May 7, 2024
Atlas Technical Consultants, LLC
358 South 700 East, B518
Salt Lake City, Utah 84104
ERRL-0188-24
Re: Work Assignment HLR-12-ATC: Preparation of a Work Plan and Price for Securing
Access and Conducting One Groundwater Monitoring Event with Reporting
Big O Tire, located at 208 South Main Street, Richfield, Utah
Facility Identification No. 2000326, Release Site HLR
Dear Mr. Coletta:
The Division of Environmental Response and Remediation (DERR) requests that Atlas
complete the enclosed Work Assignment Number HLR-12-ATC, under Contract #216364. The
Work Assignment is to submit a work plan and price for ensuring access and to conduct one
groundwater monitoring event at the above-referenced site.
Enclosed is the original Work Assignment with tasks to be completed. Please sign and return
electronically to the DERR.
If you have any questions, please contact Eileen Brennan, the DERR project manager, at
(801) 536-4100.
Sincerely,
Morgan P. Atkinson, UST Branch Manager
Division of Environmental Response and Remediation
MPAIEB/rr
cc: Thomas Kingston, Division of Environmental Response and Remediation
195 North 1950 West• Salt Lake City, UT
Mailing Address : P.O . Box 144840 • Salt Lake City, UT 84114-4840
Telephone (801) 536-4100 • Fax (801) 359-8853 • T.D.D . (801) 536-4284
www.deq.utah.gov
Printed on I 00% recycled paper
WORK ASSIGNMENT HLR-12-ATC
Contract#: 216364
Work Assignment: Preparation of a Work Plan and Price for Securing Access and
Conducting One Groundwater Monitoring Event with Reporting
Big O Tire, located at 208 South Main Street, Richfield, Utah
Facility Identification No. 2000326, Release Site HLR
The Consultant, Atlas, is requested to complete the following Work Assignment.
I. WORK OBJECTIVE:
The work objective is to submit a work plan price to secure a new Grant of Access, if needed,
and to conduct one round of groundwater monitoring and sampling of the release wells, with
a report to follow. The work plan price should provide an estimate of costs for the
implementation of the work plan, itemized per task. Each stage of the work plan should be
identified as a specific task or sub-task. Work performed under each task or subtask shall
not commence without prior approval from the DERR.
II. TASKS:
The DERR has identified the following tasks to be included in the work plan and price:
1. Secure permission to access the site wells. If necessary, have a DERR Grant of
Access signed & submitted to DERR for the project file.
2. Conduct one round of monitoring and sampling of all available monitoring wells.
This task includes documenting depth to water, thickness of any free product, and
other observations, and collecting samples for MBTEXN, GRO, and DRO by the
appropriate analytical methods. The groundwater sample with the highest
concentrations should be fractionated.
3. Submit a draft groundwater monitoring report with updated historical groundwater
data tables, appropriate maps and laboratory reports within 30 days of sampling.
Cost: $650.00.
III. PRICE AND PAYMENT SCHEDULE:
A. The expense to the DERR for completing this Work Assignment shall not exceed
$650.00, including administrative costs, contract management, project management,
and other associated costs.
B. Payment requests shall be submitted when tasks are completed, as outlined in the
Deliverable and Payment Schedule.
IV. SCHEDULE FOR COMPLETION OF WORK AND REPORTING REQUIREMENTS
A. The DERR has set a deadline of May 30, 2024, for Atlas to submit a draft work plan
and price for the determined work.
B. After the DERR has reviewed and commented on the draft work plan and price, Atlas
will be required to provide a final work plan and price within four ( 4) days of receipt
of any DERR comments.
Approved by:
DERR Project Manager: s:A ~ Date: 05/07/2024
DERR Contract Officer: 1~rw1~ Date: 05/07/2024
LUST Section Manager: ~~~ Date: 05/07/2024
'7{1.Me.1[ Cotettg,_ 05/08/2024 Consultant: James Coletta (May 8, 202416:58 MDT) Date:
DELIVERABLE AND PAYMENT SCHEDULE
Work Assignment: HLR-12-ATC
Deliverable/ Description Due Date Price
Task No.
Work Plan and Price for Securing Access
II and Conducting One Groundwater May 30, 2024 $650.00
Monitoring Event with Reporting
Work Assignment Total: $650.00