MEMORANDUM
TO: FILE – SALT LAKE CITY CORP. – City/County Building Complex and Main City
Library
THROUGH: Chad Gilgen, Minor Source Compliance Section Manager
FROM: Jared James, Environmental Scientist
DATE: May 7, 2024
SUBJECT: FULL COMPLIANCE EVALUATION, Minor, Salt Lake County
INSPECTION DATE: April 25, 2024
SOURCE LOCATION: 450 South 200 East
Salt Lake City, UT 84111
DIRECTIONS: Enter the parking structure from 500 South, between 300 and
200 East.
SOURCE CONTACTS: Jeffrey Katter, Energy Utilities Management Coordinator
801-535-7280 jeff.katter@slcgov.com
OPERATING STATUS: Operating normally.
PROCESS DESCRIPTION: Salt Lake City Corporation operates three boilers and two
generators for the Salt Lake City and County Building, the
Leonardo Museum, and the Salt Lake City Public Library. The
9.8 MMBtu/hr boilers operate solely on natural gas, while the
6.0 MMBtu/hr boiler can operate on natural gas or diesel fuel.
Diesel fuel is only used during times of curtailment or testing.
The two emergency generators provide emergency power to the
complex. The boilers and one generator are located on the south
side of the underground parking structure for the library, with
entry to the boiler room on the lower level.
APPLICABLE REGULATIONS: Approval Order (AO) DAQE-AN128150002-22, dated March 3,
2022
NSPS (Part 60) Dc: Standards of Performance for Small
Industrial-Commercial-Institutional Steam Generating Units
MACT (Part 63) -ZZZZ: National Emissions Standards for
Hazardous Air Pollutants for Stationary Reciprocating Internal
Combustion Engines,
0 0
2
SOURCE EVALUATION:
Name of Permittee: Permitted Location:
Salt Lake City Corp.- City/County Building
Complex & Main City Library
451 South State Street 450 South 200 East
Salt Lake City, UT 84111 Salt Lake City, UT 84111
SIC Code: 9199: (General Government, NEC)
Section I: GENERAL PROVISIONS
I.1 All definitions, terms, abbreviations, and references used in this AO conform to those used in the
UAC R307 and 40 CFR. Unless noted otherwise, references cited in these AO conditions refer to
those rules. [R307-101]
I.2 The limits set forth in this AO shall not be exceeded without prior approval. [R307-401]
I.3 Modifications to the equipment or processes approved by this AO that could affect the emissions
covered by this AO must be reviewed and approved. [R307-401-1]
I.4 All records referenced in this AO or in other applicable rules, which are required to be kept by
the owner/operator, shall be made available to the Director or Director's representative upon
request, and the records shall include the two-year period prior to the date of the request. Unless
otherwise specified in this AO or in other applicable state and federal rules, records shall be kept
for a minimum of two (2) years. [R307-401-8]
I.5 At all times, including periods of startup, shutdown, and malfunction, owners and operators shall,
to the extent practicable, maintain and operate any equipment approved under this AO, including
associated air pollution control equipment, in a manner consistent with good air pollution control
practice for minimizing emissions. Determination of whether acceptable operating and
maintenance procedures are being used will be based on information available to the Director
which may include, but is not limited to, monitoring results, opacity observations, review of
operating and maintenance procedures, and inspection of the source. All maintenance performed
on equipment authorized by this AO shall be recorded. [R307-401-4]
I.6 The owner/operator shall comply with UAC R307-107. General Requirements: Breakdowns.
[R307-107]
I.7 The owner/operator shall comply with UAC R307-150 Series. Emission Inventories. [R307-150]
I.8 The owner/operator shall submit documentation of the status of construction or modification to
the Director within 18 months from the date of this AO. This AO may become invalid if
construction is not commenced within 18 months from the date of this AO or if construction is
discontinued for 18 months or more. To ensure proper credit when notifying the Director, send
the documentation to the Director, attn.: NSR Section. [R307-401-18]
Status: In Compliance. No limits appear to have been exceeded. No modifications have been
made to equipment or process. Records were provided by email after the inspection. No
reportable breakdowns have occurred since the previous inspection. The source submitted
a 2020 emission inventory, however a new AO was issued in 2022 which changed the
potential to emit values. All equipment was installed at the time the AO was issued.
3
Section II: SPECIAL PROVISIONS
II.A The approved installations shall consist of the following equipment:
II.A.1 City/County Office Complex & City Library Building
II.A.2 Two (2) 250 HP Boilers
Rated Input: 9.8 MMBtu/hr Each
Fuel: Natural Gas
Control: Low NOx Burner
Location: City Library Building
II.A.3 One (1) 150 HP Boiler
Rated Input: 6.0 MMBtu/hr
Fuels: Natural Gas, #2 Fuel Oil
Control: Low NOx Burner
Location: City Library Building
II.A.4 One (1) Emergency Generator
Electrical Output: 500 kW
Fuel: Diesel
Location: City Library Building
Installed Prior to 2005
II.A.5 One (1) Emergency Generator
Electrical Output: 278 kW
Fuel: Diesel
Location: City/County Office Building
Installed Prior to 2005
II.A.6 Parking Structure
630 Stalls
II.A.7 One (1) Storage Tank
Capacity: 10,000 gallons
Service: Diesel
* for information purposes only
Status: In Compliance. The equipment observed on site was consistent with that listed.
The source is planning to replace the generators with newer and larger models,
and a new AO, DAQE-AN128150003-24, dated April 29, 2024, was issued to
make the generator change.
II.B Requirements and Limitations
II.B.1 Limitations
II.B.1.a The owner/operator shall use natural gas as a primary fuel and #1 or #2 grade fuel oil (diesel
fuel) as a backup fuel in the 150 HP boiler. [R307-401-8]
Status: In Compliance. Only natural gas has been used in the boilers in the last 12 months.
No diesel fuel has been used in the 150 HP boiler.
II.B.1.b The owner/operator shall not operate the 150 HP boiler for more than 48 hours per rolling 12-
month total during periodic testing, maintenance, or operator training on liquid fuel. There is no
time limit on the use of the 150 HP boiler during gas curtailment, gas supply interruption, or
startups. [R307-401-8]
4
II.B.1.b.1 The owner/operator shall:
A. Determine hours of operation by monitoring and maintaining an operations log
B. Record hours of operation and reason for operation on liquid fuel each day
C. Use the hours of operation to calculate a new rolling 12-month total by the 20th day of
each month using data from the previous 12 months
D. Keep hours of operation records for all periods the plant is in operation. [R307-401-8]
Status: In Compliance. No diesel fuel has been used in the 150 HP boiler in the last 12
months.
II.B.1.c The owner/operator shall not consume more than the following:
A. 25,350 gallons of diesel fuel (#1 or #2 grade fuel oil) per rolling 12-month period
B. 166,486,100 standard cubic feet of natural gas per rolling 12-month period.
[R307-401-8]
II.B.1.c.1 The owner/operator shall:
A. Determine consumption by examination of the individual fuel supplier billing records
B. Record consumption of natural gas and diesel fuel on a daily basis
C. Use the records of natural gas and diesel fuel consumption to calculate a new rolling
12-month total by the 20th day of each month using data from the previous 12 months
D. Keep the consumption records for all periods the office/library complex is in operation.
[R307-401-8]
Status: In Compliance. In the rolling 12-month period, 147 gallons of diesel fuel was used
and 17,450,997 scf of natural gas. See attached.
II.B.1.d Visible emissions from the following emission points shall not exceed the following values:
A. All boilers fueled by natural gas - 10% opacity
B. All boilers fueled by diesel fuel - 20% opacity
C. All diesel engines - 20% opacity
D. All other points - 20% opacity. [R307-401-8]
II.B.1.d.1 Opacity observations of emissions from stationary sources shall be conducted in accordance with
40 CFR 60, Method 9. [R307-201-3]
Status: In Compliance. No visible emissions were observed from any point during the
inspection.
II.B.2 Emergency Engines
II.B.2.a The owner/operator shall not operate each emergency engine on site for more than 100 hours per
rolling 12-month period during non-emergency situations. There is no time limit on the use of
the engines during emergencies. [R307-401-8, 40 CFR 63 Subpart ZZZZ]
5
II.B.2.a.1 To determine compliance with a rolling 12-month total, the owner/operator shall calculate a new
12-month total by the 20th day of each month using data from the previous 12 months. Records
documenting the operation of each emergency engine shall be kept in a log and shall include the
following:
A. The date the emergency engine was used
B. The duration of operation in hours
C. The reason for the emergency engine usage
D. Keep the consumption records for all periods the office/library complex is in operation.
[40 CFR 60 Subpart ZZZZ, R307-401-8]
II.B.2.a.2 To determine the duration of operation, the owner/operator shall install a non-resettable hour
meter for each emergency engine. [R307-401-8, 40 CFR 63 Subpart ZZZZ]
Status: In Compliance. The 12-month rolling total for generator operation was 25.2 hours
for the 500 kW engine and one hour for the 278 kW engine. Fuel consumed during this
period was 147 gallons. Each generator is equipped with a non-resettable hour meter, the
500 kW's read 379.6 hours, and the 278 kW's read 286.1 at the time of inspection. See
attached.
