HomeMy WebLinkAboutDAQ-2024-0052261 DAQC-228-24 Site ID 10096 (B4) MEMORANDUM TO: STACK TEST FILE – SUNNYSIDE COGENERATION ASSOCIATES THROUGH: Harold Burge, Major Source Compliance Section Manager FROM: Robert Sirrine, Environmental Scientist DATE: March 7, 2024 SUBJECT: Source: Circulating Fluidized Bed Combustion Boiler (EU#1) Location: 1 Power Plant Road, Sunnyside, Carbon County, UT Contact: Rusty Netz – 435-888-4476 Tester: Montrose Air Quality Services, LLC, Craig Kormylo 303-495-3936 FRS ID#: UT0000004900700030 Permit #: 700030005 dated March 8, 2023 Subject: Review of Pretest Protocol Dated February 16, 2024 On February 28, 2024, the DAQ received a stack test protocol for emissions testing of the Sunnyside EU#1 located in Sunnyside, Carbon County, UT. Testing will be performed starting the week of August 6, 2024, and continue over a 30-day operating period to determine Hg emission rates and demonstrate continuing compliance with the MATS Hg LEE requirements found in 40 CFR 63 Subpart UUUUU and permit Conditions II.B.2.m(1)(c), II.B.2.m(4) and (5), and II.B.2.m.1(c). PROTOCOL CONDITIONS: 1. RM 30B used to determine total vapor phase mercury emissions; OK 2. ALT -091 used to determine moisture content in lieu of RM4; OK DEVIATIONS: None noted. CONCLUSION: The Sunnyside Cogeneration Associates stack testing protocol for continuing Hg LEE status testing of EU#1 has been evaluated and appears to be acceptable. RECOMMENDATION: Send protocol review and test date confirmation notice. ATTACHMENT: Sunnyside Cogeneration Associates stack test protocol dated February 16, 2024. Sunnyside Cogeneration Associates P.O. Box 159 . Sunnyside, Utah tJ4539 . (435) 8884476 ' Fax (435) 888-2538 February 76,2024 Harold Burge Utah Division of Alr Quality 195 North 1950 West salt Lake city, utah 84116 I,TAH DEPARruENT OF EIWIRONMENTAL QUATJTY tEB 2B 2l,24 DIVISION OF AIR QUALTTV Subject:Protocol for Mercury Stack Testing to Demonstrate On-Going LEE status Sunnyside Cogeneration Associates (SCA) Dear Mr. Burge: lncluded is SCA's Protocol for Mercury Stack Testing to Demonstrate On-GoinB (LEE) status. The Hg testing peftains to the requirements of Utility MACI 40 CFR 63 Subpart UUUUU. SCA will continue with an annual 30-day Hg test to demonstrate Low Emittlng EGU status (LEE). The test will begin August 6,2024, We look forward to working with you to comply with the requirements of this regulation. lf you have any questions or concerns please contact Rusty Netz or myself at (435) 8884476. Thank You,Ar,-l//f Edward McCourt Agent for Sunnyside Cogeneration Associates Rusry Netz Plant File cc. Source Test Plan for 2024 LEE Demonstration Unit EU# I Sunnyside Cogeneration Associates Sunnyside, Utah Prepared For: Sunnyside Cogeneration Associates 1 Power Plant Road Sunnyside, Utah 84539 Prepared By: Montrose Air Quality Services, LLC 990 West 43rd Avenue Denver, CO 80211 For Submission To: Utah Division of Air Quality 195 North 1950 West Salt Lake City, UT 84116 Document Number: GPO43AS-O25A22-PP-673 Proposed Test Date: August 6,2(J24 Submittal Date: July 6t 2024 E;- ,"S. ot '.:::. ,,: : k UTAH DEPARTMENT OF ENVIRONMENTAL QUAL]TY I r|- r', ,1 , - ,li-i1 DI\.'ISION OF AIR QUALIT SrAG,k#, rsAtrx0jM*t{ r I I ceftify that, to the best of my knowled complete and accurate and conforms to Management System and D7036- it }tiiSignaturez ft\tl, the information contained in this document is requirements of the Montrose Quality 2/L5/2024 QA/QC AnalystName: 1 Matthew Parks I have reviewed, technically and editoriallf, details and other appropriate written materials contained herein. I hereby certify that to frre best of my knowledge the presented material is authentic and accurate and conforms td tne requirements of the Montrose Quality Management System and ASTM D7036-04. * . . )r' .,,r0" ,...1 l sisnature | ,:-'-'.t';;' ,J9*!;r'4 o"."r 2lls/2o24 Name: Tim Wojtach I Title: Account Manager GP043AS-025822-PP-81 1 Page 2 ot 43 'l;:::;;i.tii Table of Contents "Pags 1.0 Introduction. ........ 5 1.1 Summary of Test Program .......... 5 L.2 Applicable Regulations and Emission Limits ........6 1.3 Key Personnel....... ...........7 2.0 Plant and Sampling Location Descriptions........ ......... B 2.1 Process Description, Operation, and Control Equipment..... ............8 2.2 Flue Gas Sampling Locations ........ B 2.3 Operating Conditions and Process Data...... ...............9 2.4 Plant Safety........ ......9 2.4.L Safety Responsibilities ...........9 2.4.2 Safety Program and Requirements ........10 3.0 Sampling and Analytical Procedures .....12 3. 1 Test Methods .... .. ..........t2 3.1.1 EPA Method 30B.. .........12 3.2 Process Test Methods...... .....13 4.0 Quality Assurance and Reporting..... .........t4 4.L QA Audits.. ................14 4.2 Quality Control Procedures ...........t4 4.2.1 Equipment Inspection and Maintenance...... ............14 4.2.2 Audit Samples .........L4 4.3 Data Analysis and Validation .....L4 4.4 Sample Identification and Custody .......15 4.5 Quality Statement .............15 4.6 Reporting .............15 4.6.1 Example Report Format .......16 4.6.2 Example Presentation of Test Results....... ...............17 List of Appendices Appendix A Supporting Information.. ............18 Appendix A.1 Units and Abbreviations ...........19 Appendix A.2 Accreditation Information/Certifications..... .....27 Appendix "S" Field Work Safety Plan.. ............29 List of Tables Table 1-1 Summary of Test Program and Proposed Schedule....... ................. 5 Proposed Test Date ........5 1r.i GP043AS-025822-PP-8 1 1 Page 3 of 43 Table 1-2 Reporting Units and Emission Table 1-3 Test Personnel and Responsibifities.... .......... B Table 2-1 Sampling Location(s).......... i .......8 Table 4-1 Example <Parameter> Emissi{ns Results - Unit Name ..........L7 List of Figures I Figure 3-1 EPA Method 30B SampllnO Trafr ...,............13 Figure 4-1 Typical Report Format | ...............16 I I I I i I I I I I GP043AS-025822-PP-81 1 lirl i i 1.O Introduction 1,1 Summary of Test Program Sunnyside Cogeneration Associates contracted Montrose Air Quality Services, LLC (Montrose) to perform an emissions test program at the Sunnyside Power Plant located near Sunnyside, Utah. The tests are conducted to determine compliance with the emission limits in 40 CFR Part 63, Subpart UUUUU. The specific objectives are to: . Perform annual mercury emissions testing on the exhaust stack of Unit EU#1 over a 30-day operating period . Conduct the test program with a focus on safety Montrose will provide the test personnel and the necessary equipment to measure emissions as outlined in this test plan. Facility personnel will provide the process and production data to be included in the final report. A summary of the test program and proposed schedule is presented in Table 1-1. Table 1-1 Summary of Test Program and Proposed Schedule t .: l t:' Fiopojeo ' 0nit iD/ , ;l ,, ',;,,:;': fi$slD.atelli l$,q,u H$Biiil$..Erf.:|q lmetery Ta$,i-i-f"th lriiiiir(;l 8/612024 : Unit 1 Hg EPA 3oB, ALT-091 lli'I No, oJ Duration iffi fffi r,i iii, i*,gB*st