HomeMy WebLinkAboutDAQ-2024-005169
195 North 1950 West • Salt Lake City, UT
Mailing Address: P.O. Box 144820 • Salt Lake City, UT 84114-4820
Telephone (801) 536-4000 • Fax (801) 536-4099 • T.D.D. (801) 903-3978
www.deq.utah.gov
Printed on 100% recycled paper
State of Utah
Department of
Environmental Quality
Kimberly D. Shelley
Executive Director
DIVISION OF AIR QUALITY
Bryce C. Bird
Director
SPENCER J. COX
Governor
DEIDRE HENDERSON
Lieutenant Governor
DAQC-168-24
Site 12727 (B1)
Quin Bingham
Granite Construction Company
1000 North Warm Springs Road
Salt Lake City, Utah 84116-2321
Dear Mr. Bingham:
Re: Granite Construction Company – Temporary Relocation/Operation, Notice of Intent –
Tooele County
Your Notice of Intent dated February 23, 2024, to relocate portable aggregate equipment to the
temporary project to Granite Construction Company’s Coyote Pit, located at Highway 36 and
Center Street, Stansbury Park, Utah, was received by the Utah Division of Air Quality (DAQ) and
has been reviewed.
The following equipment has been approved for operation for this temporary project:
Nordtrack J127 jaw crusher
Nordtrack S4.9 screen
Lokotrack LT300HP cone crusher
Nordtrack CW85 conveyor
The above equipment has been leased from Wheeler Machinery Company and has been permitted
for portable operations in the State of Utah by the Approval Order (AO) DAQE-AN142390014-
18. Approval is granted to relocate and operate this equipment at the new location for a period not
to exceed 180 operational days. As per Utah Administrative Code (UAC) R307-401-17, the
operation of equipment at this temporary site may be for up to 180 working days in any calendar
year not to exceed 365 consecutive days, starting from the initial relocation date. The operational
days per site cannot be extended beyond the stipulated 365 consecutive day period. Aggregate
operations extending beyond this period should be approved by a permanent AO for this location.
Approval is subject to the conditions of the dust control plan submitted for this location and the
current Granite Construction Company portable AO DAQE-AN127270014-19 dated February 27,
2019. Hours of operation shall be held to 16 hours per each 24-hour day. The maximum
production rate shall be held to the requested 500 tons per hour.
" / 2 / 6 Û á Û Ù Û Ý
DAQC-168-24
Page 2
Emissions for this project have been estimated at the following:
Pollutant gram/sec lbs/hr lbs/24 hr tons/yr
PM10 1.97 15.67 156.71 12.22
SOx 0.78 6.16 61.56 4.80
NOx 5.15 40.91 409.11 31.91
CO 1.36 10.75 107.54 8.39
VOC 0.21 1.68 16.83 1.31
The owner/operator shall maintain records of the actual operation hours, days, and production
rate, of the above referenced equipment at this relocation site and have the ability to submit the
information to the DAQ upon the request of representatives of the director. Please make certain
that the plant operator is aware of all the location specific requirements for this site and the
conditions of the aforementioned AO.
Federal New Source Performance Standards Subpart OOO requires that initial Method 9
observations be performed for all applicable portable crushers, screens, and attached conveyors.
Subpart OOO also mandates that all crushers constructed, modified, or reconstructed on or after
April 22, 2008, which are not enclosed, must install spray bars on the equipment and keep
maintenance records to ensure proper spray bar operations.
Utah Division of Water Quality Storm Water Permits and regulations may apply to this temporary
project. Please refer to Utah DEQ Water Quality’s current Storm Water Construction
requirements for additional information.
This approval for relocation in no way releases the owner or operator from any liability for
compliance with all other applicable federal, state, and local regulations including the UAC.
If you have any questions regarding this relocation authorization or the temporary relocation
process please contact Susan Weisenberg at (385) 306-6512.