II.B.2.b The owner/operator shall only use diesel fuel (e.g. fuel oil #1, #2, or diesel fuel oil additives) as
fuel in each emergency engine. [R307-401-8]
II.B.2.b.1 The owner/operator shall only combust diesel fuel that meets the definition of ultra-low sulfur
diesel (ULSD), which has a sulfur content of 15 ppm or less. [40 CFR 63 Subpart ZZZZ,
R307-401-8]
II.B.2.b.2 To demonstrate compliance with the ULSD fuel requirement, the owner/operator shall maintain
records of diesel fuel purchase invoices or obtain certification of sulfur content from the diesel
fuel supplier. The diesel fuel purchase invoices shall indicate that the diesel fuel meets the ULSD
requirements. [R307-401-8]
Status: In Compliance. Diesel fuel is purchased through Sinclair Oil and is certified to be
15 ppm or less sulfur content. See attached.
Section III: APPLICABLE FEDERAL REQUIREMENTS
In addition to the requirements of this AO, all applicable provisions of the following federal programs
have been found to apply to this installation. This AO in no way releases the owner or operator from any
liability for compliance with all other applicable federal, state, and local regulations including UAC
R307.
MACT (Part 63) JJJJJJ: National Emission Standards for Hazardous Air Pollutants for Industrial, Commercial,
and Institutional Boilers Area Sources
Status: In Compliance. The 150 HP boiler has not operated on diesel fuel in the last 12 months.
MACT (Part 63) ZZZZ: National Emissions Standards for Hazardous Air Pollutants for Stationary
Reciprocating Internal Combustion Engines
Status: In Compliance. The generator engines have operated for less than 100 hours in the last 12
months for testing and maintenance. Each engine is equipped with a non-resettable hour meter. Regular
maintenance is conducted, the last oil changes and annual maintenance check took place on September
23, 2023. An operation log is kept with each engine.
6
AREA SOURCE RULES EVALUATION:
The following Area Source Rules were evaluated during this inspection:
R307-214. National Emission Standards for Hazardous Air Pollutants
Status: In Compliance. This condition is met by compliance with ZZZZ. The 150 HP boiler did not
operate on diesel fuel in the last 12 months.
R307-309. Nonattainment and Maintenance Areas for PM10 and PM2.5: Fugitive Emissions and Fugitive
Dust
Status: In Compliance. No visible emissions were observed during the inspection. The grounds are
either paved or landscaped.
EMISSION INVENTORY:
The emissions listed below are an estimate of the total potential emissions (PTE) from Salt Lake City
Corp. - City/County Building Complex and Main City Library on the Approval Order (AO)
DAQE-AN128150002-22, dated March 3, 2022. PTE are supplied for supplemental purposes only.
Criteria Pollutant PTE tons/yr
CO2 Equivalent 13561.17
Carbon Monoxide 1.33
Nitrogen Oxides 4.04
Particulate Matter - PM10 0.90
Particulate Matter - PM2.5 0.90
Sulfur Dioxide 0.07
Volatile Organic Compounds 0.68
Hazardous Air Pollutant PTE lbs/yr
Generic HAPs (CAS #GHAPS) 420
PREVIOUS ENFORCEMENT
ACTIONS: No enforcement actions within the past five years.
COMPLIANCE STATUS &
RECOMMENDATIONS: In regards to Approval Order (AO) DAQE-AN128150002-22,
dated March 3, 2022: the source should be considered in
compliance. The facility appeared to be well maintained and
operated properly. Records were provided by email post
inspection.
HPV STATUS: Not Applicable.
7
RECOMMENDATION FOR
NEXT INSPECTION: Inspect as normal. Look for the new AO
DAQE-AN128150003-24, dated April 29, 2024. The source is
planning to replace the emergency generators. The inspector may
also want to contact Jeff Katter prior to the visit, his office is off
campus a few blocks away at 248 East 600 South, and is a
secured location.
NSR RECOMMENDATIONS: None at this time.
ATTACHMENTS: VEO Form, Fuel, Maintenance, and Operation Records, Email
HF Sinclair Parco Refining LLC ⦁Laboratory Services⦁Sinclair, WY Certificate of Analysis, Pioneer Pipeline #2 ULSD Diesel Fuel
Transferor:HF Sinclair Parco Refining LLC 100 E. Lincoln Highway ⦁ PO Box 277Sinclair, WY 82334EPA Company ID: 5053, Facility ID: 23521
Transferee:ConocoPhillipsPioneer Pipeline600 N. Dairy Ashford RoadHouston, TX 77079-1175EPA Company ID: 4528, Facility ID: 82245
Sample Date: 3/13/2024 Tester(s): Kelsey Jaure, Kelsey Jaure
Tank Number: Tank 532 Sampler: K. Krejci
LIMS ID: 798488 EPA Batch Number: 5053-23521-24-500066
Tender:
Available BBLS:
Approved By: Date: 3/13/2024
Kelsey Jaure
#2 Diesel 15ppm w/w Sulfur Motor Vehicle Diesel Fuel.
15 ppm sulfur (maximum) Undyed Ultra-Low Sulfur Diesel Fuel. For use in all diesel vehicles and engines.
Lubricity/conductivity additives may need to be added at the terminal in order for the fuel to meet ASTM D975
requirements.
SPECIFICATIONSTestMETHODRESULT
MINIMUM MAXIMUM
Gravity, API @ 60°F ASTM D4052 35.0 30.0
Flash Point (PMCC), °F ASTM D93 141.0 135.0
Haze @ 50°F ASTM D4176, Proc. 2 1 2
Bright & Clear ASTM D4176 Pass PASS
Color ASTM D1500 1.0 2.5
Ash, wt%ASTM D482 <0.001 0.010
Distillation @ 760mmHg, °F ASTM D86
IBP 326.3 REPORT
10 vol.% Recovered 403.4 REPORT
50 vol.% Recovered 519.6 REPORT
90 vol.% Recovered 631.0 540.0 640.0
FBP 681.6 698.0
% Total Recovered 99.6 REPORT
% Residue 1.4 REPORT
BS&W, vol%ASTM D2709 0.025 0.050
Sulfur, ppm ASTM D7039 7.7 12.0
Copper Strip Corrosion, 3hr @ 122°F ASTM D130 1a 1b
CR, Ramsbottom, wt%ASTM D524 0.07 0.35
Thermal Stability, Y Filter ASTM D6468 99.4 82.0
Cetane Index, 4V ASTM D4737, Proc. A 46.8 40.0
Cetane Index, 2V ASTM D976 48.0 40.0
Cloud Point, °F ASTM D5773 4.3 10.0
Pour Point, °F ASTM D5949 -5 0
Conductivity, pS/m @ T, °C ASTM D2624 0 @ 21.3 10
Viscosity @ 104°F, cSt ASTM D445 2.813 1.9 3.4
NACE Rust Test, Rating TM0172-2001 A B+
Task Summary
Task ID Facility Activity Asset
815514 Library Square Boiler Room PM Boiler Weekly HVAC BLR-BOL-001
PM Descripiton Task Description Tasks Notes
Blow down boiler
Test water supply samples
Check water softener and add
salt to brine tank if needed
Check all boiler room
equipment
Record findings on Boiler Logs
-WHA-
-LOTO-
2/8/24 perform weekly tests DF
Basic Information Costs
Status Completed Labor $86.73
Priority Medium Equipment $0.00
Start Date 2/8/2024 Material $0.00
Stop Date 3/1/2024 Other $0.00
Total $86.73
Assignments
ID Full Name
027265 Russ Hansen
1001431 David Fisher
1001541 Steve Minch
102698 Brandon Maestas
4/24/2024 Generated by Cartegraph Page 1
Task Summary
Task ID Facility Activity Asset
815514 Library Square Boiler Room PM Boiler Weekly HVAC BLR-BOL-001
PM Descripiton Task Description Tasks Notes
Blow down boiler
Test water supply samples
Check water softener and add
salt to brine tank if needed
Check all boiler room
equipment
Record findings on Boiler Logs
-WHA-
-LOTO-
2/8/24 perform weekly tests DF
ID Full Name
129110 Alex Brow n
Total Assignments 5
4/24/2024 Generated by Cartegraph Page 2
Task Summary
Task ID Facility Activity Asset
821122 Library Square Boiler Room PM Boiler Service
Quarterly HVAC BLR-BOL-001
PM Descripiton Task Description Tasks Notes
1.Visually inspect unit, look for
any leaks or problems
2.Watch for water and fuel
connection leaks, repair them
as soon as possible
3.Check the feedwater
treatment. Make sure that it
operates correctly. Shut the
boiler off and allow system to
cool
4.Clean the fire tubes, if the
tubes are sooted clean them
5.Inspect the boiler feed pump
packing glands and tighten
when needed
6.Check for any replacement
needs or refactory
maintenance needs
7.Check for required burner
maintenance, the burner nozzle
consists of a nozzle tip,
strainer, locknut, disc and
brass body. Keep the burner
nozzle clean
8.Check the following electrical
controls for proper
maintenance:
a.Motor starts are a
three-phase motor. Replace or
repair as needed
b.Check all thermal relay units
c.Inspect the program control
relays
d.Check the safety warp reset
button for correct operation
e.Check the high limit pressure
4/24/2024 Generated by Cartegraph Page 1
or temperature control switch
f.Check the low water control
switch for correct operation
9.Make all necessary
adjustments and fill boiler
10.Return boiler to service,
making sure that unit has been
inspected for correct operation
Report any problems to your
supervisor
-WHA-
-LOTO-
Basic Information Costs
Status Completed Labor $48.72
Priority Low Equipment $0.00
Start Date 3/11/2024 Material $0.00
Stop Date 3/11/2024 Other $0.00
Total $48.72
Assignments
ID Full Name
027265 Russ Hansen
1001431 David Fisher
1001541 Steve Minch
102698 Brandon Maestas
129110 Alex Brow n
Total Assignments 5
4/24/2024 Generated by Cartegraph Page 2
Task Summary
Task ID Facility Activity Asset
716224 Library Square Boiler Room Inspection Generators
Weekly
Electrical Generator
BLR-EPG-001
PM Descripiton Task Description Tasks Notes
Generator is scheduled to run
differently for each building.
