Loading...
HomeMy WebLinkAboutDAQ-2024-008157 195 North 1950 West • Salt Lake City, UT Mailing Address: P.O. Box 144820 • Salt Lake City, UT 84114-4820 Telephone (801) 536-4000 • Fax (801) 536-4099 • T.D.D. (801) 903-3978 www.deq.utah.gov Printed on 100% recycled paper State of Utah Department of Environmental Quality Kimberly D. Shelley Executive Director DIVISION OF AIR QUALITY Bryce C. Bird Director SPENCER J. COX Governor DEIDRE HENDERSON Lieutenant Governor DAQC-482-24 Site 14070 (B1) Melissa Scott JP Excavating, Inc. 4102 South 1440 East Circle St. George, Utah 84790 Dear Ms. Scott: Re: JP Excavating, Inc. – Temporary Relocation/Operation, Notice of Intent – Washington County Your Notice of Intent dated April 25, 2024, to relocate portable aggregate equipment to the temporary project located 2670 West 600 North, Hurricane, Utah, was received by the Utah Division of Air Quality (DAQ) and has been reviewed. The following equipment has been approved for operation for this temporary project: CR-4 jaw crusher with 225 hp generator CR-8 Impact crusher with 385 hp generator CR-11 screen Approval is granted to relocate and operate this equipment at the new location for a period not to exceed 180 operational days. As per Utah Administrative Code (UAC) R307-401-17, the operation of equipment at this temporary site may be for up to 180 working days in any calendar yea r not to exceed 365 consecutive days, starting from the initial relocation date. The operational days per site cannot be extended beyond the stipulated 365 consecutive day period. Approval is subject to the conditions of the dust control plan submitted for this location and the current Approval Order (AO) DAQE-140700003-20 dated June 25, 2020. Hours of operation shall be held to 10 hours each day. The maximum production rate shall be held to the requested 150 tons per hour. Emissions for this project have been estimated at the following: Pollutant gram/sec lbs/hr lbs/24 hr tons/yr PM10 0.83 6.56 65.63 5.12 SOx 0.17 1.33 13.26 1.03 NOx 2.13 16.87 168.73 13.16 CO 0.58 4.58 45.75 3.57 VOC 0.17 1.33 13.29 1.04 6 Û Ü Û Ù Û Ý DAQC-482-24 Page 2 The owner/operator shall maintain records of the actual operation hours, days, and production rate, of the above referenced equipment at this relocation site and have the ability to submit the information to the DAQ upon the request of representatives of the director. Please make certain that the plant operator is aware of all the location specific requirements for this site and the conditions of the aforementioned AO. NSPS Subpart OOO requires that initial Method 9 observations be performed for all applicable portable crushers, screens, and attached conveyors. Subpart OOO also mandates that all crushers constructed, modified, or reconstructed on or after April 22, 2008, which are not enclosed, must install spray bars on the equipment and keep maintenance records to ensure proper spray bar operations. Utah Division of Water Quality Storm Water Permits and regulations may apply to this temporary project. Please refer to Utah DEQ Water Quality’s current Storm Water Construction requirements for additional information. This approval for relocation in no way releases the owner or operator from any liability for compliance with all other applicable federal, state, and local regulations including the UAC. If you have any questions regarding this relocation authorization or the temporary relocation process please contact Susan Weisenberg at (385) 306-6512. Sincerely, Jay P. Morris Assistant Director JPM:SW:rh Enclosure: Submitted Temporary Relocation Form cc: Southwest Utah Public Health Department 4 * - - $ . — 4 A A v A ? A C @ A w @ H ˜ Susan Weisenberg <sweisenberg@utah.gov> Portable/Temporary Relocation Form 1 message noreply@qemailserver.com <noreply@qemailserver.com>Thu, Apr 25, 2024 at 8:20 AM Reply-To: trigger@qemailserver.com To: sweisenberg@utah.gov Susan/Chad: Site # -- JP Excavating has requested a Temporary Relocation. Please see the information below. Any attachments can be access by clicking on the links. Recipient