a 466 North 900 West, Kaysville UT 84037 p 801 547 0393 f 801 547 0397 w www.jub.com
02022-WS004-operating permit requestv2-File 11284 SRF 3F305
May 8, 2024
Mr. Hunter Payne
Utah Division of Drinking Water
Environmental Engineer II
P.O. Box 144830
Salt Lake City, UT 84114-4830
RE: Operating Permit, West Corinne Water Company #02022, Baker Spring Redevelopment (WS004),
File #11284, SRF #3F305
Dear Hunter,
West Corinne Water Company (WCWC) is seeking a permanent operating permit for the above
referenced project. A temporary operating permit was issued by the Utah Division of Drinking Water in
their November 13, 2020, letter. The temporary permit expires May 31, 2024.
The submittal of monthly spring flow readings for a period of three years was a condition of obtaining a
permanent operating permit. This data is provided in the attached table.
We request issuance of a permanent operating permit for the Baker Spring Redevelopment Project
(WS001).
Sincerely,
J-U-B ENGINEERS, Inc.
Brandon R. Nielsen, P.E.
Project Manager
Attachment
cc: Steve Norman, West Corinne Water Company, steve.norman@fbfs.com
Cary McFarland, West Corinne Water Company, carywestcorinnewater@gmail.com
MONTH 2024 2023 2022 2021
January 569 172 195 296
February 769 157 187 253
March 666 288 181 301
April 847 766 176 291
May 1120 166 276
June 1107 160 260
July 1083 151 248
August 1007 147 237
September 852 141 221
October 741 136 216
November 659 131 211
December 622 130 186
Baker Spring (WS004) Flow History (gpm)
West Corinne Water Company ‐ PWS 02022