fi ( ( [ 56 :.,=:),:a:aa= :ii'j'i:.;l W,,, GP043AS-025822-PP-81 1 Page 5 of 43 To simplify this test plan, a list of Units Abbreviations is included in Appendix A. Throughout this test plan, chemical ature, acronyms, and repoting units are not defined. Please refer to the list for speci details. L.2 Applicable Regulation and Emission Limits The results from this test program are applicable regulations or requirements. presented in Table 1-2. Table 1-2 in units consistent with those listed in the reporting units and emission limits are Repofting Units and Emission Limits Unit EU#1 H9 Hg Hg I I lbfrBtui-- i tulew-nt l- -{--------^---- Ii lblyr oL.2 0.0013 29.O IL ."J---". GP043AS-025822-PP-8 1 1 Page 6 of 43 1.3 Key Personnel A list of project participants is included below: Facility Information Source Location:Sunnyside Cogeneration Associates Sunnyside Power Plant 1 Power Plant Road Sunnyside, UT 84539 Rusty Netz Environmental Advisor Sunnyside Cogeneration Associates (435) 888-4476xtO7 rusnetz@hotmail.com Utah Depaftment of Air Quality Rob Leishman (801) s36-4438 RLeishman@utah.gov Project Contact: Role: Company: Telephone: Email: Agency Information Regulatory Agency: Agency Contact: Telephone: Email: Testing Company Information Testing Firm: Montrose Air Quality Services, LLC Contact: Craig Kormylo Title: DistrictManager Telephone: (303) 495-3936 Email: CKormylo@montrose-env.com GP043AS-025822-PP-8 1 1 PageT of 43 ',ir,l:G'fiiti ?|;; llt:it *: '=.#iiii,',,= :: Table 1-3 details the roles and responsibilities of the test team. Table 1-3 Test Personnel and Responsibilities :;;;,;;;::.:l:;:::'. |i: :a::1;aa1:::a=a.:a::: :::a ::.B$,'1, illiiililiiilltiiiiLLii., Field Project Manager Technician ':::::a.::::::a: ::a:a:a:.:: ::: :l::.:=.:t :t ..':::.: . ,.:.-.;:..::.:.:..:Primary AssigrFnent ' Operate mobile lab Execute stack platform responsibilities Additional Responsibilities Facil ty interface, test crew cooldination Preparation, support PM -..,:,::=..,:5 tk::In5id€ ::.'a:aa::a: ::aaaaa= 4.:.:aa:a:.::::.=: t:' i \il?EP.==,i=i..8=..E't1ll!1l!t:=';,"{=! ;; , 70t"808/8 .1$!.ul;-rmbe:r.of.-,,.v..e$ .ffiints._. -,,.1,:.Hg:t 2.O Plant and Sampling Location Descriptions 2,L Process Description, Operation, and Control Equipment The Sunnyside Cogeneration Facility is a steam-electric generating power plant located in Sunnyside, Carbon County, Utah. The plant consists of a circulating fluidized bed (CFB) combustion boiler designated EU #L, an emergency backup diesel-fired PumP, diesel storage tanks, coal handling equipment, ash handling equipment and limestone handling equipment. EU #1hasa rating of 700 mmBtu/hrand isequipped with limestone injection and a baghouse for control of emissions. The EU #1 is fueled by coal refuse from the Sunnyside and Star Point Refuse Piles. The flylbottom ash generated from the coal combustion is disposed of in an on-site landfill or used for beneficial applications. 2,2 Flue Gas Sampling Locations Actual stack measurements, number of traverse points, and location of traverse points will be evaluated in the field as part of the test program. Table 2-1 presents the anticipated stack measurements and traverse points for the sampling locations listed. Table 2-1 Sampling Location !=;iiiiffii: S'am.EI,!!,, , t"F.+i,ffiililiii Unit EU#1 Sample location(s) are verified in the field to conform to EPA Method 1. Acceptable cyclonic flow conditions are confirmed priorto testing using EPA Method 1, Section 11.4. ,,U..,,P # ',-\ffif ,1fi ,ff ;,-,4.,,ii;1;.,; 2021 2 GP043AS-025822-PP-81 1 Page B of 43 : ;, :,: 2.3 Operating Conditions and Process Data Emission tests are performed while the source/units and air pollution control devices are operating at the conditions required by the applicable regulation. The units are tested when operating normally. Plant personnel are responsible for establishing the test conditions and collecting all applicable unit-operating data. Data collected includes the following parameters: . Relevant CEMS data 2.4 Plant Safety Montrose will comply with all safety requirements at the facility. The facility Client Sponsor, or designated point of contact, is responsible for ensuring routine compliance with plant entry, health, and safety requirements. The Client Sponsor has the authority to impose or waive facility restrictions. The Montrose test team leader has the authority to negotiate any deviations from the facility restrictions with the Client Sponsor. Any deviations must be documented. 2.4.L Safety Responsibilities Planning . Montrose must complete a field review with the Client Sponsor prior to the project date. The purpose of the review is to develop a scope of work that identifles the conditions, equipment, methods, and physical locations that will be utilized along with any policies or procedures that will affect our work . We must reach an agreement on the proper use of client emergency services and ensure that proper response personnel are available, as needed . The potential for chemical exposure and actions to be taken in case of exposure must be communicated to Montrose. This information must include expected concentrations of the chemicals and the equipment used to identify the substances. . Montrose will provide a list of equipment being brought to the site, if required by the client Project Day . Montrose personnel will arrive with the appropriate training and credentials for the activities they will be performing and the equipment that they will operate . Our team will meet daily to review the Project Scope, Job Hazard Assessment, and Work Permits. The Client Sponsor and Operations Team are invited to participate. GP043AS-025822-PP-B 1 1 Page 9 of 43 E. w; fit, $ b. I . Montrose will provide equipment that can interface with the client utilities previously identified in the planning phase and only work with equipment that our client has made ready and prepared for connection . We will follow client direction regarding driving safety, safe work permitting, staging of equipment, and other crafts or work in the area . As per 40 CFR Part 60 Subpart A, Section 60.8, the facility must provide the following provisions at each sample location: o Sampling ports, which meet EPA minimum requirements for testing. The caps should be removed or be hand-tight. o Safe sampling platforms o Safe access to the platforms and test ports, including any scaffolding or man lifts o Sufficient utilities to perform all necessary testing . Montrose will use the client communication system, as directed, in case of plant or project emergency . Any adverse conditions, unplanned shutdowns or other deviations to the agreed scope and project plan must be reviewed with the Client Sponsor prior to continuing work. This will include any safe work permit and hazard assessment updates. Completion . Montrose personnel will report any process concerns, incidents or near misses to the Client Sponsor prior to leaving the site . Montrose will clean up our work area to the same condition as it was prior to our arrival . We will ensure that all utilities, connection points or equipment have been returned to the pre-project condition or as stated in the safe work permit. In addition, we will walk out the job completion with Operations and the Client Sponsor if required by the facility. 