655$ 203.05$ 203.05$
Lodging 1 120.00$ 120.00$ 120.00$
Meals 2 40.00$ 80.00$ 80.00$
Direct Costs Subtotal 1,605.05$
Groundwater Monitoring Report
Labor
Category Staff Quantity Hourly Rate Subtotal Subtotal Totals
P101 Senior Project Manager - Coordination, review, invoicing 2 152.00$ 304.00$ 304.00$
P102 Professional Geologist - Preparation of the groundwater
gradient map and three isoconcentration maps
8 147.00$ 1,176.00$ 1,176.00$
P103 Project Manager - Report review and preparation of the
groundwater gradient and isoconcentration maps
3 118.00$ 354.00$ 354.00$
P105 Senior Technician - Data entry and report preparation 11 90.00$ 990.00$ 990.00$
P107 Drafter - Prepare gradient map and three isoconcentration
maps 8 85.00$ 680.00$ 680.00$
P108 Administrative Assistant - Clerical and invoicing 2 62.00$ 124.00$ 124.00$
Labor Subtotal 3,628.00$ #REF!
Task 4 Total:7,511.05$
Disposal of Absorbent Socks
Laboratory - MBTEXN/TPH-GRO & DRO, Field Blank and Trip Blank -
includes 10% markup
Work Assignment MLS-22 5 of 6
TABLE 2
Palmer Tire
395 South 200 East
Roosevelt, Utah
Quarterly Groundwater Sampling
Work Assignment MLS-22
Task 5 - Groundwater Monitoring - June 2025 (Sample MW-11, 14 , 15, 17, 18, 19, 21, and 22 - Free Product and WT Ele.)
Labor
Category Staff Quantity Hourly Rate Subtotal Subtotal Totals
P101 Senior Project Manager - Project coordination 2 152.00$ 304.00$ 304.00$
P103 Project Manager - Coordinate with laboratory and
coordination of sampling effort, and preparation of
payment request
4 118.00$ 472.00$ 472.00$
P105 Senior Technician - Preparation and coordination 1.5 90.00$ 135.00$ 135.00$
P105 Senior Technician - Travel (round trip)5 90.00$ 450.00$ 450.00$
P105 Senior Technician - Collect groundwater elevation
(includes MW-10) and free product data, and sample wells
9.5 90.00$ 855.00$ 855.00$
P108 Administrative Assistant - Amendment processing 1 62.00$ 62.00$ 62.00$
Labor Subtotal 2,278.00$ #REF!
Direct Costs
Equipment/Materials/Supplies
Water Level/Free Product Interface Probe 2 55.00$ 110.00$ 110.00$
Sampling Supplies 2 25.00$ 50.00$ 50.00$
Traffic Safety Equipment 2 15.00$ 30.00$ 30.00$
Submersible Pump 0 30.00$ -$ -$
Flexible Tubing 0 0.50$ -$ -$
Free Product Absorbent Sock (MW-17 & MW-18)0 15.00$ -$ -$
Disposable Bailers 8 9.00$ 72.00$ 72.00$
Outside Services
10 94.00$ 940.00$ 940.00$
0 50.00$ -$ -$
Per Diem
Mileage 310 0.655$ 203.05$ 203.05$
Lodging 1 120.00$ 120.00$ 120.00$
Meals 2 40.00$ 80.00$ 80.00$
Direct Costs Subtotal 1,605.05$
Groundwater Monitoring Report
Labor
Category Staff Quantity Hourly Rate Subtotal Subtotal Totals
P101 Senior Project Manager - Coordination, review, invoicing 2 152.00$ 304.00$ 304.00$
P102 Professional Geologist - Preparation of the groundwater
gradient map and three isoconcentration maps
8 147.00$ 1,176.00$ 1,176.00$
P103 Project Manager - Report review and preparation of the
groundwater gradient and isoconcentration maps
3 118.00$ 354.00$ 354.00$
P105 Senior Technician - Data entry and report preparation 11 90.00$ 990.00$ 990.00$
P107 Drafter - Prepare gradient map and three isoconcentration
maps 8 85.00$ 680.00$ 680.00$
P108 Administrative Assistant - Clerical and invoicing 2 62.00$ 124.00$ 124.00$
Labor Subtotal 3,628.00$ #REF!