Data: Time Finished: 2024-04-25 08:20:12 MDT IP: 98.97.137.201 ResponseID: R_3MYQ1tAwPhMewwq Link to View Results: Click Here URL to View Results: https://utahgov.iad1.qualtrics.com/apps/single-response-reports/reports/E2j4hPIfo3MDPnC-- ILoe91M-Fq%2Egu077FQ9uLFAIUg1jziZcvB-1NHxYVba96uG2vSmadsQ23BsXlF9% 2EOxWOmt74kmf9VbeP9spP21PsVfRKnbeEt9LpnGbWtflbmMGdCbPOMFgRT4s-qs3dT8vpuA-TUJoM3hDKN% 2EDYxXaeY15LmBZkEAnhqQEGX%2EnKVP8q49H6Srl1Hl4xBlm83fpfMxUa4mNSxCBOkblA1tbPgFVWVVioKtv- 59GAGFu1%2E7JKxVngRsSWDBpbHbD5n-Py5092yvlE9BJkNYoODMMbGCJcVTTDvQ5- RscFnHFwPJuwVUDvjiXSnbwyas9iKgk%2Eg Response Summary: Please fill out the information below: Contact Person: Melissa Scott Company Name: JP Excavating Mailing Address: 4102 S 1440 E Circle City: St George Zip: 84790 Phone Number: 435-680-4383 Email: melissa@jpexcavating.com Is the site located within a PM2.5 non-attainment and maintenance plan areas on cleared land grea... No All temporary relocation projects are required to submit a Fugitive Dust Control Plan (FDCP). Lo... D26793BE51 Briefly give directions to the site and/or physical address: 2670 West 600 North Hurricane, UT 84737 Proposed Relocation Information: Closest City Hurricane County Washington UTM X Coordinates 292373 UTM Y Coordinates 4118032 Approximate distance to the nearest house/business 130 UTM X Coordinates to nearest house/business 292330 UTM Y Coordinates to nearest house/business 4118051 5/20/24, 11:25 AM State of Utah Mail - Portable/Temporary Relocation Form https://mail.google.com/mail/u/1/?ik=bffac613d3&view=pt&search=all&permthid=thread-f:1797316753416347633%7Cmsg-f:1797316753416347633&…1/2 Does this site currently have a permit with DAQ? No Please provide the permit ID for the equipment? (DAQE-XXXXXXXXX-XX) DAQE-AN140700003-20 Please list all the Equipment on Site:Note: It is important to identify ALL diesel powered engine... 1 Equipment Type Jaw Crusher Make/Model Unknown Serial or ID# CR-4 Manufactured Date Unknown Design Capacity Unknown 2 Equipment Type Impact Crusher Make/Model Unknown Serial or ID# CR-8 Manufactured Date Unknown Design Capacity Unknown 3 Equipment Type Screen Make/Model Unknown Serial or ID# CR-11 Manufactured Date Unknown Design Capacity Unknown Please attach a site diagram showing the equipment layout and general site dimensions for this re... https://utahgov.co1.qualtrics.com/WRQualtricsControlPanel/File.php?F=F_1Lh69ZDNNRbHTe3 Have any other state or local regulatory agencies issued any other "Conditional Use Permits" for... No Operational Information: (Please note: Operating time over 16 hours in a 24 hour period will re... Total Hours of operation per 24 hr period 12 Starting time of operation (am/pm) 6:00 AM Ending time of operation (am/pm) 6:00 PM Maximum hourly production rate for project 300 tph Expected startup date 05/01/2024 Expected completion date 09/30/2024 What type of application is this for? New Application Owner/Operator Representative: https://utahgov.co1.qualtrics.com/WRQualtricsControlPanel/File.php?F=F_22zAhOqzteI1ZDG 5/20/24, 11:25 AM State of Utah Mail - Portable/Temporary Relocation Form https://mail.google.com/mail/u/1/?ik=bffac613d3&view=pt&search=all&permthid=thread-f:1797316753416347633%7Cmsg-f:1797316753416347633&…2/2 Susan Weisenberg <sweisenberg@utah.gov> Fwd: 2670 W 600 N Temporary Relocation 1 message Melissa Scott <melissa.jpei@gmail.com>Wed, May 1, 2024 at 5:22 PM To: Susan Weisenberg <sweisenberg@utah.gov> Susan, Hi! After our conversation, I was able to better confirm the location of our crusher for this site. The GPS coordinates are: 37.186305, -113.347988. We will be 1,000 Lf away from the nearest home. Please let me know if you have any more questions or if you need anything else. Thanks, MElissa ---------- Forwarded message --------- From: Alysen Tarrant <aly@adtenviro.com> Date: Thu, Apr 25, 2024 at 8:23 AM Subject: 2670 W 600 N Temporary Relocation To: Melissa Scott <melissa.jpei@gmail.com> Hi Melissa, Here is the final application for 2670 W 600 N location. If you hadn't received the link for payment, can you please follow the link here: https://secure.utah.gov/cart/daq_cart/details.html?productId=141 Your temporary permit for the Washington location is still good until September of this year, so yes you can continue to move back and forth between locations without any issue. -- Alysen D. Tarrant, CWP Environmental Permits Specialist ADT Environmental & Mineral Consultants, LLC 26849 Road M Cortez, CO 81321 Cell: (801) 918-0799 E-mail: aly@adtenviro.com -- Melissa Scott 4102 So 1440 E Circle St. George, UT 84790 5/20/24, 11:45 AM State of Utah Mail - Fwd: 2670 W 600 N Temporary Relocation https://mail.google.com/mail/u/1/?ik=bffac613d3&view=pt&search=all&permthid=thread-f:1797894473093962719%7Cmsg-f:1797894473093962719&…1/2 (435) 680-4383 Melissa@jpexcavating.com Temporary Relocation_Portable_JPExcavating_2670W.pdf 2488K 5/20/24, 11:45 AM State of Utah Mail - Fwd: 2670 W 600 N Temporary Relocation https://mail.google.com/mail/u/1/?ik=bffac613d3&view=pt&search=all&permthid=thread-f:1797894473093962719%7Cmsg-f:1797894473093962719&…2/2 Susan Weisenberg <sweisenberg@utah.gov> Re: temporary relocation to Hurricane questions 1 message Melissa Scott <melissa.jpei@gmail.com>Thu, May 9, 2024 at 12:20 PM To: Susan Weisenberg <sweisenberg@utah.gov> Cc: Brandon Burrows <brandon@jpexcavating.com> Susan, Hi! Please use this email as authorization to use the sizes of our equipment that we submitted to Jordan for our Washington relocate and use them for our project in Hurricane, Utah . Jaw 225 hp Impact 385 hp Also, our operation would average about 150 Ton/Hour at the 10 hour per day operation rate. Thank you for your help! Melissa On Thu, May 2, 2024 at 3:37 PM Susan Weisenberg <sweisenberg@utah.gov> wrote: Yes, that is what my management is looking for. With regards to the emissions estimates, if the 10 hour operation limit does not work for them, would it be possible to lower the production rate to 250 TPH? Thanks Susan Weisenberg, Environmental Scientist Office: 385-306-6512 On Thu, May 2, 2024 at 1:15 PM Melissa Scott <melissa.jpei@gmail.com> wrote: Hi Susan, We don't have any generators, because they are all self-propelled. I did provide Jordan with our HP ratings for another relocation. Would that help you with what you are doing on this relocation? Let me know how I can best help. Thanks! Melissa On Thu, May 2, 2024 at 11:48 AM Susan Weisenberg <sweisenberg@utah.gov> wrote: Hello Melissa, I accidentally left a voicemail to Alysen instead of reaching your cell number. 1000 feet to the nearest house is still a little close, but this project located at 2670 West 600 North, in Hurricane, will pass our National Ambient Air Quality Standards (NAAQS) modeling estimates if your operators can run the equipment for 10 hours rather than the requested 12 hours. This hourly limit would only apply to the actual listed aggregate equipment and does not apply to off loading storage piles or other miscellaneous equipment. The other issue is that I forgot to request information regarding how the equipment is powered. Can you let me know the size of any diesel fueled generators that will be used - or provide a statement that everything will be connected to an electrical power grid? Thanks, just as a heads up - all relocation requests are now required to provide the diesel generator information prior to authorization. Let me know if you have any questions or need additional information. Susan Weisenberg, 5/20/24, 11:29 AM State of Utah Mail - Re: temporary relocation to Hurricane questions https://mail.google.com/mail/u/1/?ik=bffac613d3&view=pt&search=all&permthid=thread-a:r-5251315859940239236%7Cmsg-f:179860021023999978…1/2 Environmental Scientist Office: 385-306-6512 Melissa Scott 4102 So 1440 E Circle St. George, UT 84790 (435) 680-4383 Melissa@jpexcavating.com -- Melissa Scott 4102 So 1440 E Circle St. George, UT 84790 (435) 680-4383 Melissa@jpexcavating.com 5/20/24, 11:29 AM State of Utah Mail - Re: temporary relocation to Hurricane questions https://mail.google.com/mail/u/1/?ik=bffac613d3&view=pt&search=all&permthid=thread-a:r-5251315859940239236%7Cmsg-f:179860021023999978…2/2