2.4.2 Safety Program and Requirements Montrose has a comprehensive health and safety program that satisfies State and Federal OSHA requirements. The program includes an Illness and Injury Prevention Program, site- specific safety meetings, and training in safety awareness and procedures. The basic elements include: . All regulatory required policies/procedures and training for OSHA, EPA, FMCSA, and MSHA . Medical monitoring, as necessary . Use of Personal Protective Equipment (PPE) and chemical detection equipment . Hazard communication GP043AS-025822-PP-8 1 r Page 10 of 43 . Pre-test and daily toolbox meetings . Continued evaluation of work and potential hazards r Near-miss and incident reporting procedures as required by Montrose and the Client Montrose will provide standard PPE to employees. The PPE will include but is not limited to; hard hats, safety shoes, glasses with side shields or goggles, hearing protection, hand protections, and fall protection. In addition, our trailers are equipped with four gas detectors to ensure that workspace has no unexpected equipment leaks or other ambient hazards. The detailed Site Safety Plan for this project is attached to this test plan in Appendix "S". GP043AS-025822-PP-81 1 Page 11 of 43 , I I 3.1 Test Methods The test methods for this test program have been presented in Table 1-1. Additional information regarding specific applications or modifications to standard procedures is presented below. 3.1.1 EPA Method 3OB Determination of Total Vapor Phase Mercury Emissions from Coal-Fired Combustion Sources Using Carbon Sorbent Traps EPA Method 30B is a manual test method for measuring total vapor phase mercury (Hg) emissions from coal-fired combustion sources using sorbent trap sampling and an extractive or thermal analytical technique. The method includes sampling into duplicate sorbent traps, which are analyzed using a sorbent trap mercury analyzer. This type of analyzer uses thermal desorption with ultraviolet atomic absorption (UV AA) or ultraviolet atomic fluorescent (UV AF) cold vapor analysis. Each trap consists of two equal-mass sections of iodinated activated charcoal (Section 1 and 2). The results for Section 1 and Section 2 of each tube are reported in nanograms (ng) of Hg per section, and then they are summed. The charcoal sorbent is pre-checked to certify that mercury background levels are below the detection limit of the laboratory instrument. Each trap is uniquely numbered, and the sorbent batch number is printed on the outside of the glass tubes. One trap per run is pre- spiked in the first sorbent section with a known quantity of elemental mercury, using a proprietary gas-phase bulk spiking procedure. Each run includes two samples (A and B) collected concurrently from a single representative sampling point in the exhaust stack using a dual probe. Samples are drawn through the sorbent traps into a moisture knockout loaded with desiccant, and then through a sampling orifice. The typical sampling system is detailed in Figure 3-1. 3.O Sampling and Analytical Procedures :,a:1:::,l.:.a.a.aaa.aa :;,:;::::;;:::::::,1 t,i..;: 'iil;:ll.,lillZit:tlttll,filfi i Page 12 of 43GP043AS-025822-PP-B 1 1 :t::t:: : , ' t i'"'ll Figure 3-1 EPA Method 3OB Sampling Train fTherrccouple Healed Vaeum Line D|H,O Sh&t .- Vaculm Line 3,2 Process Test Methods The applicable regulations do not require process samples to be collected during this test program. GP043AS-025822-PP-B 1 1 4.A Quality Assurance and Reporting 4.L QA Audits Montrose has instituted a rigorous QA/QC program for its air quality testing. Quality assurance audits are performed as part of the test program to ensure that the results are calculated using the highest quality data available. This program ensures that the emissions data we report are as accurate as possible. The procedures included in the cited reference methods are followed during preparation, sampling, calibration, and analysis. Montrose is responsible for preparation, calibration, and cleaning of the sampling apparatus. Montrose will also perform the sampling, sample recovery, storage, and shipping. Approved contract laboratories may perform some of the preparation and sample analyses, as needed. 4.2 Quality Control Procedures Montrose calibrates and maintains equipment as required by the methods pefformed and applicable regulatory guidance. Montrose follows internal procedures to prevent the use of malfunctioning or inoperable equipment in test programs. All equipment is operated by trained personnel. Any incidence of nonconforming work encountered during testing is reported and addressed through the corrective action system. 4.2.L Equipment Inspection and Maintenance Each piece of field equipment that requires calibration is assigned a unique identification number to allow tracking of its calibration history. All field equipment is visually inspected prior to testing and includes pre-test calibration checks as required by the test method or regulatory agency. 4.2.2 Audit Samples When required by the test method and available, Montrose obtains EPA TNI SSAS audit samples from an accredited provider for analysis along with the samples. Currently, the SSAS program has been suspended pending the availability of a second accredited audit sample provider. If the program is reinstated, the audit samples will be ordered. If required as part of the test program, the audit samples are stored, shipped, and analyzed along with the emissions samples collected during the test program. The audit sample results are reported along with the emissions sample results. 4.3 Data Analysis and Validation Montrose convefts the raw field, laboratory, and process data to reporting units consistent with the permit or subpart. Calculations are made using proprietary computer spreadsheets or data acquisition systems. One run of each test method is also verified using a separate example calculation. The example calculations are checked against the spreadsheet results and are included in the final report. The"Standard Conditions"forthis project are29.92 inches of mercury and 68 oF. G P043AS -025 822-PP -BLL Page 14 of 43 i: 4.4 Sample Identification and Custody The on-site Field Project Manager will assume or assign the role of sample and data custodian until relinquishing custody. The sample custodian will follow proper custody procedures before departing from the test site including: . Assign the unique sample identification number to each sample . Attach sample labels and integrity seals to all samples . Complete COC form(s), ensuring that the sample identification numbers on the samples match the sample identification numbers on the COC . Pack and store samples in accordance with the test method requirements in appropriate transport containers for protection from breakage, contamination, or loss . Keep