State of Utah
SPENCER I COX
Governor
DEIDRE HENDERSON
Lieutenant Governor
December 1, 2023
Blair Palmer
Department of
Environmental Quality
Kimberly D. Shelley
Executive Director
DIVISION OF DRINKING WATER
Tim Davis
Director
Northrop Grumman
P0 Box 707 MS 301
Brigham City, UT 84302
Subject: Corrective Action Plan for Northrop Grumman, UTAHO2O32 (2023-0 1)
Dear Blair Palmer:
The Division of Drinking Water (the Division) has received your request for a Corrective Action
Plan to address the significant deficiencies associated with the Northrop Grumman water system. A
copy of the Corrective Action Plan is enclosed with this letter. Please review the agreement and
sign a copy if you agree with the terms and return the signed copy to the Division within 14 days of
receipt of this agreement. A copy of the fully executed document will be returned to you.
Please oontact Brandi Smith at (385) 515-1650 or brandismith@utah.gov if you have any questions
regarding this letter or the enclosed copy of Corrective Action Plan.
Sincerely,
20 23 08 40 M ST)
Helen Lau
Compliance and Operations Manager
Division of Drinking Water
Enclosures -Northrop Grumman Corrective Action Plan 2023-01
cc: Blair Palmer, Northrop Grumman, blair.palmer@ngc.com
Ben Harker, Bear River Health Department, bharker@brhd.org
195 North 1950 West Salt Lake City, UT
Mailing Address: P.O. Box 144830 Salt Lake City, UT 84114-4830
Telephone (801) 536-4200 " Fax (801) 536-4211 " T.D.D. (801) 536-4414
wii'w.deq,utali.gov
Printed on 100% recycled paper
Exhibit A
Corrective Action Plan UTAHO2O32, 2023-01
System Name: Northrop Grumman
System Number: UTAHO2O32
Administrative Contact: Blair Palmer
Email: blair.palmerngc.com
Phone Number: 435-863-2430
Corrective Action Plan Requirements and Due Dates
Aiithliv Stnrwe (STflfl7'
Item #1 Deficiency Facility Significant Deficiency Rule Citation
_______ Code ID
V022 STOO7 Storage tank roof or sidewalls show signs of
______________________
R309-545-6(1) and 545-9(1)
severe deterioration
Corrective Action to be Taken Completion Due Date
Repair or replace tank so there is no ponding or deterioration on the 12/01/2024
sidewalls and lid
CAP Page 1
Corrective Action Plan (2023-01)
Northrop Grumman - UTAHO2O32
The purpose of this Corrective Action Plan ("CAP") is to establish terms and conditions of
compliance for Northrop Grumman ("System"), system number UTAHO2O32, to take actions and
correct significant deficiencies identified in Exhibit A.
The Corrective Action Plan terms and conditions are described in detail in Exhibit A. As long as
the System complies with every one of the requirements in Exhibit A, the Division will:
" Temporarily allow the extended deadlines for correcting the identified significant
deficiencies,
" Temporarily hold off assessing additional points for failure to fix violations, and
" Temporarily silence the significant deficiencies and hold off reporting those to US EPA.
Nothing in this Corrective Action Plan prohibits the Division from taking further enforcement
actions if the System fails to comply with any of the requirements in Exhibit A or if an imminent
public risk exists in the System.
We the undersigned parties agree to the terms, conditions and deadlines set forth in the Corrective
Action Plan (see Exhibit A).
Helen Lau
Compliance & Operations Manager
2023
Blair Palmer
Northrop Grumman
,2023
Signature:
Email:
Helen Lau (Dec 12, 2023 08:45 MST)
hlau@utah.gov