Maintenance for generator:
1.Check fuel level is above ¾
2.Check that voltage is approx.
60 hertz and 120, 208, 480
depending upon building
3.Check that antifreeze is full
and within spec
4.Check battery condition,
voltage 12V +- 1, and age
5.Check general operation
6.Visually inspect transfer
switch **Record finding in the
comments** if there is a
problem shut off the machine.
7.Run time is set for ½ hour
8.Make sure start time has
been adjusted for daylight
saving each spring and fall
9.**Record the start/stop hours
for the machine in the comment
field**
10. Check engine oil level
Report any problems to
Supervisor
-WHA-
Basic Information Costs
Status Completed Labor $37.82
Priority Medium Equipment $0.00
4/25/2024 Generated by Cartegraph Page 1
Task Summary
Task ID Facility Activity Asset
716224 Library Square Boiler Room Inspection Generators
Weekly
Electrical Generator
BLR-EPG-001
PM Descripiton Task Description Tasks Notes
Generator is scheduled to run
differently for each building.
Maintenance for generator:
1.Check fuel level is above ¾
2.Check that voltage is approx.
60 hertz and 120, 208, 480
depending upon building
3.Check that antifreeze is full
and within spec
4.Check battery condition,
voltage 12V +- 1, and age
5.Check general operation
6.Visually inspect transfer
switch **Record finding in the
comments** if there is a
problem shut off the machine.
7.Run time is set for ½ hour
8.Make sure start time has
been adjusted for daylight
saving each spring and fall
9.**Record the start/stop hours
for the machine in the comment
field**
10. Check engine oil level
Report any problems to
Supervisor
-WHA-
Start Date 4/19/2024 Material $0.00
Stop Date 4/19/2024 Other $0.00
Total $37.82
4/25/2024 Generated by Cartegraph Page 2
Task Summary
Task ID Facility Activity Asset
716224 Library Square Boiler Room Inspection Generators
Weekly
Electrical Generator
BLR-EPG-001
PM Descripiton Task Description Tasks Notes
Generator is scheduled to run
differently for each building.
Maintenance for generator:
1.Check fuel level is above ¾
2.Check that voltage is approx.
60 hertz and 120, 208, 480
depending upon building
3.Check that antifreeze is full
and within spec
4.Check battery condition,
voltage 12V +- 1, and age
5.Check general operation
6.Visually inspect transfer
switch **Record finding in the
comments** if there is a
problem shut off the machine.
7.Run time is set for ½ hour
8.Make sure start time has
been adjusted for daylight
saving each spring and fall
9.**Record the start/stop hours
for the machine in the comment
field**
10. Check engine oil level
Report any problems to
Supervisor
-WHA-
Assignments
4/25/2024 Generated by Cartegraph Page 3
Task Summary
Task ID Facility Activity Asset
716224 Library Square Boiler Room Inspection Generators
Weekly
Electrical Generator
BLR-EPG-001
PM Descripiton Task Description Tasks Notes
Generator is scheduled to run
differently for each building.
Maintenance for generator:
1.Check fuel level is above ¾
2.Check that voltage is approx.
60 hertz and 120, 208, 480
depending upon building
3.Check that antifreeze is full
and within spec
4.Check battery condition,
voltage 12V +- 1, and age
5.Check general operation
6.Visually inspect transfer
switch **Record finding in the
comments** if there is a
problem shut off the machine.
7.Run time is set for ½ hour
8.Make sure start time has
been adjusted for daylight
saving each spring and fall
9.**Record the start/stop hours
for the machine in the comment
field**
10. Check engine oil level
Report any problems to
Supervisor
-WHA-
ID Full Name
095807 John Pananos
1001097 Giovanni Fernandez
104653 Martin Chacon
4/25/2024 Generated by Cartegraph Page 4
Task Summary
Task ID Facility Activity Asset
716224 Library Square Boiler Room Inspection Generators
Weekly
Electrical Generator
BLR-EPG-001
PM Descripiton Task Description Tasks Notes
Generator is scheduled to run
differently for each building.
Maintenance for generator:
1.Check fuel level is above ¾
2.Check that voltage is approx.
60 hertz and 120, 208, 480
depending upon building
3.Check that antifreeze is full
and within spec
4.Check battery condition,
voltage 12V +- 1, and age
5.Check general operation
6.Visually inspect transfer
switch **Record finding in the
comments** if there is a
problem shut off the machine.
7.Run time is set for ½ hour
8.Make sure start time has
been adjusted for daylight
saving each spring and fall
9.**Record the start/stop hours
for the machine in the comment
field**
10. Check engine oil level
Report any problems to
Supervisor
-WHA-
ID Full Name
497810 Sean Odell
500706 Bill Porm
844769 Daniel Tali
4/25/2024 Generated by Cartegraph Page 5
Task Summary
Task ID Facility Activity Asset
716224 Library Square Boiler Room Inspection Generators
Weekly
Electrical Generator
BLR-EPG-001
PM Descripiton Task Description Tasks Notes
Generator is scheduled to run
differently for each building.
Maintenance for generator:
1.Check fuel level is above ¾
2.Check that voltage is approx.
60 hertz and 120, 208, 480
depending upon building
3.Check that antifreeze is full
and within spec
4.Check battery condition,
voltage 12V +- 1, and age
5.Check general operation
6.Visually inspect transfer
switch **Record finding in the
comments** if there is a
problem shut off the machine.
7.Run time is set for ½ hour
8.Make sure start time has
been adjusted for daylight
saving each spring and fall
9.**Record the start/stop hours
for the machine in the comment
field**
10. Check engine oil level
Report any problems to
Supervisor
-WHA-
ID Full Name
Total Assignments 6
4/25/2024 Generated by Cartegraph Page 6
Task Summary
Task ID Facility Activity Asset
819770 City Hall Inspection Generators
Monthly
Electrical Generator
CCB-EPG-001
PM Descripiton Task Description Tasks Notes
Generator is scheduled to run
differently for each building.
Maintenance for generator:
1.Check fuel level is above ¾
2.Check that voltage is approx.
60 hertz and 120, 208, 480
depending upon building
3.Check that antifreeze is full
and within spec
4.Check battery condition,
voltage 12V +- 1, and age
5.Check general operation
6.Visually inspect transfer
switch **Record finding in the
comments** if there is a
problem shut off the machine.
7.Run time is set for ½ hour
8.Make sure start time has
been adjusted for daylight
saving each spring and fall
9.**Record the start/stop hours
for the machine in the comment
field**
10. Check engine oil level
Report any problems to
Supervisor
-WHA-
Basic Information Costs
Status Completed Labor $34.58
Priority Medium Equipment $0.00
4/24/2024 Generated by Cartegraph Page 1
Task Summary
Task ID Facility Activity Asset
819770 City Hall Inspection Generators
Monthly
Electrical Generator
CCB-EPG-001
PM Descripiton Task Description Tasks Notes
Generator is scheduled to run
differently for each building.
