HomeMy WebLinkAboutDDW-2024-007978Utah Division of Drinking Water ― Checklist for Issuing Operating Permits
Water System Name: System Number:
Project Description: File Number:
Items 1 through 8 below must be submitted to the Division and found to be acceptable prior to
operating permit issuance (unless a water line project meets the requirements of R309-500-7 and
is not required to obtain an Operating Permit).
Distribution lines (not including in-line booster pump stations) requiring Plan Approval may be
placed into service prior to submitting all of the following items and receipt of Operating Permit
if the water system has received items 1 and 4 below.
☐1. Certification of Rule Conformance by a professional engineer (P.E.) that all conditions of
Plan Approval were accomplished, and if applicable, changes made during construction
were in conformance with rules R309-500 through 550
☐2. As-built or record drawings incorporating all changes to approved plans and
specifications (unless no changes were made to the previously approved plans during
construction)
☐3. Confirmation that as-built or record drawings have been received by the water system
☐4. Satisfactory bacteriological samples as evidence of proper disinfection and flushing in
accordance with the appropriate ANSI/AWWA standards:
☐ANSI/AWWA C651-14 AWWA Standard for Disinfecting Water Mains
Two consecutive sample sets at least 16 hours apart, none positive (e.g., every
1,200 feet, end-of-line, each branch)
☐ANSI/AWWA C652-11 AWWA Standard for Disinfection of Water-Storage Facilities
One or more samples, none positive
☐ANSI/AWWA C653-13 AWWA Standard for Disinfection of Water Treatment
Plants
Two consecutive samples per unit, none positive, no less than 30 minutes apart
☐ANSI/AWWA C654-13 AWWA Standard for Disinfection of Wells
Two consecutive samples, none positive, no less than 30 minutes apart
☐5. Water quality data, where appropriate [For example, include raw and finished water data that
demonstrate satisfactory performance of the treatment facility; sample should be taken from a
storage tank for residual volatile organic compounds after tank interior re-coating; etc.]
☐6. If applicable, all other documentation that may have been required during the plan review
process
☐7. If applicable, confirmation that the water system owner has received the O&M manual
for the new facility
☐8. If applicable, location data of new storage tank, treatment facility, or source