May 15, 2024
Atlas Technical Consultants, LLC
358 South 700 East, B518
Salt Lake City, Utah 84104
ERRL-0221-24
Re: Work Assignment MLS-23-ATC: Groundwater Monitoring with Reporting
Palmer Tire, located at 395 South 200 East, Roosevelt, Utah
Facility Identification No. 9000371, Release Site MLS
Dear Mr. Coletta:
The Department of Environmental Quality, Division of Environmental Response and
Remediation (DERR) requests that Atlas Technical Consultants, LLC (Atlas), complete the
enclosed Work Assignment, under Contract #216364. The enclosed Work Assignment identifies
the work necessary to conduct quarterly groundwater monitoring with reporting at the subject site.
Enclosed is an original copy of the Work Assignment and tasks to be completed. Please sign
and return electronically to the DERR.
If you have any questions concerning this Work Assignment, please contact Mark Crim,
the DERR Project Manager, at (801) 536-4100.
Sincerely,
Morgan P. Atkinson, PST Branch Manager
Division of Environmental Response and Remediation
MPA/MEC/rr
cc: Thomas Kingston, Division of Environmental Response and Remediation
195 North 1950 West• Salt Lake City, UT
Mailing Address : P.O . Box 144840 • Salt Lake City, UT 84114-4840
Telephone (801) 536-4100 • Fax (801) 359-8853 • T.D.D . (801) 536-4284
www.deq.utah.g ov
Printed on 100% recycled paper
WORK ASSIGNMENT MLS-23-ATC
Contract#: 216364
Work Assignment: Quarterly Groundwater Monitoring with Reporting
Palmer Tire, located at 395 South 200 East, Roosevelt, Utah
Facility Identification No. 9000371, Release Site MLS
The Consultant, Atlas, LLC (Atlas) is requested to complete the following Work Assignment:
I. WORK OBJECTIVE:
The work objective is to conduct quarterly groundwater monitoring with reporting for the
purpose of evaluating plume behavior.
II. TASKS:
The DERR has identified the following tasks, which follow Atlas's work plan and price
submitted on May 6, 2024:
A. June 2024 Groundwater Sampling with July 2024 Report
Cost: $7,663.05
B. September 2024 Groundwater Sampling with October 2024 Report
Cost: $7,511.05
C. December 2024 Groundwater Sampling with January 2025 Report
Cost: $7,511.05
D. March 2025 Groundwater Sampling with April 2025 Report
Cost: $7,511.05
E. June 2025 Groundwater Sampling with July 2025 Report
Cost: $7,511.05
F. September 2025 Groundwater Sampling with October 2025 Report
Cost: $7,511.05
Total Work Assignment Cost: $45,218.30
III. PRICE AND PAYMENT SCHEDULE:
A. The expense to the DERR for completing this Work Assignment shall not exceed
$45,218.30, including administrative costs, contract management, project
management and all other associated costs.
B. Payment requests shall be submitted when tasks are completed, as outlined in the
"Deliverable and Payment Schedule."
IV. SCHEDULE FOR COMPLETION OF WORK AND REPORTING
REQUIREMENTS
A. The DERR has set a start date of June 2024 for the above-referenced tasks. Atlas is
required to provide draft groundwater monitoring reports within 30-days of the work
outlined above.
B. After the DERR has reviewed and commented on the draft reports, Atlas will be
required to provide final groundwater monitoring reports within 4 days of receipt of
the DERR comments.
Approved by:
DERR Project Manager: ~~ Date: 05/15/2024
DERR Contract Officer: 1~m1~ Date: 05/15/2024
LUST Section Manager: ~~~ Date: 05/15/2024
Consultant: ,JfJ,.me,£ Cotetta. Date: 05/17/2024
James Coletta (Ma l 17, 202411:54 MDT)
DELIVERABLE AND PAYMENT SCHEDULE
Work Assignment: MLS -23-ATC
Deliverable/ Description Due Date Price Task
1 Quarterly Groundwater Sampling and Report July 2024 $7,663 .05
2 Quarterly Groundwater Sampling and Report October 2024 $7,511.05
3 Quarterly Groundwater Sampling and Report January 2025 $7,511.05
4 Quarterly Groundwater Sampling and Report April 2025 $7,511.05
5 Quarterly Groundwater Sampling and Report July 2025 $7,511.05
6 Quarterly Groundwater Sampling and Report October 2025 $7,511.05
Work Assignment Total: $45,218.30