samples in a secure locked area if not in the direct presence of Montrose staff The sample custodian will follow proper custody procedures upon arriving at the Montrose office including: . Remove samples and COC documents from vehicles and check into designated secure sample holding areas . Store samples requiring additional measures such as refrigeration or dry ice appropriately 4.5 Quality Statement Montrose is qualified to conduct this test program and has established a quality management system that led to accreditation with ASTM Standard D7036-04 (Standard Practice for Competence of Air Emission Testing Bodies). Montrose participates in annual functional assessments for conformance with D7036-04 which are conducted by the American Association for Laboratory Accreditation (A2LA). All testing performed by Montrose is supervised on site by at least one Qualified Individual (QI) as defined in D7036-04 Section 8.3.2. Data quality objectives for estimating measurement unceftainty within the documented limits in the test methods are met by using approved test protocols for each project as defined in D7036-04 Sections 7.2.7 and 12.L0. Additional quality assurance information is included in the appendices. The content of this test plan is modeled after the EPA Emission Measurement Center Guideline Document (GD-042). 4.6 Reporting Montrose will prepare a final report to present the test data, calculations/equations, descriptions, and results. Prior to release by Montrose, each report is reviewed and certified by the project manager and their supervisor, or a peer. Source test reports will be submitted to the facility or appropriate regulatory agency (upon customer approval) within GP043AS-025822-PP-81 1 Page 15 of43 25 days of the completion of the field work. The report will include a series of appendices to present copies of the intermediate calculations and example calculations, raw field data, laboratory analysis data, process data, and equipment calibration data. 4.6.L Example Report Format The report is divided into various sections describing the different aspects of the source testing program. Figure 4-1 presents a typical Table of Contents for the final report. Figure 4-1 Typical Repoft Format Cover Page Ceftification of Repod Table of Contents Section 1.0 Introduction 2.O Plant and Sampling Location Descriptions 3.0 Sampling and Analytical Procedures 4.O Test Discussion and Results 5.0 Internal QA/QC Activities Appendices A Field Data and Calculations B Facility Process Data C Laboratory Analysis Data D Quality Assurance/Quality Control E Regulatory Information GPO43AS-025 822-PP -BLL Page 16 of 43 4.6.2 Example Presentation of Test Results Table 4-1 presents the typical tabular format that is used to summarize the results in the final source test report. Separate tables will outline the results for each target analyte and compare them to their respective emissions limits. Table 4-1 Example <Parameter> Emissions Results - Unit Name fy"cery oat: -P1lgIF-!e-r lr-lIre I Oz, o/o volume dry I l--1- -" i xx xx ! .........,.._,.s 1 I I--.'* *4 i ii:npJ!-r9_.111-v:_"c_::_"1"-1::_n9J9r:__ .__"_ * i**]--.-*}-."..-"]*"' i sample duration, minutes , XX i XX ! XX : XX.**flsj.v.r*n*-ril:!e.?- -- * r "II ":"-l--r"- - l--:- *-, - -;x :* I-* r* ..... -:.. . -- - - n _c-oa eo vorur" dry " __:T* i1 * ": XL -| !\ _ _ j -_;i- ,a..^ ^^^ !^--^-^!..-^ 6r f .,., i .,., 1 .,., i .,., i XX **-***l** ****"-'"------ - -1I flue gas temperature, oF XX I xX ] xX i xx 1 i moisture content, o/o volume 1 xx i xi : xx j xx i GP043AS-025822-PP-8 1 1 Page 17 of 43 Appendix A Su pportiryg f nformation Appendix A.1 Units and Abbreviations GP043AS-025822-PP-81 1 Page 19 of 43 60 l*?.x,I\gLE UNITS AND ABBREVIATIONS @X% 02 corrected to X% oxygen (corrected for dilution air) lCCl absolute value of the confidence coefficient ldl absolute value of the mean differencesoC degrees CelsiusoF degrees FahrenheitoR degrees Rankine " HzO inches of water column 13.6 specific gravity of mercury AH pressure drop across orifice meter, inches H2O AP velocity head of stack gas, inches H2O e total sampling time, minutes Ug microgram P" density of acetone, mg/ml Pw density of water, 0.9982 g/ml or 0.00220't lb/ml acfrn actual cubic feet of gas per minute at stack conditions A" cross-sectional area of nozzle, ft As cross-sectional area ofstack, square feet (ft') Btu British thermal unit Bm proportion by volume of water vapor in gas stream Ca particulate matter concentration in stack gas, gr/acf Crrg average unadjusted gas concentration, ppmv Coi, measured concentration of calibration gas, ppmv cf or ft3 cubic feet cfrn cubic feet per minute CG". average gas concentration adjusted for bias, ppmv CM average of initial and final system bias check responses from upscale calibration gas, ppmv cm or mt cubic meters Cr,rr actual concentration of the upscale calibration gas, ppmv Co average of initial and final system bias check responses from lowievel calibration gas, ppmv Cp pitot tube coefficient Cs particulate matter concentration in stack gas, gr/dscf CS calibration span, % or ppmv Cs measured concentration of calibration gas, ppmv Cv manufactured certified concentration of calibration gas, ppmv D drift assessment, % of span dcf dry cubic feet dcm dry cubic meters Dn diameter of nozzle, inches Ds diameter of stack, inches dscf dry standard cubic feet dscfm dry standard cubic feet per minute dscm dry standard cubic meters Fd F-factor, dscf/MMBtu of heat input fom feet per minute fps feet per second feet t( square feetg gram gal gallons gr grains (7000 grains per pound) grldscf grains per dry standard cubic feel hour GP043AS-025822-PP-B 1 1 Page 20 of 43 I in k K K3 1(4 kg 64\ l*?N,I+g[,H UNITS AND ABBREVIATIONS percent of isokinetic sampling inch kilo or thousand (metric units, multiply Uy t O3) kelvin (temperature) conversion factor 0.0154 grlmg conversion factor 0.00266S ((in. Hgxft'))/((ml)('R)) kilogram 6 pitot tube constant (85.49 fUsec) kwscfrr thousand wet standard cubic feet per hour I liters lb/hr pounds per hour lb/MMBtu pounds per million Btu lpm liters per minute m meter or milli M thousand (English units) or mega (million, metric units) mt cubic meters ma mass of residue of acetone after evaporation, mg Md molecular weight of stack gas; dry basis, lb/lb-mole meq milliequivalent mg milligram Mg megagram (106 grams) min minute ml or mL milliliter mm millimeter MM million (English units)MMBtu/hr million Btu per hour mn total amount of particulate matter collected, mg mol mole mol. vvt. or MW molecular weight Ms molecular weight of stack gas; wet basis, lb/lb-mole MW molecular weight or megawattn number of data points ng nanogram nm nanometer Pu", barometric pressure, inches Hg pg picogram Ps stack static pressure, inches H2O Pm barometric pressure of dry gas meter, inches Hg ppb parts per billionppbv parts per billion, by volumeppbvd parts per billion by volume, dry basisppm parts per millionppmv parts per million, by volumeppmvd parts per million by volume, dry basisppmvw parts per million by volume, wet basis Ps