HomeMy WebLinkAboutDDW-2024-008354Mr. Wright:
The Red Canyon Village Water Well and Storage Project is substantially complete. To the best of my
knowledge, all conditions of Plan Approval have been accomplished.
The project included upgrading an existing well and installing a 2,500 gallon water tank.
The water has been tested according to ANSI/AWWA C651-14 AWWA Standard for Disinfecting Water
Mains. Bacteriological sample tests were taken from the well and cafe. The cafe is immediately
downstream from the tank. Results (negative coliform) are included.
As-built Plans are being delivered to you and the owner.
There were no major changes to the project. We are waiting for a ventless, hinged, lockable lid for the
water tank. It should come in the mail any day. We are requesting permission to send you
documentation that the lid has been installed a few days from now. We would like to avoid immediate
interruption of water service. The tank does have a lid (an unapproved lid) and the tank is inside of a
locked building. We will install the approved lid as soon as we get it.
Location data is:
Well:Latitude: 37.74914 Longitude: -112.36316
Pump Building:Latitude: 37.74921 Longitude: -112.36363
It is my opinion that the completed project conforms (with the exception of the lid to be replaced) to the
requirements of the State Drinking Water Regulations. Please issue an operating permit for the project.
If you have questions, please call.
Thank you for your help.
Respectfully,
Lynn Wall, P.E.
Wall Engineering, Inc.
p.c.Aramark
c/o Dean Hutchings
P.O. Box 95315
South Jordan, Utah 84095
Dean@utahmrc.com
Department of Environmental Quality
620 South 400 East #400
St. George, Utah 84770
Wall Engineering, Inc.
55 South Main #2, P.O. Box 39
Fillmore, Utah 84631
(435) 864-7503 Cell
wallengineering@frontiernet.net
To:
Paul Wright, P.E.ATTENTION
RE:
DATE PHONE NO.May 15, 2024 (435) 680-0163
LYNN D.
WALL
No. 182598
Red Canyon Village Water System #9054
File # 13300.
Water Well and Storage Project Tank
2023-2024.