Sincerely,
Jay P. Morris
Assistant Director
JPM:SW:rh
Enclosure: Submitted Temporary Relocation Form
Email correspondence
cc: Tooele County Health Department
4 * - - $ . — A F v A ? A C ? H w ? @ ˜
2/26/24, 10:54 AM State of Utah Mail - Portable/Temporary Relocation Form
https://mail.google.com/mail/u/0/?ik=bffac613d3&view=pt&search=all&permthid=thread-f:1791698250368333739%7Cmsg-f:1791698250368333739&…1/2
Susan Weisenberg <sweisenberg@utah.gov>
Portable/Temporary Relocation Form
1 message
noreply@qemailserver.com <noreply@qemailserver.com>Fri, Feb 23, 2024 at 6:56 AM
Reply-To: trigger@qemailserver.com
To: sweisenberg@utah.gov
Susan/Chad:
Site # -- Granite Construction Company has requested a Temporary Relocation. Please see the information below. Any
attachments can be access by clicking on the links.
Recipient Data:
Time Finished: 2024-02-23 06:56:21 MST
IP: 161.69.91.33
ResponseID: R_6cU4CXMgGzPqzpt
Link to View Results: Click Here
URL to View Results: https://utahgov.iad1.qualtrics.com/apps/single-response-reports/reports/
o3sDacmh4dwsKQJr6mOXGOqrIEwLZN86gzHKBGzHcCuW1YVq8SIP9V-2W63RI8u08HUhqaDRVOiNdyDnyXMaj
B74DNa2Eeck26v-SY0pHnRdnEShpNBqQsQvF14pIQKniUlIHLNWcxGJHrCgjb2lO-ZE6-
BRGijVrkctPuVgFXvHmPLcDEVTDAG6xtsr9cHE62YuqEltukiUZfau3wmyYTXWBJnooTTgn-0-
DxzIyJlPH9G3tYAqPNPaznFeOeyHmUdavzhuC1KeDXE3dqU-oi8DDtA2p9vRCoKnGRCFLJCTetuqr0
JpRNR33CMIYLcPG9PqN0pqRmreR2yc0aNYuA
Response Summary:
Please fill out the information below:
Contact Person: Quin Bingham
Company Name: Granite Construction Company
Mailing Address: 1000 N Warm Springs Road
City: Salt Lake City
Zip: 84116
Phone Number: 4357704319
Email: quin.bingham@gcinc.com
Is the site located within a PM2.5 non-attainment and maintenance plan areas on cleared land grea...
Yes
All temporary relocation projects are required to submit a Fugitive Dust Control Plan (FDCP). Lo...
See attached copy of FDCP
Briefly give directions to the site and/or physical address:
HWY 36 and Center Street in Stansbury Park, Utah
Proposed Relocation Information:
Closest City Stansbury Park
County Tooele
UTM X Coordinates 40.650959
UTM Y Coordinates -112.283220
Approximate distance to the nearest house/business 2000 feet
UTM X Coordinates to nearest house/business 40.652180
UTM Y Coordinates to nearest house/business -112.290010
Does this site currently have a permit with DAQ?
2/26/24, 10:54 AM State of Utah Mail - Portable/Temporary Relocation Form
https://mail.google.com/mail/u/0/?ik=bffac613d3&view=pt&search=all&permthid=thread-f:1791698250368333739%7Cmsg-f:1791698250368333739&…2/2
No
Please provide the permit ID for the equipment? (DAQE-XXXXXXXXX-XX)
DAQE-AN127270014-19
Please list all the Equipment on Site:Note: It is important to identify ALL diesel powered engine...
1
Equipment Type JAW
Make/Model Nordtrack J127
Design Capacity 500 TPH
2
Equipment Type Screen
Make/Model Nordtrack S4.9
Design Capacity 500 TPH
3
Equipment Type Cone
Make/Model Lokotrack LT300HP
Design Capacity 500 TPH
4
Equipment Type Conveyor
Make/Model Nordtrack CW85
Please attach a site diagram showing the equipment layout and general site dimensions for this re...
https://utahgov.co1.qualtrics.com/WRQualtricsControlPanel/File.php?F=F_27UnpvULLiaM44M
Have any other state or local regulatory agencies issued any other "Conditional Use Permits" for...