absolute stack gas pressure, inches Hg psi pounds per square inchpsia pounds per square inch absolutepsig pounds per square inch gauge Psto standard absolute pressure, 29.92 inches Hg Q" volumetric flow rate, actual conditions, acfrn Q. volumetric flow rate, standard conditions, scfrn Qsta volumetric flow rate, dry standard conditions, dscfrn R ideal gas constant 21.85 ((in. Hg) (ft3)y(('R) (lbmole)) GP043AS-025822-PP-8 1 1 Paqe 21 of 43 64\ I,}?N,Iryg[,H UNITS AND ABBREVIATIONS SBnna post-run system bias check, % ofspan SBi pre-run system bias check, % of span scf standard cubic feet scfh standard cubic feet per hour scftn standard cubic feet per minute scm standard cubic meters scmh standard cubic meters per hour sec second sf, sq. ft., or d square feet std standard t metric ton (1000 kg) T o.szs t-value Ta absolute average ambient temperature, "R (+459.67 for English) T, absolute average dry gas meter temperature, oR (+459.67 for English) ton ort ton = 2000 pounds tph or tons/hr tons per hour tpy or tons/yr tons per year T" absolute average stack gas meter temperature, oR (+459.67 for English) Tsta absolute temperature at standard conditions % V" vm Vmlstol vm vn vs Vwc(sto) Vwilstol Vres1sto1 W wa W,p Wss Y volt volume of acetone blank, ml volume of acetone used in wash, ml total volume H2O collected in impingers and silica gel, grams volume of gas sampled through dry gas meter, ft' volume of gas measured by the dry gas meter, conected to standard conditions, dscf stack gas volume sampled, acf volume collected at stack conditions through nozzle, acf average stack gas velocity, feet per second volume of water vapor condensed, corrected to standard conditions, scf volume of water vapor in gas sampled from impingers, scf volume of water vapor in gas sampled from silica gel, scf watt weight of residue in acetone wash, mg total weight of impingers, grams total weight of silica gel, grams dry gas meter calibration factor, dimensionless GP043AS-025 822-PP -BlL Page 22 of 43 64\ llg,N,T\P"LH AAS ACDP ACE AD ADL AETB AS ASTM BACT BDL BHP BIF BLS CC CD CE CEM CEMS CERMS CET CFR CGA CHNOS CNCG co coc COMS CPM CPMS CT CTM cTo CVAAS De DE Dioxins DLL DNCG ECD EIT ELCD EMPC EPA EPRI ES ESP EU FCCU FGD FI FIA FID FPD FPM FTIR FTPB FTRB Furans GC ACRONYMS atomic absorption spectroscopy air contaminant discharge permit analyzer calibration error, percent of span absolute difference above detection limit Air Emissions Testing Body applicable standard (emission limit) American Society For Testing And Materials best achievable control technology below detection limit brake horsepower boiler and industrial furnace black liquor solids confidence coefficient calibration drift calibration error continuous emissions monitor continuous emissions monitoring system continuous emissions rate monitoring system calibration error test Code of Federal Regulations cylinder gas audit elemental analysis for determination of C, H, N, O, and S content in fuels concentrated non-condensable gas catalytic oxidizer chain of custody continuous opacity monitoring system condensible particulate matter continuous parameter monitoring system combustion turbine conditional test method catalytic thermal oxidizer cold vapor atomic absorption spectroscopy equivalent diameter destruction efficien cy polychlorinated dibenzo-p-dioxins (pcdd's) detection level limited dilute non-condensable gas electron capture detector Engineer ln Training electoconductivity detector (hall detector) estimated maximum possible concentration US Environmental Protection Agency Electric Power Research lnstitute emission standard (applicable limit) electrostatic precipitator emission unit fluid catalytic cracking unit fl ue gas desulfurization flame ionization fl ame ionization analyzer fl ame ionization detector fl ame photometric detector fi lterable particulate matter Fou rier-transform i nfrared spectroscopy field train proof blank field train recovery blank polychlorinated dibenzofurans (pcdfs) gas chromatography GP043AS-025822-PP-B 1 1 Page 23 of 43 60 **?,N,Tryg[,E ACRONYMS GC/MS gas chromatography/mass spectroscopy GFAAS graphite furnace atomic absorption spectroscopy GFC gas filter correlation GHG greenhouse gas HAP hazardous air pollutant HC hydrocarbons HHV higher heating value HPLC high performance liquid chromatography HRGC/HRMS high-resolution gas chromatography/high-resolution mass spectroscopy HRSG heat recovery steam generator lC ion chromatography ICAP inductively-coupled argon plasmography ICPCR ion chromatography with a post-column reactor ICP-MS inductively coupled plasma-mass spectroscopy lR infrared radiation ISO lnternational Standards Organization kW kilowatts LFG landfill gas LHV lower heating value LPG liquified petroleum gas MACT maximum achievable control technology MDI methylene diphyenyl diisocyanate MDL method detection limit MNOC maximum normal operating conditions MRL method reporting limit MS mass spectrometry NA not applicable or not availableNCASI National Council For Air And Steam lmprovement NCG non-condensable gases ND not detectedNDIR non-dispersive infraredNESHAP National Emissions Standards For Hazardous Air Pollutants NG natural gas NIOSH National lnstitute For Occupational Safety And Health NIST National lnstitute Of Standards And Technology NMC non-methane cutterNMOC non-methane organic compounds NMVOC non-methane volatile organic compoundsNPD nitrogen phosphorus detector NSPS New Source Performance Standards OSHA Occupational Safety And Health Administration PAH polycyclic aromatic hydrocarbons PCB polychlorinated biphenyl compounds PCWP plywood and composite wood products PE Professional Engineer PFAS per- and polyfluoroalkyl substances (PFAS) Pl photoionization PID photoionization detector PM particulate matter PMro particulate matter less than 10 microns in aerodynamic diameter PMz.s particulate matter less than 2.5 microns in aerodynamic diameter POM polycyclic organic matter PS performance specification PSD particle size distributionPSEL plant site emission limits PST performance specification testPTE permanent total enclosure PTM performance test method GP043AS-025822-PP-B 1 1 Page 24 of 43 6C l*?,N,T+p"[,8 ACRONYMS QtuQC quality assurance and quality control Ql Qualified lndividual QSTI Qualified Source Testing lndividualRA relative accuracyRAA relative accuracy auditRACT reasonably available control technologyRATA relative accuracy test auditRCTO rotary concentrator thermal oxidizerRICE stationary reciprocating internal combustion engineRM reference method RTO regenerative thermal oxidizerSAM sulfuric acid mist SCD sulfur chemiluminescent deteclorSCR selective catalytic reduction systemSD standard deviationSemi-VOST semivolatile organic compounds sample trainSRM standard reference materialTAP toxic air pollutant TBD to be determinedTCA thermal conductivity analyzerTCD thermal conductiMty detectorTGNENMOC total gaseous non-ethane non+nethane organic compoundsTGNMOC total gaseous non-methane organic compoundsTGOC total gaseous organic compoundsTHC total hydrocarbonsTIC tentatively