Maintenance for generator:
1.Check fuel level is above ¾
2.Check that voltage is approx.
60 hertz and 120, 208, 480
depending upon building
3.Check that antifreeze is full
and within spec
4.Check battery condition,
voltage 12V +- 1, and age
5.Check general operation
6.Visually inspect transfer
switch **Record finding in the
comments** if there is a
problem shut off the machine.
7.Run time is set for ½ hour
8.Make sure start time has
been adjusted for daylight
saving each spring and fall
9.**Record the start/stop hours
for the machine in the comment
field**
10. Check engine oil level
Report any problems to
Supervisor
-WHA-
Start Date 3/7/2024 Material $0.00
Stop Date 3/7/2024 Other $0.00
Total $34.58
4/24/2024 Generated by Cartegraph Page 2
Task Summary
Task ID Facility Activity Asset
819770 City Hall Inspection Generators
Monthly
Electrical Generator
CCB-EPG-001
PM Descripiton Task Description Tasks Notes
Generator is scheduled to run
differently for each building.
Maintenance for generator:
1.Check fuel level is above ¾
2.Check that voltage is approx.
60 hertz and 120, 208, 480
depending upon building
3.Check that antifreeze is full
and within spec
4.Check battery condition,
voltage 12V +- 1, and age
5.Check general operation
6.Visually inspect transfer
switch **Record finding in the
comments** if there is a
problem shut off the machine.
7.Run time is set for ½ hour
8.Make sure start time has
been adjusted for daylight
saving each spring and fall
9.**Record the start/stop hours
for the machine in the comment
field**
10. Check engine oil level
Report any problems to
Supervisor
-WHA-
Assignments
4/24/2024 Generated by Cartegraph Page 3
Task Summary
Task ID Facility Activity Asset
819770 City Hall Inspection Generators
Monthly
Electrical Generator
CCB-EPG-001
PM Descripiton Task Description Tasks Notes
Generator is scheduled to run
differently for each building.
Maintenance for generator:
1.Check fuel level is above ¾
2.Check that voltage is approx.
60 hertz and 120, 208, 480
depending upon building
3.Check that antifreeze is full
and within spec
4.Check battery condition,
voltage 12V +- 1, and age
5.Check general operation
6.Visually inspect transfer
switch **Record finding in the
comments** if there is a
problem shut off the machine.
7.Run time is set for ½ hour
8.Make sure start time has
been adjusted for daylight
saving each spring and fall
9.**Record the start/stop hours
for the machine in the comment
field**
10. Check engine oil level
Report any problems to
Supervisor
-WHA-
ID Full Name
095807 John Pananos
1001097 Giovanni Fernandez
104653 Martin Chacon
4/24/2024 Generated by Cartegraph Page 4
Task Summary
Task ID Facility Activity Asset
819770 City Hall Inspection Generators
Monthly
Electrical Generator
CCB-EPG-001
PM Descripiton Task Description Tasks Notes
Generator is scheduled to run
differently for each building.
Maintenance for generator:
1.Check fuel level is above ¾
2.Check that voltage is approx.
60 hertz and 120, 208, 480
depending upon building
3.Check that antifreeze is full
and within spec
4.Check battery condition,
voltage 12V +- 1, and age
5.Check general operation
6.Visually inspect transfer
switch **Record finding in the
comments** if there is a
problem shut off the machine.
7.Run time is set for ½ hour
8.Make sure start time has
been adjusted for daylight
saving each spring and fall
9.**Record the start/stop hours
for the machine in the comment
field**
10. Check engine oil level
Report any problems to
Supervisor
-WHA-
ID Full Name
497810 Sean Odell
500706 Bill Porm
844769 Daniel Tali
4/24/2024 Generated by Cartegraph Page 5
Task Summary
Task ID Facility Activity Asset
819770 City Hall Inspection Generators
Monthly
Electrical Generator
CCB-EPG-001
PM Descripiton Task Description Tasks Notes
Generator is scheduled to run
differently for each building.
Maintenance for generator:
1.Check fuel level is above ¾
2.Check that voltage is approx.
60 hertz and 120, 208, 480
depending upon building
3.Check that antifreeze is full
and within spec
4.Check battery condition,
voltage 12V +- 1, and age
5.Check general operation
6.Visually inspect transfer
switch **Record finding in the
comments** if there is a
problem shut off the machine.
7.Run time is set for ½ hour
8.Make sure start time has
been adjusted for daylight
saving each spring and fall
9.**Record the start/stop hours
for the machine in the comment
field**
10. Check engine oil level
Report any problems to
Supervisor
-WHA-
ID Full Name
Total Assignments 6
4/24/2024 Generated by Cartegraph Page 6
Salt Lake City Fleet Management
W300d - WorkOrderDetailsByDate
4/25/2024 6:07:24 AM
p.1WORK ORDER DETAILS REPORT
WORK ORDER: 775741244
ASSET NUMBER: GenCC
Work Order Status: C - Closed Date In: 07/06/2023
Work Order Shop: XSP - Mobile Service Date Out:09/22/2023
ASSET NUMBER INFORMATION
YEAR: 1987 ORG: Salt Lake City Corp TIRE SIZE:
MAKE: Cummins DEPT: Public Services Facilities ENGINE SIZE: NT 855-G33
MODEL: Generator BILL CODE: Bill everything but (Ins, Miles,
Base, Replacement)
TRANS:
LICENSE: N/A SITE: Facilities Management FUEL TYPE: B, W, D
OPERATOR: Mike Adkins VIN/SERIAL NUMBER: 3030B42B ASSET AVAIL CODE: 7am to 4pm M-F
CLASS: Non Self Propelled Generator Stations METERS: Hour Meter - 2680
TECHNICIAN REPAIRS PERFORMED
TECH END DATE REPAIR DESCRIPTION HOURS LABOR COST
BODILY 09/01/2023 Maintenance / Preventative Maintenance / PM B
Service / Perform
2.55 $346.233
BODILY 09/21/2023 Repaired From PM Service / Engine / Gasket
ValveCov / Replace
2.50 $339.774
Salt Lake City Fleet Management
W300d - WorkOrderDetailsByDate
4/25/2024 6:07:24 AM
p.2WORK ORDER DETAILS REPORT
PARTS ISSUED
PART NUMBER S/NS ISS QTY PART PRICE ISSUE DATE TOTAL PART COST
3067459 NS 1.000 $38.557 09/15/2023 $38.557
PART NAME: Gasket, Cover, Valve, Cummins, Generator REPAIR: Repaired From PM Service / Engine / Gasket ValveCov / Replace
107981 NS 1.000 $149.411 09/18/2023 $149.411
PART NAME: Cap, Filler, Oil, Cummins, Generator REPAIR: Repaired From PM Service / Engine / Gasket ValveCov / Replace
64775 NS 1.000 $22.044 09/18/2023 $22.044
PART NAME: Hose, Crankcase, Cummins, Generator REPAIR: Repaired From PM Service / Engine / Gasket ValveCov / Replace
3038076 NS 14.000 $3.083 09/18/2023 $43.162
PART NAME: Screw, Cover, Valve, Cummins, Generator REPAIR: Repaired From PM Service / Engine / Gasket ValveCov / Replace
S 602 NS 1.000 $5.940 09/18/2023 $5.940
PART NAME: washer, cover, valve, cummins, generator REPAIR: Repaired From PM Service / Engine / Gasket ValveCov / Replace
63385 NS 1.000 $37.924 09/18/2023 $37.924
PART NAME: Spacer, Screw, Cover, Valve, Cummins REPAIR: Repaired From PM Service / Engine / Gasket ValveCov / Replace
3035624 NS 1.000 $7.049 09/18/2023 $7.049
PART NAME: Screw, Long, Cover, Valve, Cummins, Gen REPAIR: Repaired From PM Service / Engine / Gasket ValveCov / Replace
FS1212 S 1.000 $9.345 08/09/2023 $9.345
PART NAME: Separator,Fuel,Cummins,8.3L REPAIR: Maintenance / Preventative Maintenance / PM B Service /
Perform
FS1000 S 1.000 $12.277 08/09/2023 $12.277
PART NAME: Filter,Separator,Fuel,Intern,Cummins,ISM REPAIR: Maintenance / Preventative Maintenance / PM B Service /
Perform
WF2122 S 1.000 $35.849 08/09/2023 $35.849
PART NAME: Filter,Water/Coolant,Cummins,06,ISM,500 REPAIR: Maintenance / Preventative Maintenance / PM B Service /
Perform
1970XE NS 1.000 $34.320 08/15/2023 $34.320
PART NAME: Filter,Oil,Detroit,92,8V REPAIR: Maintenance / Preventative Maintenance / PM B Service /
Perform
9923 NS 1.000 $221.311 08/15/2023 $221.311
PART NAME: Filter,Air,Cummins,Generator REPAIR: Maintenance / Preventative Maintenance / PM B Service /
Perform
226535721 S 3.000 $7.454 08/17/2023 $22.362
PART NAME: Oil.ATF.Synthetic.Bottle.Quart REPAIR: Maintenance / Preventative Maintenance / PM B Service /
Perform
VABO215.3 S 1.000 $26.398 08/18/2023 $26.398
PART NAME: Oil,15W40,Valvoline,PB,1,SOL,GEN2,Gallon REPAIR: Maintenance / Preventative Maintenance / PM B Service /
Perform
MISCELLANEOUS COSTS
CODE DESCRIPTION POSTED DATE MISC COST
Shop Charge Shop Charge 07/06/2023 $25.000
WORK ORDER TOTALS
TOTAL PARTS:$665.949 PARTS TAX:$0.000 MANUAL ADJUSTMENTS:$0.000
TOTAL SUBLET:$0.000 SUBLET TAX:$0.000
Salt Lake City Fleet Management
W300d - WorkOrderDetailsByDate
4/25/2024 6:07:24 AM
p.3WORK ORDER DETAILS REPORT
TOTAL LABOR:$686.007 TOTAL MISC:$25.000 TOTAL COST:$1,376.956
NOTES
PMB - ; 8-18-23 - Traveled to location and attempted to complete the PMB service, unable to do so due to an event being set up at the City-
County building. Will return or completion later. ; PMB - Traveled to location, completed replacement of the engine oil filters, the engine primary
and secondary fuel filters, the engine air filter, and the engine coolant filter. Ran the engine to confirm that the unit is operational post service.