No
Operational Information: (Please note: Operating time over 16 hours in a 24 hour period will re...
Total Hours of operation per 24 hr period 16
Starting time of operation (am/pm) 0600
Ending time of operation (am/pm) 2200
Maximum hourly production rate for project 500 TPH
Expected startup date 03/01/2024
Expected completion date 03/01/2025
What type of application is this for?
New Application
In accordance with the fee schedule approved by the Utah State Legislature, the Division of Air Q...
https://utahgov.co1.qualtrics.com/WRQualtricsControlPanel/File.php?F=F_26hc73wS6I2vZ0j
Owner/Operator Representative:
https://utahgov.co1.qualtrics.com/WRQualtricsControlPanel/File.php?F=F_3lJljgugoGQWBPG
2/26/24, 10:59 AM State of Utah Mail - RE: Request for Expedited Processing of Temporary Relocate Permit
https://mail.google.com/mail/u/0/?ik=bffac613d3&view=pt&search=all&permthid=thread-f:1791698754806749527%7Cmsg-f:1791717331398699941&…1/2
Susan Weisenberg <sweisenberg@utah.gov>
RE: Request for Expedited Processing of Temporary Relocate Permit
1 message
Bingham, Quin <Quin.Bingham@gcinc.com>Fri, Feb 23, 2024 at 11:59 AM
To: Susan Weisenberg <sweisenberg@utah.gov>
Susan,
We are renting the equipment from Wheeler, so please reference their portable equipment AO # DAQE-AN142390014-18.
Thanks again for all your help!
-Quin
From: Susan Weisenberg <sweisenberg@utah.gov>
Sent: Friday, February 23, 2024 10:46 AM
To: Bingham, Quin <Quin.Bingham@gcinc.com>
Subject: Re: Request for Expedited Processing of Temporary Relocate Permit
CAUTION: External Email: Be Cyber-Alert
I spoke with Chad regarding this TRP and he has no concerns other than that this is a site that has historically generated
dust complaints from the surrounding residents. He states that it would be good to make certain to stay on top of all dust
control measures. Thanks
Susan Weisenberg,
Environmental Scientist
Office: 385-306-6512
On Fri, Feb 23, 2024 at 7:04 AM Bingham, Quin <Quin.Bingham@gcinc.com> wrote:
2/26/24, 10:59 AM State of Utah Mail - RE: Request for Expedited Processing of Temporary Relocate Permit
https://mail.google.com/mail/u/0/?ik=bffac613d3&view=pt&search=all&permthid=thread-f:1791698754806749527%7Cmsg-f:1791717331398699941&…2/2
Dear Susan,
Good morning. I trust this message finds you well. I am reaching out to you regarding my recent application for a
temporary relocate permit for a mobile crushing/screening plant at our Coyote aggregate facility in Stansbury Park,
Utah.
I have noticed that you have handled the last few temporary relocate permits I applied for, and I am grateful for your
assistance. Given the urgency of our situation, with plans to commence crushing late next week, I am reaching out to
inquire if there is any possibility of expediting the processing of this application.
I understand the importance of proper planning and don't wish to impose any unnecessary burden on your end. If
expediting the process is feasible, it would greatly assist us in meeting our timeline.
Thank you for your ongoing support, and I appreciate your consideration of this matter.