identified compoundTO thermal oxidizerTO toxic organic (as in EPA Method TO-15)TPM total particulate matterTSP total suspended particulate matterTTE temporary total enclosureULSD ultra-low sulfur dieselUV ultraviolet radiation rangeVE visible emissionsVOC volatile organic compoundsVOST volatile organic sample trainWC water column \ /WTP waste water treatment plant GP043AS-025822-PP-8 1 1 Page 25 of 43 Ag As Ba Be c cd cds 60 s?sIryp"Lr Ni NO Noz Nor o2 Clz cl02 co Co CO, Cr Cu H2 HrO CHEMICAL NOMENCLATURE silver arsenic barium beryllium carbon cadmium cadmium sulfide CH2O formaldehyde CH3CHO acetaldehyde CH3OH methanol CHo methane C2H4O ethylene oxide CzHe ethane CaH4O acrolein CaH6O propionaldehyde CeHe propane C6H5OH phenol chlorine chlorine dioxide carbon monoxide cobalt carbon dioxide chromium copper EtO ethylene oxide EtOH ethyl alcohol (ethanol) hydrogen water HuOz hydrogen peroxide HrS hydrogen sulfide H2SO4 sulfuric acid HCI hydrogen chlorideHg mercuryIPA isopropyl alcoholMDI methylene diphyenyl diisocyanate MeCl2 methylene chloride MEK methyl ethyl ketone MeOH methanolMn manganese nitrogen ammonia nickel nitric oxide nitrogen dioxide nitrogen oxides oxygen P phosphorus Pb lead PCDD polychlorinateddibenzo.pdioxins PCDF polychlorinated dibenzofurans Sb antimony Se SO, Sos SO, TCDD TCDF TGOC THC TI TRS Zn selenium sulfur dioxide suffur trioxide sulfur oxides tetrachlorodibenzod ioxin tetrach lorodibenzofu ran total gaseous organic concentration total hydrocarbons thallium total reduced sulfur compounds zinc N2 NHs GP043AS-025822-PP-81 1 Page 26 of 43 Appendix A.2 Accred itation I nformation / Ce rtifications ffi Americon Associotio n f or Loborotorv Accreditotion Accredited Air Emission Testing Body A2LA hos occredited MONTROSE AIR QUALITY SERVICES ln recognition of ihe successful completion of the joint A2LA ond Stock Testing Accredilotion Council (STAC) evoluolion process, this loborolory is occrediied to perform testing ociivities in complionce wilh ASTM D7035:2004 - Stondord Prociice for Competence of Air Emission Testing Bodies. Vice President, Accreditotion Services For the Accreditotion Council Certificoie Number 3925.0 1 Volid to Februory 29,2024 Th.is accred.itation program. is not includcd under the A2LA ILAC Mutual Recognition Arrongement. GP043AS-025822-PP-81 1 Paqe 28 of 43 Presenied this 4th doy of Februory 2022 Appendix r\S" Field Work Safety Plan I I ffiffiq &ne#MY.eer}*6e 'Wu f ' AI{a ntu,Airtry $ilRVs{ rq; I I I I SITE SAFEry PLAN BOOKLET I I Glient Project Revision Date: January 21,2022 GP()43AS-025822-PP-811 Page 30 of 43 .#fo" .L t L ./;'{ ." t i.}; Page 1 of 2 Site Safety Plan and JHA Purpose and lnstructions Purpose Employee safety is the top priority of Montrose Environmental Group. All employees must be trained to assess and mitigate hazards. The District Manager and Project Manager are responsible to ensure all hazards have been properly identified and managed. All employees have Stop Work Authority in all situations where an employee feels they or their co-worker cannot perform a job safely or if there is a task for which they have not been adequately trained. The Site Safety Plan (SSP) has been developed to help assist Montrose test crews with identifying physical and health hazards and determining how the hazards will be managed. Additionally, the SSP will help each crew manage the safety of the employees by providing emergency procedures and information. The booklet contains a severalsafety forms that may be required in the field. lnstructions The SSP consists of the following: 1. A Pre-Mobilization Test Plan - To be completed in it's entirety by the client project Manager prior to the test. 2. A Job Hazard Analysis is a standardized, two-page, fillable form that is used to evaluated the tasUsite's particular hazards and controls. The form also includes a daily toolbox topic and daily hazard review with sign off by the team. The client Project Manager is responsible to complete the JHA form through section B. Upon arrival at the test site, the team will review the form for accuracy, making any corrections required and complete the remainder of the JHA. Section 9 will require at least three tasks, hazards and controls be identified for the project. Each team member has the option to discuss making changes or adding to the JHA and must sign on the Job Hazard Analysis form in agreement and sign in Section 10. The JHA is to be modified when conditions change. A toolbox meeting with a daily topic in addition to a review of the hazard analysis is required daily for the duration of the test. An additional sheet of paper with the toolbox topic and signatures can be added to the SSP packet. 3. Hazard Control Matrix - contains useful information on both engineering and administrative controls that a crew can use to reduce or eliminate the hazards they have observed plus applicable PPE that may be required. 4. Emergency Action Plan - The Job Supervisor/ Client Project Manager (CPM) will complete the Emergency Action Plan form and ensure that allemployees are familiar with the facility emergency and evacuation procedures, assembly/ rally points, alert systems, and signals prior to work commencing. ln the event of an emergency situation/ evacuation, the Job Supervisor/ CPM will maintain a roster and be responsible for accounting for all employees. The Job Supervisor/ CPM will ensure that this Emergency Action Plan Form is completed, communicated to all employees, signed, and posted. 5. Additional Forms, as applicable a. MEWP Lift lnspection Form b. Heat Stress Prevention Form Based on Heat Index c. Extended Hours Form AQS-FRM-1.13R1 Page 31 of 43GP043AS-025822-PP-81 1 Page2 of2 AQS-FRM-1.13R1 Page 32 of43 Purpose and lnstructions ger should continually update their SSPs as hazards are presented. the Test Plan in the office for a period of 3 for the Site Safety Plans. tI &V,c &qL.${\ & }dLJ}H I4W ' ;ri r,.\ r. ,'i ' rl j,. f , I Site Safety Plan ano .lln The SSP is a living document. The Project $ana new information and conditions change or ifkrew I Each completed SSP should be maintainedfwith years. There will be an audit process develfOed GPO43AS-025822-PP -8LL PROJ ECT NAME/LOCATION : TEST DATE: PROJECT #: PROJECT MANAGER: TEST SCOPE: SITE CONTACT: Name:Contact Phone: ; ;<;zo a.ia I ita.,,*,: [, Page 1 of 2 PRE.MOBILIZATION TEST I NFORMATION $gglSe fypei New Source: _ Revisit: _ Prj#/Date/Tech: Coal Fired Electric Utility: _ Ethanol Plant: _ Chemical Mfg. of CemenULime Kiln Plant: _ Specialty Mfg. of:Other: Anticipated Effluent Composition - check all that apply and fill in expected concentration in ppm/% tr voc Toxic: Corrosive: Dust: trtr CO NOx tr other lf other, explain: Flammable: Engineering Controls to be lmplemented: tr SOz Additional Safety Equipment Required : Personal gas monitors: _ Respiratory Protection: Half Face_ Full Face_ HEPA Filters_ Supplied Air: _ (Safety Dept. Approval) Approximate Flue Gas Temperatures, (F) below 210 210 to 450 450 to 950 above 950 other lf other, explain: Approximate Duct Pressure, (iwg): -3 -3 to +3 +3 