Task 5 Total:7,511.05$
Laboratory - MBTEXN/TPH-GRO & DRO, Field Blank and Trip Blank -
includes 10% markup
Disposal of Absorbent Socks
Work Assignment MLS-22 6 of 6
TABLE 2
Palmer Tire
395 South 200 East
Roosevelt, Utah
Quarterly Groundwater Sampling
Work Assignment MLS-22
Task 6 - Groundwater Monitoring - September 2025 (Sample MW-11, 14 , 15, 17, 18, 19, 21, and 22 - Free Product and WT Ele.)
Labor
Category Staff Quantity Hourly Rate Subtotal Subtotal Totals
P101 Senior Project Manager - Project coordination 2 152.00$ 304.00$ 304.00$
P103 Project Manager - Coordinate with laboratory and
coordination of sampling effort, and preparation of
payment request
4 118.00$ 472.00$ 472.00$
P105 Senior Technician - Preparation and coordination 1.5 90.00$ 135.00$ 135.00$
P105 Senior Technician - Travel (round trip)5 90.00$ 450.00$ 450.00$
P105 Senior Technician - Collect groundwater elevation
(includes MW-10) and free product data, and sample wells
9.5 90.00$ 855.00$ 855.00$
P108 Administrative Assistant - Amendment processing 1 62.00$ 62.00$ 62.00$
Labor Subtotal 2,278.00$ #REF!
Direct Costs
Equipment/Materials/Supplies
Water Level/Free Product Interface Probe 2 55.00$ 110.00$ 110.00$
Sampling Supplies 2 25.00$ 50.00$ 50.00$
Traffic Safety Equipment 2 15.00$ 30.00$ 30.00$
Submersible Pump 0 30.00$ -$ -$
Flexible Tubing 0 0.50$ -$ -$
Free Product Absorbent Sock (MW-17 & MW-18)0 15.00$ -$ -$
Disposable Bailers 8 9.00$ 72.00$ 72.00$
Outside Services
10 94.00$ 940.00$ 940.00$
0 50.00$ -$ -$
Per Diem
Mileage 310 0.655$ 203.05$ 203.05$
Lodging 1 120.00$ 120.00$ 120.00$
Meals 2 40.00$ 80.00$ 80.00$
Direct Costs Subtotal 1,605.05$
Groundwater Monitoring Report
Labor
Category Staff Quantity Hourly Rate Subtotal Subtotal Totals
P101 Senior Project Manager - Coordination, review, invoicing 2 152.00$ 304.00$ 304.00$
P102 Professional Geologist - Preparation of the groundwater
gradient map and three isoconcentration maps
8 147.00$ 1,176.00$ 1,176.00$
P103 Project Manager - Report review and preparation of the
groundwater gradient and isoconcentration maps
3 118.00$ 354.00$ 354.00$
P105 Senior Technician - Data entry and report preparation 11 90.00$ 990.00$ 990.00$
P107 Drafter - Prepare gradient map and three isoconcentration
maps 8 85.00$ 680.00$ 680.00$
P108 Administrative Assistant - Clerical and invoicing 2 62.00$ 124.00$ 124.00$
Labor Subtotal 3,628.00$ #REF!
Task 6 Total:7,511.05$
45,218.30$ PROJECT TOTAL:
Laboratory - MBTEXN/TPH-GRO & DRO, Field Blank and Trip Blank -
includes 10% markup
Disposal of Absorbent Socks
APPENDIX A
CONTRACT REQUIRED PAPER
EXHIBIT “3”
DELIVERABLE AND PAYMENT SCHEDULE
Date May 6, 2024
Work Assignment No. MLS-22
Deliverable/Task
Number Description Due Date Price
Task 1
June 2024 Groundwater
Monitoring and Reporting
Sampling – June 31, 2024
Reporting – July 31, 2024
$7,663.05
Task 2
September 2024
Groundwater Monitoring and
Reporting
Sampling – September 30, 2024
Reporting – October 31, 2024
$7,511.05
Task 3
December 2024 Groundwater
Monitoring and Reporting
Sampling – December 31, 2024
Reporting – January 30, 2025
$7,511.05
Task 4
March 2025 Groundwater
Monitoring and Reporting
Sampling – March 31, 2025
Reporting – April 30, 2025
$7,511.05
Task 5
June 2025 Groundwater
Monitoring and Reporting
Sampling – June 31, 2025
Reporting – July 31, 2025
$7,511.05
Task 6
September 2025
Groundwater Monitoring and
Reporting
Sampling – September 30, 2025
Reporting – October 31, 2025
$7,511.05
Work Assignment Total $45,218.30