Best regards,
Quin
Quinten G. Bingham
Regional Environmental Manager
1000 N Warm Springs Rd
Salt Lake City,UT 84116
Direct: 801-526-6050
Mobile: 435-770-4319
Email: Quin.Bingham@gcinc.com
2/26/24, 10:56 AM State of Utah Mail - RE: Request for Expedited Processing of Temporary Relocate Permit
https://mail.google.com/mail/u/0/?ik=bffac613d3&view=pt&search=all&permthid=thread-f:1791698754806749527%7Cmsg-f:1791713012217398631&…1/2
Susan Weisenberg <sweisenberg@utah.gov>
RE: Request for Expedited Processing of Temporary Relocate Permit
1 message
Bingham, Quin <Quin.Bingham@gcinc.com>Fri, Feb 23, 2024 at 10:50 AM
To: Susan Weisenberg <sweisenberg@utah.gov>
Susan,
Thanks for following up with Chad. And I agree that we have had issues with dust in the past here due to a subcontractor
operating without water. Super frustrating.
Anyway, I will personally make sure our guys are using their dust suppression equipment on the processing equipment.
Thanks,
From: Susan Weisenberg <sweisenberg@utah.gov>
Sent: Friday, February 23, 2024 10:46 AM
To: Bingham, Quin <Quin.Bingham@gcinc.com>
Subject: Re: Request for Expedited Processing of Temporary Relocate Permit
CAUTION: External Email: Be Cyber-Alert
I spoke with Chad regarding this TRP and he has no concerns other than that this is a site that has historically generated
dust complaints from the surrounding residents. He states that it would be good to make certain to stay on top of all dust
control measures. Thanks
Susan Weisenberg,
Environmental Scientist
Office: 385-306-6512
2/26/24, 10:56 AM State of Utah Mail - RE: Request for Expedited Processing of Temporary Relocate Permit
https://mail.google.com/mail/u/0/?ik=bffac613d3&view=pt&search=all&permthid=thread-f:1791698754806749527%7Cmsg-f:1791713012217398631&…2/2
On Fri, Feb 23, 2024 at 7:04 AM Bingham, Quin <Quin.Bingham@gcinc.com> wrote:
Dear Susan,
Good morning. I trust this message finds you well. I am reaching out to you regarding my recent application for a
temporary relocate permit for a mobile crushing/screening plant at our Coyote aggregate facility in Stansbury Park,
Utah.
I have noticed that you have handled the last few temporary relocate permits I applied for, and I am grateful for your
assistance. Given the urgency of our situation, with plans to commence crushing late next week, I am reaching out to
inquire if there is any possibility of expediting the processing of this application.
I understand the importance of proper planning and don't wish to impose any unnecessary burden on your end. If
expediting the process is feasible, it would greatly assist us in meeting our timeline.
Thank you for your ongoing support, and I appreciate your consideration of this matter.
Best regards,
Quin
Quinten G. Bingham
Regional Environmental Manager
1000 N Warm Springs Rd
Salt Lake City,UT 84116
Direct: 801-526-6050
Mobile: 435-770-4319
Email: Quin.Bingham@gcinc.com
Develop Fugitive Dust Plan
Introduction
Applicant Information
Project Information
Latitude/Longitude Veri cation
Point of Contact
Dust Suppressants
Best Management Practices (BMP)
Checklist
BMP - 01 Back lling area previously
excavated or trenched.
BMP - 02 Blasting soil and rock -
drilling and blasting.
BMP - 03 Clearing for site
preparation and vacant land
cleanup.
BMP - 04 Clearing forms,
foundations, slab clearing ... prior to
pouring concrete.
BMP - 05 Crushing of construction
and demolition debris, rock and
soil.
BMP - 06 Cut and ll soils for site
grade preparation.
BMP - 07 Demolition - Implosive
demolition of a structure, using
explosives.
BMP - 08 Demolition -
mechanical/manual demolition..... of
structures
BMP - 09 Disturbed soil throughout
project including between
structures.
BMP - 10 Disturbed land - long term
stabilization and erosion control ...
for more than 30 days.
BMP - 11 Hauling materials.
BMP - 12 Paving/subgrade
preparation for paving streets,
parking lots, etc.