to +7 trtr tr above tr +7 other lf other, AQS-FRM-1.17 tr u below explain: _ GP043AS-025822-PP-8 1 1 Page 33 of 43 ,.":.,i ,1,1(l+o"" E !.'" J r, M Page 2 of 2 PRE.MOBILIZATION TEST I N FORMATION Sampling Location: Stack Port _ Duct Port _ Approximate Sampling Platform Height, (ft) tr 100 other lf other, explain: Access and Protection: Elevators: _ Ladders: _ MEWP Lift: _ Scaffold: _ Equipment Hoist: _ Guardrails: _ Toe plate: _ Engineered Tie Off Points: _ Heat Shield: _ Other: Describe how equipment will be mobilized to the sampling location: trtrtr below 6 6 to 50 50 to 100 tr above Additional Information: Effluent Chem ical Requlatorv Limits Gas Name Ghemical Formula Gal OSHA PELI (ppm) Cal OSHA STEL2 {ooml NIOSH REL TWA3 (ppm) Cal OSHA Ceiling {ooml IDLHl {ppm} 3arbon Monoxide CO 25 200 35 200 1,200 Nitric Oxide NO,25 ND5 25 ND 100 Sulfur Dioxide SOz 2 5 2 ND 100 Hvdroqen Chloride HCI 0.3 2 ND 2 50 Hydrogen Sulfide HzS 10 15 10 (10 min.)c 50 100 )alifomia Occupational Safety and Health Administmtion (OSHA) Permissible Exposure Limit (PEL) based on an $-hour shift; 2: Cal OSHA Shott-term Exposure Limit (STEL) based on a lSminute peiod; 3: National lnstitute for O@upational Safety and Health (NIOSH) Recommended Exposure Limit (REL) Time-weighted Average (TWA) based on an 8-hour shift; 4: lmmediately Dangerousto Life or Heafth (IDLH); 5: Not Defined (ND); C: Ceiling Limit - Maximum allowable human exposure limit fu an aiftome or gaseous subsfarrce, which is not to be exceeded, even momentaily. Prepared by: Reviewed by: Date: Date: AQS-FRM-1.17 GP043AS-025822-PP-8 1 1 Page 34 of 43 lient lontact Name )ate =acility SSP Writer )M 3lient Rep I Job Preparation [ .lou Site Walk Through Completed tr ! Sate Work Permit Received from Client -J Site Specific Training Complete lf the heat index is expected to be above 91', fill out the Heat Stress Prevention Form. Job Hazard Analysis Risk E rime Pressure E Remote Work Location E > 12 hr shift [ Wo*ing > 8 consecutive days E u"t of procedures E E*tr"r" temps, wind >30mph E Personal illnessffatigue LJ vague work guidane E Monotonous Aciivity E rirst day back after time off E tvtuttipte job locations E Other: PPE E Hard Hats ! Safety Glasses lSafety Toe Shoe/Boot I Hearing Protection lSafety Spotter E Hi-Vis Vests E Harness/Lanyard* E Goggles E Personal Monitor Type: E Metatarsal Guards EI Hot Gloves E Face Shield E Respirator Type: E Nomex/FRC E Other PPE: 1of3 '{;Ri: l1 2. 3. 4. AQS-FRM-1.18 Page 35 of 43 acility lnformation/Emergency Preparedness lf non-emergency medical attention is needed, call: AXIOM #:,877-502-9466. Plant Emergenry # Certified First Aid Person: EMS Location Evacuation Routes Rally Point Severe Weather Shelter Location Eye Wash & Safety Shower Location Operational: EYes ENo lnformation : (list type): Stack Gas Temp. ("F) Stack Gas Press. ("H2O) Stack Gas Components: Stack Gas lnhalation Potential? EYes E t'to tf ves, see List of Hazard Chemicats. Hazards Dust Hazards Thennal:Burn Electrical Hazards lnadequate Lighting Slip and Trip Hand Protection Secondary Permits Working from Heights S€e also Sect 7 Eleclrical Lifting Respiratory See also Sect. 8 Hazards for Consideration Hazard Controls E Dust Mask E Goggles E Other: E HotGloves DHeatshields EOther:ProtectiveClothing: E Connections Protecied from Elements n External GFCI E Other: E Xe nating Requirement E lntrinsically Safe Requirement E lnstall Temporary Lighting E Headlamps I Housekeeping E Barricade Area E Other: E Cut Resistant Gloves E pincn ms. El cen;;f D eearicat I tmpact Resistant fl other: E Hotwork E Confined Space ! Excavation f] Falling objects E Fall protection E Drop zone protec{ion f] Phtform load ratings I ScattotO inspection E Ladder inspedion E Barricades for equipment E Exposed wire/connector ! Verity equipment grounding f] Arc Flash fl Crane lift plan E Rigging inspection E fag lines used El noists in place E Unexpected exposure E Chemical E Dust (combustible) ! PEL provided E Cartridoes or suoolied air available E Gas detection GP043AS-025822-PP-B 1 1 @" i',- ;'"" '] s \ ;\i Additional Work Place Hazards Job Hazard Analysis 2of3 6.ritical Procedures - check all that apply - *indicates additional form must be completed or collected from client E Heat Stress Prevention" fl Confined Space* fl MEWP- E Roof Work fl Scaffoto ECotoWeatherWork IHazardousEnergyControf f]ExposureMonitoring EOther: From Heights Fall Protection Falling Objects Proteclion Fall Hazard Communication ![ fixea Guardrails/Toe boards E fatt Prevention PPE Warning Line System i E e"nioOing tr Netting ! House Keeping flTethered Tools O Catctr Blanket or Tarp D AdjacenUOverhead Workers ! Contractor Contact E Client Contac{ Other Considerations Environmental Hazards - Weather Forecast E HeaVCold ELigntning E Rain E Snow E lce E Tornado ! wind Speed Steps for Mitigation: Electrical Safety Planning Plant Hook up: n t tov D 22OD4OV E aaov E cenerator E nard wired into panel Electrical Classified Area: EYes fl No Trailer Grounded: E Yes E tlo Plug Type Electrical Hook Up Responsibility: List of Hazardous Chemicals E Acetone fl Nitric Acid Other Chemacals: E Hydrogen Peroxide E Compressed Gases D Hexane Esufuric Acid El lsopropyl Alcohol I Fhmmable Gas E Toluene fl Hydrochloric Acid E liquia Nitrogen l-l Non-Flammable Gas E Hzs E carbon Monoxide Steps for Mitigation: lildlife/Fauna in Area E Poison tuy flPoison oak Elnsects:!Wildlife: Personnel M known allergies to bees stings or other allergens? ! Yes Eruo 8. Hazards and Mitigation Steps 1 2 3 1 2 3 1 2 3 'l 2 3 1 2 3 1 2 3 1 2 3 1 2 3 AQS-FRM-1.18 Page 36 of 43GP043AS-025822-PP-8 1 1 Job Hazard Analysis 10 3of3 JHA REVIEW: Crew Names & Signatures Printed Name Siqnature Date Printed Name Signature Date Dailv JHA Meetinq & Review Items to review: o Change in conditions r Extended work hours r Daily Safety Topic o New workers or contractors r Occurrence of near misses or injuries Initialing demonstrates that site conditions and hazards have not changed from the original SSP. lf changes did occur, make the updates to this JHA and add notes as applicable in Section 9. Day Discussion Topic lnitials 2 3 4 5 6 7 8 9 10 11 AQS-FRM-1.1 Page37 of 43GP043AS-025822-PP-81 1 lra ,! iitt..,.. "t ),\t \ r" I i \ t i ". i. .j .: g g:/2 Poge 1 ol 2 EMERGENCY ACTION PLAN FORM The Job Supervisor/ Client Project Manager (CPM) will ensure that all employees are familiar with the facility emergency and evacuation prooedures, assembly/ rally points, alert systems, and signals prior to work commencing. ln the event of an emergency situation/ evacuation, the Job Supervisor/ CPM will maintain a roster and be responsible for accounting for all employees. The Job Supervisor/ CPM will ensure that this Emergency Action Plan Form is completed, communicated to all employees, and posted. -Eou must follow the client's emergency action plan first, and notify your Supervisor immediately, .lf incident is life threatening, CALL 911 IMMEDIATELLY .E non-em€rgency medical attention is needed, call AXIOM Medical number: 877-502-9466. AQS-FRM-1.11 GP043AS-025822-PP-8 