HomeMy WebLinkAboutDAQ-2024-008008MarchL5,2024
Electronic Submittal
Mr, Bryce Bird, Director
Utah Department of Env. Quality
Utah Division of AirQuality
Attn.: NSR Section
195 North 1950 West,4th Floor
salt Lake city, uT 84116
Re: Kinder Morgan Altamont LLC
Farm Compressor Station, Approval Order DAqE-AN16ql1fi)03-21
Construction Status
Sincerely,ee>
Erin Dunman
Environmental Engineer
RLWEWED
rnidars: @ o^,,, 3f tI lz,{
Compliance St^t * We-irx&
ril,# lboo (
Dear Mr. Bird,
As required by Condition 1.8 in Approval Order DAQE-AN15OO10O03-21, Kinder Morgan Altamont LLC
(Kinder Morgan) is submitting this correspondence to provide a status of construction of Farm
Compressor Station. As of the date of this letter, six of the eight reciprocating engines (C-L, C-2, C-3, C-4,
C-5, and C-6) have been installed and begun operation. All of these emission units were authorized in
the referenced Approval Order, which was issued on September 23,2021. Previous correspondence was
provided informing the Utah Division of Air Quality (UDAQ of the equipment start dates following
installation.
lf you have any questions about this submittal, please contact me at (303) 914-7605 or by email at
Erin_Dunman@ kindermorgan.com.