BMP - 13 Sawing/cutting material,
concrete, asphalt, block or pipe.
Introduction
Applicant Information
Project Information
Latitude/Longitude Veri cation
Please complete the following information in order to create a Fugitive Dust Application
for your project. You will have a chance to review the plan prior to nal submission.
Applicant Type::PM Plan Certi cate Number
61EE9E0AFE
Name:Granite Construction Company - Quinten G Bingham
Mailing Address *
Mailing Address - Address Line 1:1000 N Warm Springs Road
Mailing Address - Address Line 2:
Mailing Address - City:
Salt Lake City
Mailing Address - State:
UT
Mailing Address -
Zip:
84116
Email:quin.bingham@gcinc.com Phone:(435) 770-4319
Project Name:
Coyote Agg Facility - Temp Relocate
Project End Date:02/24/2025
Project Location *
Address Line 1:HWY 36 & Center Street
Address Line 2:
City:Stansbury Park State:UT Zip:84074
Site Directions:Head east on Pole Canyon road o HWY 36
County:Tooele Acreage:10
Acreage - Rounded to the nearest 0.1 of an acre
10.0
For Manual Latitude and Longitude input:
Make sure to include at least 6 digits after the decimal and it must fall
within the state of Utah.
Example 40.404976 or 40.404976232
Latitude (Decimals Only) :40.650886 Longitude (Decimals Only) :-112.283721
Map Veri cation
Copy the following URL into your browser so you can verify on a map that the project
latitude and longitude you provided are correct.
Map Calculation b
https://www.google.com/maps/place/40.650886,-112.283721
Latitude/Longitude veri cation
The above Latitude and Longitude have been veri ed.
*
BMP - 14 Screening of rock, soil or
construction debris.
BMP - 15 Staging areas, equipment
storage, vehicle parking lots, and
material storage areas.
BMP - 16 Stockpiles materials
(storage), other soils, rock or
debris, for future use or export.
BMP - 17 Tailings piles, ponds and
erosion control.
BMP - 18 Trackout, Prevention and
cleanup of mud, silt and soil
tracked out onto paved roads.
Best Management Practice
Selections - 19 Tra c - unpaved
routes and parking, construction
related tra c ... parking areas.
BMP - 20 Trenching with track or
wheel mounted excavator, shovel,
backhoe or trencher.
BMP - 21 Truck loading with
materials including construction
and demolition debris, rock and
soil.
Reviewing Your Plan
Point of Contact
Dust Suppressants
Best Management Practices (BMP) Checklist
BMP - 05 Crushing of construction and demolition debris, rock
and soil.
Point of Contact for dust control matters and to whom a
COMPLIANCE ACTION should be sent if necessary.
Name:Quin Bingham Company:
Granite Construction Company
Address *
Address Line 1:1000 N Warm Springs Road
Address Line 2:
City:Salt Lake City State:UT Zip:84116
Phone number:(435) 770-4319 Cell number:(435) 770-4319
Do you plan on using chemical dust suppressing or stabilizing agents?
Yes
No
*
Fugitive Dust Plan Number
A7047E2C6D
Select all that apply
01. Back lling area previously excavated or trenched.
02. Blasting soil and rock - drilling and blasting.
03. Clearing for site preparation and vacant land cleanup.
04. Clearing forms, foundations, slab clearing and cleaning of forms, foundations and
slabs prior to pouring concrete.
05. Crushing of construction and demolition debris, rock and soil.
06. Cut and ll soils for site grade preparation.
07. Demolition - Implosive demolition of a structure, using explosives.
08. Demolition - mechanical/manual demolition of walls, stucco, concrete,
freestanding structures, buildings and other structures.
09. Disturbed soil throughout project including between structures. THIS ACTIVITY
MUST BE SELECTED FOR ALL PROJECTS.
10. Disturbed land - long term stabilization and erosion control of large tracts of
disturbed land that will not have continuing activity for more than 30 days.