1 1 1 MEG Job Supervisor/ CPM's Name: 2 MEG Job Supervisor/ CPM's Telephone Number: 3 MEG Job Safety Superuisor (if applicable): 4 MEG Job Safety Supervisor's Telephone Number: 5 Plant's Emergency Telephone Number: 6 Local Hospital/ Clinic Telephone Number: 7 Emergency Ops Radio Ghanne!: 8 Plant's #1 Gontact Person's Name: 9 Plant's #1 Contact Person's Telephone Number: 10 Plant's #2 Contact Person's Name: 11 Plant's #2 Contact Person's Telephone Number: 12 Designated Assembly Point Location: 13 Evacuation Routes: 14 Severe Weather Shelter Location: 15 Eye Wash and Safety Shower Location: 16 The First Aid Kit is Located: 17 The Fire Extinguisher is Located: Page 38 of 43 I Facility Name: 2 Facility Alamr (Circle) :YES or NO 3 Alarm Tones: CHEMTCAL/ GAS:. SHELTER-IN-PLACE: OTHER: 4 Designated Shelter(s) Description: 5 Designated Assembly Point(s) Description: N * JLoY S EMERGENCY ACTION PLAN FORM AND EVACUATION ASSEMBLY MAP REVIEW: Crew Names and Signatures Printed Nome:Signature:Ddte:Printed Nome:Siqnature:Date: AQS-FRM-1.11 GP043AS-025822-PP-B 1 1 EMERGENCY EVACUATION AND ASSEMBLY MAP Poge 2 ol 2 Page 39 of 43 Page 1 of 1 Daily MEWP Lift lnspection Form All checks must be completed prior to each work shift, before operation of the MEWP lift. This checklist must be used atthe beginning of each shift or following 6 to 8 hours of use. MEWP Lift Model #:Serial Number: Make:Rented or Owned: . Check "Yes" if an item is adequate, operational, and safe.. Check "No" to indicate that a repair or other corrective action is required prior to use.. Check'N/A" to indicate "Not Applicable." Items to be lnspected 1. All MEWP lift components are in working condition (i.e. no loose or missing parts, torn or loose hoses, etc.) - if something can be easily loosened by hand then it is not sufficient. 2. Hydraulic fluid level is sufficient, with the platform fully lowered 3. Hydraulic system pressure (see manufacturer specs) is acceptable. lf the pressure is low, determine cause and repair in accordance with accepted procedures as outlined in service manual. 4. Tires and wheel lug nuts (for tightness) 5. Hoses and cables (i.e. worn areas or chafing) 6. Platform rails and safety gate (no damage present) 7. Pivot pins secure 8. Welds are not cracked and structural members are not bent or broken 9. Warning and instructional labels are legible and secure, and load capacity is clearly marked. 10. Manufacturer's lnstruction Manual is present inside the bucket 1 1. Base controls (switches and push buttons) can be properly operated '12. Platform conditions are safe (i.e. not slippery) 13. Fire extinguisher is present, mounted and fully charged, located inside the bucket '14. Headlights, safety strobe light and back-up alarm are functional 15. Workplace is free of hazards (overhead powerlines, obstructions, level surface, high winds, etc.) *Do not operate if winds are 20 mph, unless otherwise specified by manufacturcr recommendations. Yes n tr tr tr n n tr u ! ! n tr ! n tr trtr No N/A DD trtr trtr trtr D! trtr trtr trtr trtr Dtr trD trtr trtr tr D Operator Name & Signature Location Date Ground Control Name & Signature Location Date Harness lnspections: Printed Name Signature Date Printed Name Signature Date Printed Name GP043AS-025822-PP-B 1 1 Date AQS.FRM-1.16 Page 40 of 43 Signature at): r.ad " i)lc ii" r er,ti.lu-ff),A' | 'Page 1 of 1 Extended Hours Safety Audit Project Number:Date:Time: When a project is expected to extend past a 14-hour work day, this form must be completed to evaluate the condition of the crew, and the safety of the work environment. Permission to proceed into extended work hours must come from a District Manager (DM) or Regional Vice President (RVP). Technical RVPs can authorize moving forward, if they are in the field or if they are managing the project. 1. Hold test crew meetinq Test crew initials: . Temperature and weather . Hoisting. Lighting . PPE (i.e. respirators, etc.) . Working from Heights . Pollutant concentration in ambient air (SOz, HzS, ect.) Notifv DM or RVP The PM must contact either the DM or RVP to discuss the safety issues that may arise due to the extended work period. lf the DM is the acting PM on the job site, they must contact the RVP. During this time, they can come to an agreement on how to proceed. ltemsto discuss include: a a I a Reason for extended hours Reason for delay Production limitations lmpending Weather Contact the client The PM, DM or RVP must discuss with client any identified safety concerns, the client's needs and mutually agree on how to proceed. Discussion should also include the appropriate rest period needed before the next day's work shift can begin. The DM and/or a RVP must be informed on the finaldecision. FinalOutcome: Approver: 2. 3. OOlAS-SAFEry-FM-3 Page 4L of 43 The test leader should look for signs of the following in their crews: . lnitability. Lack of motivation. Headaches. Giddiness . Fatigue. Depression o Reduced alertness, lack of concentration and memory The test leader should assess the environmental and hazardous concerns: GP043AS-025822-PP-81 1 1. 2. Page 1 of 1 Heat Stress Prevention Form This form is to be used when the Expected Heat lndex is above 91' F, and is to be kept with project documentation. Proiect Manaoer (PM):Exoected Hioh Temo: Date(s):Exoected Heat lndex: Review the signs of Heat Exhaustion and Heat Stroke lf Heat lndex is above 91' F:. Provide cold water and/or sports drinks to allfield staff (avoid caffeinated drinks and energy drinks which can increase core temperature). o Bring no less than one gallon of water per employee. lf employee(s) are dehydrated, on blood pressure medication or not acclimated to heat, ensure they are aware of the heightened risk for heat illness. Provide cool head bands/vests/etc.. Have ice available to employees. lmplement work shift rotations and breaks, particularly for employees working in direct sunlight.. Provide as much shade at the jobsite as possible, including tarps, tents or other acceptable temporary structures.. PM should interview each field staff periodically to evaluate for signs of heat illness lf Heat lndex is above 103" F:. Employees must stop for drinks and breaks every hour (about 4 cups/hour). Employees are not permitted to work alone for more than one hour at a time without a break offering shade and drinks. Employees should wear cool bands and vests if working outside more than one hour at a time. PM should interview each field staff every 2 hours to evaluate for signs of heat illness 3. OOlAS-SAFEry-FM-s Page 42 of 43GP043AS-025822-PP-81 1 This is the Last Page of This Document If you have any questions, please contact one of the following individuals by email or phone. Name: Craig Kormylo Title: District Manager Region: USA - Stack - Great Plains - Operations Email: CKormvlo@montrose-env.com Phone: (303) 495-3936 Name: Glen Capra Title: Vice President Region: USA - Stack Email : GCapra@montrose-env.com Phone: (512) 772-6450 LTTAH DEPAHTMENT OF ENVIRONMENTAL OUAJTY FEB 28 20?4 DIVISION OF AIR QUALITY GPO43AS-025822-PP-8 1 1 Page 43 of 43