Topped off the oil and checked the coolant. Completed. ; Valve cover - When completing the filter service, noted that the engine is still leaking
from the valve covers, ordered from parts for repair. ; PR-Gasket and Screw - ; PO - see dropdown; Peterbilt; ETA 9/22 - Valve Cover Gasket x3 -
Arrived Filler Cap Hose Screw x14 Screw - Arrived Washer Spacer ; PR- Gen Parts / Still waiting on one parts. - ; Valve cover gasket - After
obtaining new parts, traveled to City County and replaced the engine valve cover gaskets and associated hardware. Replaced the engine oil cap
on the unit. Removed the engine breather and cleaned. Replaced the existing breather as a new one is not available. Resealed the breather
with new silicone after cleaning. Completed. ; Reviewed and Closed -
Salt Lake City Fleet Management
W300d - WorkOrderDetailsByDate
4/25/2024 6:07:24 AM
p.4WORK ORDER DETAILS REPORT
WORK ORDER: 775744711
ASSET NUMBER: GenCC
Work Order Status: C - Closed Date In: 10/20/2023
Work Order Shop: XSP - Mobile Service Date Out:02/07/2024
ASSET NUMBER INFORMATION
YEAR: 1987 ORG: Salt Lake City Corp TIRE SIZE:
MAKE: Cummins DEPT: Public Services Facilities ENGINE SIZE: NT 855-G33
MODEL: Generator BILL CODE: Bill everything but (Ins, Miles,
Base, Replacement)
TRANS:
LICENSE: N/A SITE: Facilities Management FUEL TYPE: B, W, D
OPERATOR: Mike Adkins VIN/SERIAL NUMBER: 3030B42B ASSET AVAIL CODE: 7am to 4pm M-F
CLASS: Non Self Propelled Generator Stations METERS: Hour Meter - 2680
TECHNICIAN REPAIRS PERFORMED
TECH END DATE REPAIR DESCRIPTION HOURS LABOR COST
BODILY 02/07/2024 Repaired From PM Service / Exhaust System /
Clamp / Replace
1.93 $263.123
BODILY 02/07/2024 Repaired From PM Service / Cooling System /
System / Diagnosis
0.15 $19.796
BODILY 02/07/2024 Maintenance / Preventative Maintenance / PM I
Service / Perform
1.61 $219.489
BODILY 02/07/2024 Repaired From PM Service / Cooling System / Pre-
Heater Cool / Replace
8.17 $1,111.422
BODILY 02/07/2024 Repaired From PM Service / Engine / Cooler Engine
O / Repair
0.00 $0.076
PARTS ISSUED
PART NUMBER S/NS ISS QTY PART PRICE ISSUE DATE TOTAL PART COST
6601659 NS 2.000 $4.620 02/01/2024 $9.240
PART NAME: Connector, Hose, Heater, 5/8 x 3/4 REPAIR: Repaired From PM Service / Cooling System / System /
Diagnosis
10SHH NS 5.000 $13.487 02/06/2024 $67.435
PART NAME: Hose,Heater 5/8" Silicone REPAIR: Repaired From PM Service / Cooling System / System /
Diagnosis
085W2 NS 4.000 $2.402 01/17/2024 $9.608
PART NAME: Clamp, Bolt, 21-23mm, 13/16"-29/32"REPAIR: Repaired From PM Service / Exhaust System / Clamp / Replace
100W2 NS 4.000 $2.442 01/17/2024 $9.768
PART NAME: Clamp REPAIR: Repaired From PM Service / Exhaust System / Clamp / Replace
105W2 NS 3.000 $2.468 01/17/2024 $7.404
PART NAME: Clamp REPAIR: Repaired From PM Service / Exhaust System / Clamp / Replace
80335 NS 2.000 $3.802 01/31/2024 $7.604
PART NAME: Sealer,Pipe,Tail & Muffler,Permatex REPAIR: Repaired From PM Service / Exhaust System / Clamp / Replace
KAT13200 NS 1.000 $173.804 12/20/2023 $173.804
PART NAME: Heater,Engine,Tank Circulation,2000W REPAIR: Repaired From PM Service / Engine / Cooler Engine O / Repair
Salt Lake City Fleet Management
W300d - WorkOrderDetailsByDate
4/25/2024 6:07:24 AM
p.5WORK ORDER DETAILS REPORT
12mp-12mp NS 2.000 $4.066 02/01/2024 $8.132
PART NAME: Fittings REPAIR: Repaired From PM Service / Engine / Cooler Engine O / Repair
12MP-12FP90 NS 2.000 $8.897 02/01/2024 $17.794
PART NAME: Connector,Male X Female Pipe,90 REPAIR: Repaired From PM Service / Engine / Cooler Engine O / Repair
12-12MPX-B NS 2.000 $10.204 02/01/2024 $20.408
PART NAME: Barb x Male Pipe Swivel REPAIR: Repaired From PM Service / Engine / Cooler Engine O / Repair
VLVMPB-12FP-12FP NS 2.000 $52.932 02/01/2024 $105.864
PART NAME: Valve, Ball, Steel, Carbon, 3/4"REPAIR: Repaired From PM Service / Engine / Cooler Engine O / Repair
16MP-12FP S 2.000 $4.528 02/01/2024 $9.056
PART NAME: Fitting REPAIR: Repaired From PM Service / Engine / Cooler Engine O / Repair
20MP-16FP NS 2.000 $7.669 02/01/2024 $15.338
PART NAME: Male Pipe x Female Pipe REPAIR: Repaired From PM Service / Engine / Cooler Engine O / Repair
1PGJ9 NS 1.000 $43.666 01/18/2024 $43.666
PART NAME: Plug, STRT, GCM REPAIR: Repaired From PM Service / Cooling System / Pre-Heater Cool /
Replace
792T39 NS 1.000 $21.714 01/18/2024 $21.714
PART NAME: Plug, Locking REPAIR: Repaired From PM Service / Cooling System / Pre-Heater Cool /
Replace
5A087 NS 1.000 $60.878 01/18/2024 $60.878
PART NAME: Plug, Locking, STRT, 30A REPAIR: Repaired From PM Service / Cooling System / Pre-Heater Cool /
Replace
DSLC5 S 2.000 $13.970 01/26/2024 $27.940
PART NAME: Decal,5",Round,City/County (White)REPAIR: Maintenance / Preventative Maintenance / PM I Service / Perform
VABO215.0 S 7.000 $4.479 02/02/2024 $31.353
PART NAME: Oil,15W40,Valvoline,PB,1,SOL,GEN2,Bulk,REPAIR: Maintenance / Preventative Maintenance / PM I Service / Perform
MISCELLANEOUS COSTS
CODE DESCRIPTION POSTED DATE MISC COST
Shop Charge Shop Charge 10/20/2023 $25.000
WORK ORDER TOTALS
TOTAL PARTS:$647.006 PARTS TAX:$0.000 MANUAL ADJUSTMENTS:$0.000
TOTAL SUBLET:$0.000 SUBLET TAX:$0.000
TOTAL LABOR:$1,613.906 TOTAL MISC:$25.000 TOTAL COST:$2,285.912
NOTES
Salt Lake City Fleet Management
W300d - WorkOrderDetailsByDate
4/25/2024 6:07:24 AM
p.6WORK ORDER DETAILS REPORT
PMI - ; PMI - Traveled to location, completed inspection on the unit for service needs. Inspected the engine oil, the engine coolant, the engine
drive belts, the operating condition of the engine, and the engine components. Found several items that need to be addressed, parts request
handed to Kathy. See other lines for repairs needed. Completed. ; Repairs needed - The unit needs a new block heater, a new oil temp sensor,
and a new coolant level sensor. The decision has been made to forgo this portion of the repair as the unit is slated to be replaced in the mid
future as per Dru. The safety shut down on the engine is still operative, this is only for the gauges on the panel. ; ALEX WILL GET THE MODEL