11. Hauling materials.
12. Paving/subgrade preparation for paving streets, parking lots, etc.
13. Sawing/cutting material, concrete, asphalt, block or pipe.
14. Screening of rock, soil or construction debris.
15. Staging areas, equipment storage, vehicle parking lots, and material storage areas.
16. Stockpiles materials (storage), other soils, rock or debris, for future use or export.
17. Tailings piles, ponds and erosion control.
18. Trackout, Prevention and cleanup of mud, silt and soil tracked out onto paved
roads. (THIS ACTIVITY MUST BE SELECTED FOR ALL PROJECTS.)
19. Tra c - unpaved routes and parking, construction related tra c on unpaved
interior and/or access roads and unpaved employee/worker parking areas.
20. Trenching with track or wheel mounted excavator, shovel, backhoe or trencher.
21. Truck loading with materials including construction and demolition debris, rock
and soil.
*
Stabilize surface soils where support equipment and vehicles will operate.
05-01. Pre-water and maintain surface soils in a stabilized condition.
05-02. Apply and maintain a chemical stabilizer to surface soils.
05-03. Pave operational area(s).
*
Stabilize material before crushing.
05-04. Pre-water material.
*
Review
BMP - 09 Disturbed soil throughout project including between
structures.
BMP - 11 Hauling materials.
BMP - 14 Screening of rock, soil or construction debris.
05-05. Test material to determine moisture content and silt loading, crush only
material that is at optimum moisture content.
Stabilize material during crushing.
05-06. Apply water to stabilize material so as to maintain compliance with opacity
standards and permit conditions.
*
Monitor opacity.
05-07. Make adjustments to maintain compliance with opacity standards and permit
conditions.
05-08. Install wind break or use enclosure.
*
Stabilize material after crushing.
05-09. Water crushed material immediately following crushing.
05-10. Apply and maintain a chemical stabilizer to crushed material.
05-11. Maintain in enclosure.
05-12. Minimize height of stockpile.
*
Tra c
05-13. Minimize vehicle miles.
05-14. Reduce truck tra c.
05-15. Reduce truck speed.
*
Transfer height.
05-16. Minimize transfer and drop point height.
*
Limit disturbance of soils where possible.
09-01. Limit disturbance of soils with the use of fencing, barriers, barricades, and/or
wind barriers.
09-02. Limit vehicle mileage and reduce speed.
*
Stabilize and maintain stability of all disturbed soil throughout construction site.
09-03. Apply water to stabilize disturbed soils. Soil moisture must be maintained such
that soils can be worked without generating fugitive dust.
09-04. Apply and maintain a chemical stabilizer.
09-05. Use wind breaks.
09-06. Apply cover (natural or synthetic).
*
Limit visible dust opacity from vehicular operations.
11-01. Apply and maintain water/chemical suppressant to operational areas and haul
routes.
11-02. Limit vehicle mileage and speed.
*
Stabilize materials during transport on site.
11-03. Use tarps or other suitable enclosures on haul trucks.
11-04. Apply water prior to transport.
*
Clean wheels and undercarriage of haul trucks prior to leaving construction site.
11-05. Clean wheels.
11-06. Sweep or water haul road.
*
Stabilize surface soils where support equipment and vehicles will operate.
14-01. Pre-water and maintain surface soils in a stabilized condition.
14-02. Apply and maintain a chemical stabilizer on surface soils.
14-03. Pave operational area(s).
*
Pre-treat material prior to screening.
14-04. Apply a dust suppressant to material.
*
Stabilize material during screening.
14-05. Dedicate water source to screening operation and apply water as needed to
prevent dust.
14-06. Install wind barrier upwind of screen as high as the drop point.
*
Stabilize material and surrounding area immediately after screening.
14-07. Apply water to stabilize screened material and surrounding area.
14-08. Apply and maintain a chemical stabilizer to stabilize screened material and
surrounding area.
