PERMIT DEVIATION REPORT
Executive Secretary, Utah Air Quality Board
Deviation Report for Permit # 2100036004
21212024
TJTAH DEPARTMENT OF
ENVIRONMENTAL OUALITY
FEB 1 5 '-fi2-4
DIVISION OF AIR QUALIT\J
ln accordance with Operating Permit provision 1.5.2.b, and Utah Administrative Code (UAC) R307-415-6a
(3XcXii), the following deviation report is submitted.
1 Dates that the deviation occurred:
o2lotl2o24
2 Permit conditions for which deviation occurred:
ll.B.3.a. Operating temperature shall be no less than 1,360 degrees F. [Authority granted
under R307-401-8(fXa) [BACT]; condition originated in DAQE-AN011767000812I
Describe the deviation that occurred:
RTO temperature fell below 1,360 degrees F for approximately 15 hrs. Production activities
were halted, and lines connected to the RTO remained down untilthe repairs were
completed.
Was the deviation due to and "upset condition" as defined in Section ll of the permit.
NO
5 Describe the probable cause of the deviation:
The north tower main shaft wore through and broke in 3 places.
6 Describe any corrective actions or prevention measures taken:
The shaft was replaced, cool down damper switch also replaced.
ln accordance with Operating Permit Provision l.K and UAC R307-415-5b and based on information and belief
formed after responsible inquiry, I certify that the statement and information in this document are true,
accurate and complete.
Signature of responsible Official for the source.
&ac SroTT Plnsr nfivil*Z
Print or type the name and title of Responsible Official.
Genpak, LLC
279LW Hwy 56
Cedar City, UT 84720
435-85s-702s
REVIEWED
Initials JBR Date 3/6/2024
Comp Status Meets
File # 11767 Blue 2
NFA. temp due to equip fail
production ceased for
repairs.