NUMBER SO WE CAN ORDER PARTS. - ; UPDATE NO PARTS ORDERED WAITING FOR ALEX TO GET INFO. - ; PO-Engine Heater from Napa by end
of day. - ; Block heater - Traveled to the City County building and met with the Electricians for Facilities and talked to them about the needs of
the unit for repair and retrofit to plugs for the new block heater that will be installed on the unit. After the plugs were installed, retuned and
installed a 2000 watt heater to see if this can keep the engine warmer and allow for better runability during exercise. Installed new fitting in the
engine that were obtained from Hose and Rubber including shut off valves to allow for future repair as needed. Installed new hoses for the heater
as well. Completed. ; PR-Heater - ; PO- Muffler Sealer from Parts Authority ETA 1/31/24 - ; Exhaust repair - Traveled to location, found that the
gasket between the turbo and the exhaust piping has failed fully and is in need of replacement. Unable to locate a suitable replacement due to
the age on the genset. Ordered Permatex Ceramic exhaust seal and removed the pipe section that was leaking. Cleaned with wire wheel and
installed back on the unit with the ceramic sealer. Found that there is oil coming from the pipe, possible the turbo outlet. Will check at next PM
to see if the problem needs to be addressed. Confirmed no further leaks. Completed. ; Reviewed & Closed -
Salt Lake City Fleet Management
W300d - WorkOrderDetailsByDate
4/25/2024 6:07:24 AM
p.7WORK ORDER DETAILS REPORT
WORK ORDER: 775746320
ASSET NUMBER: GenCC
Work Order Status: C - Closed Date In: 12/12/2023
Work Order Shop: HSP - Heavy Shop Date Out:12/12/2023
ASSET NUMBER INFORMATION
YEAR: 1987 ORG: Salt Lake City Corp TIRE SIZE:
MAKE: Cummins DEPT: Public Services Facilities ENGINE SIZE: NT 855-G33
MODEL: Generator BILL CODE: Bill everything but (Ins, Miles,
Base, Replacement)
TRANS:
LICENSE: N/A SITE: Facilities Management FUEL TYPE: B, W, D
OPERATOR: VIN/SERIAL NUMBER: 3030B42B ASSET AVAIL CODE: 7am to 4pm M-F
CLASS: Non Self Propelled Generator Stations METERS: Hour Meter - 2680
PARTS ISSUED
PART NUMBER S/NS ISS QTY PART PRICE ISSUE DATE TOTAL PART COST
3067459 NS 2.000 $38.557 12/12/2023 $77.114
PART NAME: Gasket, Cover, Valve, Cummins, Generator REPAIR: Maintenance / Engine / Gasket ValveCov / Replace
WORK ORDER TOTALS
TOTAL PARTS:$77.114 PARTS TAX:$0.000 MANUAL ADJUSTMENTS:$0.000
TOTAL SUBLET:$0.000 SUBLET TAX:$0.000
TOTAL LABOR:$0.000 TOTAL MISC:$0.000 TOTAL COST:$77.114
Salt Lake City Fleet Management
W300d - WorkOrderDetailsByDate
4/25/2024 6:07:24 AM
p.8WORK ORDER DETAILS REPORT
REPORT PARAMETERS:
Time Zone:Mountain Standard Time
Start Date:04/01/2023
End Date:03/31/2024
Organization:All Values
Department:All Values
Asset Number:gencc
Maint Shop:All Values
Labor Hours:Actual Hours
Page Breaks:Yes
Display Unit Cost
or True Cost or
Issue Price:
Issue Price
REPORT VERSIONS:
Report Version:20211207.2000
Script Version:20211207.1600
Salt Lake City Fleet Management
W300d - WorkOrderDetailsByDate
4/25/2024 6:09:14 AM
p.1WORK ORDER DETAILS REPORT
WORK ORDER: 775740282
ASSET NUMBER: GenLB
Work Order Status: C - Closed Date In: 06/01/2023
Work Order Shop: XSP - Mobile Service Date Out:08/09/2023
ASSET NUMBER INFORMATION
YEAR: 2001 ORG: Salt Lake City Corp TIRE SIZE:
MAKE: Cummins DEPT: Public Services Facilities ENGINE SIZE: No Engine Provided
MODEL: Generator BILL CODE: Bill everything but (Ins, Miles,
Base, Replacement)
TRANS:
LICENSE: N/A SITE: Facilities Management FUEL TYPE: B, W, D
OPERATOR: Mike Adkins VIN/SERIAL NUMBER: XX ASSET AVAIL CODE: 7am to 4pm M-F
CLASS: Non Self Propelled Generator Stations METERS: Hour Meter - 364
TECHNICIAN REPAIRS PERFORMED
TECH END DATE REPAIR DESCRIPTION HOURS LABOR COST
BODILY 08/09/2023 Maintenance / Preventative Maintenance / PM F
Service / Perform
0.08 $11.031
BODILY 08/09/2023 Maintenance / Preventative Maintenance / PM B
Service / Perform
1.65 $199.574
BODILY 08/09/2023 Maintenance / Preventative Maintenance / PM I
Service / Perform
0.00 $0.151
BODILY 08/09/2023 Maintenance / Cooling System / System /
Diagnosis
4.90 $665.834
PARTS ISSUED
PART NUMBER S/NS ISS QTY PART PRICE ISSUE DATE TOTAL PART COST
307-2859 NS 1.000 $454.212 06/12/2023 $454.212
PART NAME: Relay/Breaker,Heater,Block,Cummins/ONAN REPAIR: Maintenance / Cooling System / System / Diagnosis
FS1000 S 2.000 $11.675 06/12/2023 $23.350
PART NAME: Filter,Separator,Fuel,Intern,Cummins,ISM REPAIR: Maintenance / Preventative Maintenance / PM B Service /
Perform
WF2122 S 1.000 $33.763 06/12/2023 $33.763
PART NAME: Filter,Water/Coolant,Cummins,06,ISM,500 REPAIR: Maintenance / Preventative Maintenance / PM B Service /
Perform
25042054 S 1.000 $106.435 06/12/2023 $106.435
PART NAME: Filter,Air,Element,Mack REPAIR: Maintenance / Preventative Maintenance / PM B Service /
Perform
1970XE NS 2.000 $34.320 06/12/2023 $68.640
PART NAME: Filter,Oil,Detroit,92,8V REPAIR: Maintenance / Preventative Maintenance / PM B Service /
Perform
VABO215.0 S 32.000 $4.533 08/09/2023 $145.056
PART NAME: Oil,15W40,Valvoline,PB,1,SOL,GEN2,Bulk,REPAIR: Maintenance / Preventative Maintenance / PM B Service /
Perform
MISCELLANEOUS COSTS
CODE DESCRIPTION POSTED DATE MISC COST
Shop Charge Shop Charge 06/01/2023 $25.000
Salt Lake City Fleet Management
W300d - WorkOrderDetailsByDate
4/25/2024 6:09:14 AM
p.2WORK ORDER DETAILS REPORT
WORK ORDER TOTALS
TOTAL PARTS:$831.456 PARTS TAX:$0.000 MANUAL ADJUSTMENTS:$0.000
TOTAL SUBLET:$0.000 SUBLET TAX:$0.000
TOTAL LABOR:$876.590 TOTAL MISC:$25.000 TOTAL COST:$1,733.046
NOTES
PMB - ; PMI - ; GETTING ALARM FOR LOW ENGINE TEMP...HAS BEEN ONGOING ISSUE - FOR SEVERAL WEEKS THIS ALARM HAS BEEN GOING
OFF...THEY CALL A FEW TIMES A WEEK TO REPORT SEAN ODELL 801-347-7472 ; Engine warning - Traveled to the library and checked the unit
for issues. Found that the block heater is not operating normally. Noted that the block heater was recently replaced. Went to the breaker room
and found that the breaker for the heater circuit was tripped. Reset breaker and found that the block heater is still not functioning normally.