*
BMP - 15 Staging areas, equipment storage, vehicle parking lots,
and material storage areas.
BMP - 16 Stockpiles materials (storage), other soils, rock or
debris, for future use or export.
BMP - 18 Trackout, Prevention and cleanup of mud, silt and soil
tracked out onto paved roads.
Best Management Practice Selections - 19 Tra c - unpaved
14-09. Minimize storage pile height.
Transfer height.
14-10. Drop material through the screen slowly and minimize drop height.
*
Stabilize staging area soils during use.
15-03. Pre-water and maintain surface soils in a stabilized condition.
15-04. Apply and maintain a chemical stabilizer to surface soils.
*
Stabilize staging area soils at project completion.
15-05. Apply a chemical stabilizer.
15-06. Apply screened or washed aggregate.
15-07. Use wind breaks.
15-08. Pave.
15-09. Completed project will cover staging area with buildings, paving, and/or
landscaping.
15-10. Apply water to form adequate crust and prevent access.
*
Stabilize surface soils where support equipment and vehicles will operate.
16-01. Pre-water and maintain surface soils in a stabilized condition.
16-02. Apply and maintain a chemical stabilizer on surface soils.
16-03. Pave area.
*
Stabilize stockpile materials during handling.
16-04. Remove material from the downwind side of the stockpile, when safe to do so.
16-05. Reduce height.
16-06. Create wind screen
*
Stabilize stockpiles after handling.
16-07. Water stockpiles to form a crust immediately.
16-08. Apply and maintain a chemical stabilizer to all outer surfaces of the stockpiles.
16-09. Provide and maintain wind barriers on 3 sides of the pile.
16-10. Apply a cover (natural or synthetic)
16-11. Wind screen.
16-12. Avoid steep sides to prevent material sloughing.
16-13. Reduce height.
*
Prevent dust from trackout.
18-01. Clean trackout at the end of the work shift from paved surfaces to maintain
dust control
18-02. Maintain dust control during working hours and clean trackout from paved
surfaces at the end of the work shift/day.
18-03. Install gravel pad(s), clean, well-graded gravel or crushed rock. Minimum
dimensions must be 30 feet wide by 3 inches deep, and, at minimum, 50' or the length of
the longest haul truck, whichever is greater. Re-screen, wash or apply additional rock in
gravel pad to maintain e ectiveness.
18-04. Install wheel shakers. Clean wheel shakers on a regular basis to maintain
e ectiveness.
18-05. Install wheel washers. Maintain wheel washers on a regular basis to maintain
e ectiveness.
18-06. Motorized vehicles will only operate on paved surfaces.
18-07. Install cattle guard before paved road entrance.
*
All exiting tra c must be routed over selected trackout control device(s).
18-08. Clearly establish and enforce tra c patterns to route tra c over selected
trackout control device(s).
18-09. Limit site accessibility to routes with trackout control devices in place by
installing e ective barriers on unprotected routes.
*
routes and parking, construction related tra c ... parking areas.
BMP - 21 Truck loading with materials including construction
and demolition debris, rock and soil.
Stabilize surface soils where support equipment and vehicles will operate.
19-01. Limit vehicle mileage and speeds.
19-02. Apply and maintain water on surface soils.
19-03. Apply and maintain chemical stabilizers on surface soils.
19-04. Apply and maintain gravel on surface soils.
19-05. Supplement chemical stabilizers, water or aggregate applications as necessary.
19-06. Apply recycled asphalt (RAP) to surface soils.
*
Apply and maintain a chemical stabilizer on surface soils where loaders, support
equipment and vehicles will operate.
21-01. Pre-water and maintain surface soils in a stabilized condition where loaders,
support equipment and vehicles will operate.
21-02. Apply and maintain a chemical stabilizer on surface soils where loaders,
support equipment and vehicles will operate.
21-03. Empty loader bucket slowly and keep loader bucket close to the truck to
minimize the drop height while dumping.
*