Found that the 210V relay that is on the unit for the block heater is currently stuck in the open position with some minor scorch marks on the
contacts. Traveled to Fleet and ordered the block heater relay, with a block heater just in case both are needed. Will attempt to replace the relay
first then the block heater as needed after that. ; PR- Block Heater - Received & at the parts counter. ; PR- Block Heater Relay - Received & at
the parts counter. ; PO- Oil Filter ETA 6/12/23 - Ordered from Napa. ; PR- Oil Filters - Received & at the parts counter. ; Block heater - Traveled
to location and installed the previously ordered relay for the block heater. After powering the system up, found that the block heater is working
as designed and is now operational. Reset the screen warnings and confirmed that the unit is working normally. Completed. ; PMB - Traveled to
location and completed replacement of the engine coolant filter, engine air filter, the two engine oil filters, and the two engine fuel filters.
Completed. ; PMF - Completed engine oil change with the replacement of all the filters. ; PMI - Completed inspection of the unit for service
needs. Inspected the engine assembly, the engine cooling system, the drive belt, and the overall condition of the engine. Ran the generator for
30 minutes after service was complete and found no issues. Completed. ; Reviewed & Closed -
Salt Lake City Fleet Management
W300d - WorkOrderDetailsByDate
4/25/2024 6:09:14 AM
p.3WORK ORDER DETAILS REPORT
WORK ORDER: 775745937
ASSET NUMBER: GenLB
Work Order Status: C - Closed Date In: 11/30/2023
Work Order Shop: XSP - Mobile Service Date Out:03/20/2024
ASSET NUMBER INFORMATION
YEAR: 2001 ORG: Salt Lake City Corp TIRE SIZE:
MAKE: Cummins DEPT: Public Services Facilities ENGINE SIZE: No Engine Provided
MODEL: Generator BILL CODE: Bill everything but (Ins, Miles,
Base, Replacement)
TRANS:
LICENSE: N/A SITE: Facilities Management FUEL TYPE: B, W, D
OPERATOR: Mike Adkins VIN/SERIAL NUMBER: XX ASSET AVAIL CODE: 7am to 4pm M-F
CLASS: Non Self Propelled Generator Stations METERS: Hour Meter - 364
TECHNICIAN REPAIRS PERFORMED
TECH END DATE REPAIR DESCRIPTION HOURS LABOR COST
BODILY 12/15/2023 Maintenance / Preventative Maintenance / PM I
Service / Perform
2.91 $395.873
BODILY 03/20/2024 Repaired From PM Service / Exhaust System /
Manifold Exhaus / Replace
0.02 $2.607
MISCELLANEOUS COSTS
CODE DESCRIPTION POSTED DATE MISC COST
Shop Charge Shop Charge 11/30/2023 $25.000
WORK ORDER TOTALS
TOTAL PARTS:$0.000 PARTS TAX:$0.000 MANUAL ADJUSTMENTS:$0.000
TOTAL SUBLET:$0.000 SUBLET TAX:$0.000
TOTAL LABOR:$398.480 TOTAL MISC:$25.000 TOTAL COST:$423.480
NOTES
PMI - ; PMI - Traveled to location, found that the block heater was not functioning. Found that the circuit breaker for the unit was tripped. Reset
the breaker and spoke to facilities. Told them that the new unit should not be the issue and to have the electricians come check the circuit. After
finding that, the engine would not start due to a low coolant condition. Returned later and found that the electricians were installed new wiring
for the heater circuit and that there was a new breaker that is a 30 amp breaker being installed. After confirming that the engine was OK to run,
ran and inspected for service needs. See lines for repairs PMI Completed. ; Exhaust leak - Found that there are two exhaust leaks on the unit.
One from the turbo to manifold flange and the other from the split in the exhaust manifold at the rear of the engine. P/A from parts then repair
will be decided on by Dru. ; Repair another time - After speaking with Dru, the exhaust repair will completed when the issue gets worse.
Currently not a concern due to the unit being outside and well vented. ; reviewed and closed -
Salt Lake City Fleet Management
W300d - WorkOrderDetailsByDate
4/25/2024 6:09:14 AM
p.4WORK ORDER DETAILS REPORT
REPORT PARAMETERS:
Time Zone:Mountain Standard Time
Start Date:04/01/2023
End Date:03/31/2024
Organization:All Values
Department:All Values
Asset Number:genlb
Maint Shop:All Values
Labor Hours:Actual Hours
Page Breaks:Yes
Display Unit Cost
or True Cost or
Issue Price:
Issue Price
REPORT VERSIONS:
Report Version:20211207.2000
Script Version:20211207.1600
Task ID Activity Status Estimated Start Date Actual Start Date Actual Stop Date Priority Total Cost Other Cost
836367 PM Boiler Weekly Completed 3/8/2024 0:00 3/18/2024 0:00 4/17/2024 0:00 Medium 69.34 0
813830 Inspection Boiler Annual Completed 2/1/2024 0:00 3/11/2024 0:00 3/28/2024 0:00 Low 83.21 0
821122 PM Boiler Service Quarterly Completed 2/14/2024 0:00 3/11/2024 0:00 3/11/2024 0:00 Low 48.72 0
815514 PM Boiler Weekly Completed 2/2/2024 0:00 2/8/2024 0:00 3/1/2024 0:00 Medium 86.73 0
808796 PM Boiler Weekly Completed 1/23/2024 0:00 1/24/2024 0:00 1/26/2024 0:00 Medium 117.58 0
792039 PM Boiler Weekly Completed 12/20/2023 0:00 12/18/2023 0:00 1/16/2024 0:00 Medium 1707.4 1647.92
785464 PM Boiler Weekly Completed 11/28/2023 0:00 12/12/2023 0:00 12/13/2023 0:00 Medium 30.43 0
780786 PM Boiler Weekly Completed 11/14/2023 0:00 11/6/2023 0:00 11/21/2023 0:00 Medium 3347.69 3310
781995 PM Boiler Weekly Completed 11/17/2023 0:00 11/16/2023 0:00 11/21/2023 0:00 Medium 68.12 0
780785 PM Boiler Service Quarterly Completed 11/14/2023 0:00 11/14/2023 0:00 11/14/2023 0:00 Low 68.12 0
758619 PM Boiler Weekly Completed 10/17/2023 0:00 11/7/2023 0:00 11/7/2023 0:00 Medium 37.69 0
755698 PM Boiler Weekly Completed 10/9/2023 0:00 10/9/2023 0:00 10/10/2023 0:00 Medium 30.43 0
745075 PM Boiler Start-up Annual Completed 9/20/2023 0:00 9/18/2023 0:00 10/2/2023 0:00 Low 475.07 0
743501 PM Boiler Weekly Completed 9/14/2023 0:00 9/29/2023 0:00 10/2/2023 0:00 Medium 90.82 0
740672 PM Boiler Weekly Completed 9/5/2023 0:00 9/5/2023 0:00 9/7/2023 0:00 Medium 891.92 366
737373 PM Boiler Weekly Completed 8/25/2023 0:00 8/28/2023 0:00 8/29/2023 0:00 Medium 29.82 0
735070 PM Boiler Weekly Completed 8/18/2023 0:00 8/18/2023 0:00 8/18/2023 0:00 Medium 29.82 0
720056 PM Boiler Service Quarterly Completed 7/3/2023 0:00 8/14/2023 0:00 8/14/2023 0:00 Low 406.54 0
731163 PM Boiler Weekly Completed 8/7/2023 0:00 8/10/2023 0:00 8/11/2023 0:00 Medium 11.13 0
732905 Repair Completed 8/11/2023 0:00 8/11/2023 0:00 8/11/2023 0:00 Important 643.83 0
727023 PM Boiler Weekly Completed 7/25/2023 0:00 7/28/2023 0:00 7/31/2023 0:00 Medium 11.13 0
719667 Inspection Prepare Boiler Annual Completed 7/1/2023 0:00 7/20/2023 0:00 7/20/2023 0:00 Low 11.13 0
719205 PM Boiler Weekly Completed 6/30/2023 0:00 7/18/2023 0:00 7/18/2023 0:00 Medium 3.56 0
711108 Inspection Prepare Boiler Annual Completed 6/2/2023 0:00 6/28/2023 0:00 Low 89.02 0
714878 PM Boiler Weekly Completed 6/16/2023 0:00 6/22/2023 0:00 6/23/2023 0:00 Medium 11.13 0
712430 PM Boiler Weekly Completed 6/9/2023 0:00 6/9/2023 0:00 6/9/2023 0:00 Medium 11.13 0
709417 PM Boiler Weekly Completed 5/30/2023 0:00 6/2/2023 0:00 6/2/2023 0:00 Medium 44.51 0
678291 PM Boiler Weekly Completed 4/5/2023 0:00 5/23/2023 0:00 5/23/2023 0:00 Medium 29.38 0
652846 Inspection Boiler Annual Completed 2/1/2023 0:00 5/2/2023 0:00 5/3/2023 0:00 Low 161.46 150
677720 PM Boiler Service Quarterly Completed 4/3/2023 0:00 4/3/2023 0:00 4/3/2023 0:00 Low 89.02 0
Task ID Activity Status Estimated Start Date Actual Start Date Actual Stop Date Priority Total Cost Other Cost
836368 PM Boiler Weekly Completed 3/8/2024 0:00 4/16/2024 0:00 4/17/2024 0:00 Medium 47.66 0
813831 Inspection Boiler Annual Completed 2/1/2024 0:00 3/11/2024 0:00 3/28/2024 0:00 Low 82.24 0
837111 PM Boiler Service Quarterly Completed 3/11/2024 0:00 3/11/2024 0:00 3/11/2024 0:00 Low 97.44 0
815515 PM Boiler Weekly Completed 2/2/2024 0:00 2/8/2024 0:00 3/1/2024 0:00 Medium 2222.95 2114.5
808797 PM Boiler Weekly Completed 1/23/2024 0:00 1/24/2024 0:00 1/26/2024 0:00 Medium 115.8 0
792040 PM Boiler Weekly Completed 12/20/2023 0:00 1/16/2024 0:00 1/16/2024 0:00 Medium 58.58 0
785465 PM Boiler Weekly Completed 11/28/2023 0:00 12/12/2023 0:00 12/13/2023 0:00 Medium 30.43 0
743500 PM Boiler Service Quarterly Completed 9/14/2023 0:00 12/11/2023 0:00 12/11/2023 0:00 Low 90.82 0
780787 PM Boiler Weekly Completed 11/14/2023 0:00 11/20/2023 0:00 11/21/2023 0:00 Medium 38.15 0
758620 PM Boiler Weekly Completed 10/17/2023 0:00 11/7/2023 0:00 11/7/2023 0:00 Medium 37.69 0
755699 PM Boiler Weekly Completed 10/9/2023 0:00 10/9/2023 0:00 10/10/2023 0:00 Medium 29.97 0
745076 PM Boiler Start-up Annual Completed 9/20/2023 0:00 9/20/2023 0:00 10/2/2023 0:00 Low 382.99 0
743502 PM Boiler Weekly Completed 9/14/2023 0:00 9/28/2023 0:00 10/2/2023 0:00 Medium 68.12 0
740673 PM Boiler Weekly Completed 9/5/2023 0:00 9/6/2023 0:00 9/7/2023 0:00 Medium 7.57 0
737374 PM Boiler Weekly Completed 8/25/2023 0:00 8/28/2023 0:00 8/29/2023 0:00 Medium 29.82 0
735071 PM Boiler Weekly Completed 8/18/2023 0:00 8/18/2023 0:00 8/18/2023 0:00 Medium 29.38 0
731164 PM Boiler Weekly Completed 8/7/2023 0:00 8/10/2023 0:00 8/11/2023 0:00 Medium 11.13 0
727024 PM Boiler Weekly Completed 7/25/2023 0:00 7/28/2023 0:00 7/31/2023 0:00 Medium 11.13 0
719668 Inspection Prepare Boiler Annual Completed 7/1/2023 0:00 7/20/2023 0:00 7/20/2023 0:00 Low 11.13 0
719206 PM Boiler Weekly Completed 6/30/2023 0:00 7/18/2023 0:00 7/18/2023 0:00 Medium 4.01 0
711110 Inspection Prepare Boiler Annual Completed 6/2/2023 0:00 6/28/2023 0:00 Low 89.02 0
714879 PM Boiler Weekly Completed 6/16/2023 0:00 6/22/2023 0:00 6/23/2023 0:00 Medium 11.13 0
700956 PM Boiler Service Quarterly Completed 4/30/2023 0:00 6/13/2023 0:00 6/14/2023 0:00 Low 66.76 0
712431 PM Boiler Weekly Completed 6/9/2023 0:00 6/9/2023 0:00 6/9/2023 0:00 Medium 11.13 0
709418 PM Boiler Weekly Completed 5/30/2023 0:00 6/2/2023 0:00 6/2/2023 0:00 Medium 44.51 0
678292 PM Boiler Weekly Completed 4/5/2023 0:00 4/18/2023 0:00 5/23/2023 0:00 Medium 518.07 488.25
652847 Inspection Boiler Annual Completed 2/1/2023 0:00 5/2/2023 0:00 5/3/2023 0:00 Low 161.46 150
Task ID Activity Status Estimated Start Date Actual Start Date Actual Stop Date Priority Total Cost Other Cost
840313 PM Boiler Weekly Completed 3/14/2024 0:00 4/17/2024 0:00 4/19/2024 0:00 Low 43.35 0
854233 PM Boiler Burner Quarterly Completed 4/5/2024 0:00 4/5/2024 0:00 4/5/2024 0:00 Low 182.7 0
813832 Inspection Boiler Annual Completed 2/1/2024 0:00 3/11/2024 0:00 3/28/2024 0:00 Low 82.72 0
826738 PM Boiler Weekly Completed 2/23/2024 0:00 2/23/2024 0:00 3/7/2024 0:00 Low 2019.78 1846.37
815516 PM Boiler Weekly Completed 2/2/2024 0:00 2/8/2024 0:00 2/16/2024 0:00 Low 97.49 0
808798 PM Boiler Weekly Completed 1/23/2024 0:00 1/24/2024 0:00 1/26/2024 0:00 Low 117.58 0
792041 PM Boiler Weekly Completed 12/20/2023 0:00 1/16/2024 0:00 1/16/2024 0:00 Low 59.48 0
795455 PM Boiler Burner Quarterly Completed 1/2/2024 0:00 1/4/2024 0:00 1/5/2024 0:00 Low 45.41 0
785466 PM Boiler Weekly Completed 11/28/2023 0:00 12/12/2023 0:00 12/13/2023 0:00 Low 29.97 0
780788 PM Boiler Weekly Completed 11/14/2023 0:00 11/20/2023 0:00 11/21/2023 0:00 Low 37.69 0
758621 PM Boiler Weekly Completed 10/17/2023 0:00 11/7/2023 0:00 11/7/2023 0:00 Low 38.15 0
755700 PM Boiler Weekly Completed 10/9/2023 0:00 10/9/2023 0:00 10/10/2023 0:00 Low 30.43 0
745077 PM Boiler Start-up Annual Completed 9/20/2023 0:00 9/19/2023 0:00 10/2/2023 0:00 Low 283.4 0
743503 PM Boiler Weekly Completed 9/14/2023 0:00 9/28/2023 0:00 10/2/2023 0:00 Low 68.12 0
743196 PM Boiler Burner Quarterly Completed 9/13/2023 0:00 10/2/2023 0:00 10/2/2023 0:00 Low 11.35 0
740674 PM Boiler Weekly Completed 9/5/2023 0:00 9/6/2023 0:00 9/7/2023 0:00 Low 7.57 0
737375 PM Boiler Weekly Completed 8/25/2023 0:00 8/28/2023 0:00 8/29/2023 0:00 Low 29.38 0
735072 PM Boiler Weekly Completed 8/18/2023 0:00 8/18/2023 0:00 8/18/2023 0:00 Low 29.82 0
731165 PM Boiler Weekly Completed 8/7/2023 0:00 8/10/2023 0:00 8/11/2023 0:00 Low 11.13 0
727025 PM Boiler Weekly Completed 7/25/2023 0:00 7/28/2023 0:00 7/31/2023 0:00 Low 11.13 0
719669 Inspection Prepare Boiler Annual Completed 7/1/2023 0:00 7/20/2023 0:00 7/20/2023 0:00 Low 11.13 0
719207 PM Boiler Weekly Completed 6/30/2023 0:00 7/18/2023 0:00 7/18/2023 0:00 Low 3.56 0
711111 Inspection Prepare Boiler Annual Completed 6/2/2023 0:00 6/28/2023 0:00 Low 89.02 0
714880 PM Boiler Weekly Completed 6/16/2023 0:00 6/22/2023 0:00 6/23/2023 0:00 Low 11.13 0
705544 PM Boiler Burner Quarterly Completed 5/16/2023 0:00 6/12/2023 0:00 6/13/2023 0:00 Low 178.04 0
712432 PM Boiler Weekly Completed 6/9/2023 0:00 6/9/2023 0:00 6/9/2023 0:00 Low 11.13 0
709419 PM Boiler Weekly Completed 5/30/2023 0:00 6/2/2023 0:00 6/2/2023 0:00 Low 44.51 0
678293 PM Boiler Weekly Completed 4/5/2023 0:00 5/23/2023 0:00 5/23/2023 0:00 Low 29.82 0
652848 Inspection Boiler Annual Completed 2/1/2023 0:00 5/2/2023 0:00 5/3/2023 0:00 Low 161.46 150