Page | 1
February 27, 2024
Mr. Kevin Beery
Utah Department of Environmental Quality
Division of Environmental Response and Remediation
195 North 1950 West
Salt Lake City, UT 84114
Re: Work Plan and Budget OFU -03 for Corrective Action Plan – CAP Meeting and Public Notice
Utah State Prison Uintah Maximum Security Generator
14400 South Pony Express Road, Draper, Utah
Facility Identification No. 4002081, Release OFU
Dear Mr. Beery:
WSP USA Environment & Infrastructure, Inc. (WSP) is pleased to present this Work Plan and Budget (WP&B) for the
preparation of a Public Notice related to Corrective Action Plan (CAP) and for conducting a CAP meeting for the Utah State
Prison Uintah Generat or, located at 14400 South Pony Express Road, Draper, Utah (Site), Facility ID No. 4002081. The DERR
assigned the facility Release OFU. This WP&B was prepared in response to request from the Division of Environmental
Response and Remediation (DERR) in emai l communication on February 2, 2024.
The Site is the location of a former underground storage tank (UST) that was closed by removal in October 2022. Findings of
subsurface investigations conducted by WSP at the Site were summarized in a report submitted to the DERR (WSP, 2024)1.
Based on the findings, it was recommended that a CAP for source removal will be prepared for the Site. A CAP meeting was
held via video conferencing on January 30, 2024, with participants from the DERR, the Utah Division of Fleet - State Fuel
Network (SFN), which is the Responsible Party (RP) for the Site, the Division of Facilities and Construction Managem ent
(DFCM), and WSP as the certified UST consultant for the RP.
As required by Utah Administrative Code R311-202, incorporating by reference 40 CFR § 280.67 , a Public Notice must be
prepared and published before the CAP is approved. WSP will prepare the Public Notice in accordance with the DERR
Corrective Action Plan Guide, dated June 14, 2017.
This WP&B is submitted for the efforts associated with the CAP meeting and the preparation and distribution of the Public
Notice. The scope of work under this WP&B includes the following tasks:
1. Preparation of this WP&B
2. Submittal of payment vouchers for the Petroleum Storage Tank Trust Fund
3. CAP Meeting preparation and submittal of CAP Meeting Summary Letter
4. Preparation and distribution of the Public Notice
WSP will perform the work on a time and materials basis. Labor rates are based on the DERR Cost Guidelines for Utah
Underground Storage Tank Sites, as updated January 2023. The total estimated cost for this WP&B is $3,530.00. Estimated
cost details are provided in Table 1. No activities will be performed outside the proposed SOW and budget without prior
approval from the DERR.
1 WSP, 2024. Additional Subsurface Investigation Report , Utah State Prison Uintah Generator, Facility ID 4002081 Release OFU, 14400
South Pony Express Road, Draper, Utah WSP USA Environment & Infrastructure Inc., January 12 , 2024
10876 South River Front Parkway
Suite 250
South Jordan, Utah 84095
+1 801-999-2002
wsp.com
Page | 2
Please contact Ehud Ardon at ehud.ardon@wsp.com or Corey Buchanan at corey.buchanan@wsp.com or if you have
questions or comments regarding this WP&B.
Respectfully submitted,
WSP USA Environment & Infrastructure Inc.
Submitted By: Reviewed By:
Ehud Ardon Corey Buchanan, P.G.
Senior Environmental Scientist Senior Environmental Scientist
Certified UST Consultant # CC -279 Certified UST Consultant # CC -275
Cc: Mr. Brett Gurney, Manager – State Fuel Network
Attachments:
Table 1: Cost Estimate
WP&B Approval Application and Agreement
Activity Cost
Senior Project Manager (P101) - Documents and WP&B Review 2 hours $152.00 hour 304.00$
Project Manager (P103) -SOW & Cost Estimate 6 hours $118.00 hour 708.00$
1,012.00$
Senior Project Manager (P101) - Documents Review 1 hours $152.00 hour 152.00$
PST Claim Specialist (P108)2 hours $78.00 hour 156.00$
308.00$
Senior Project Manager (P101) - Prep, Meeting, Summary Review 5 hours $152.00 hour 760.00$
Project Manager (P103) -Meeting, Meeting summary 5 hours $118.00 hour 590.00$
1,350.00$
Senior Project Manager (P101) - Documents Review 1 hours $152.00 hour 152.00$
Project Manager (P103) -PN Preparation, distribution 6 hours $118.00 hour 708.00$
860.00$
3,530.00$
Table 1: Cost Estimate
Utah State Prison Uintah Maximum Security Generator
14400 South Pony Express Road, Draper, Utah
Facility Id No. 4002081, Release OFU
Task 4 Subtotal:
WP&B OFU-03
Hours or Units Hourly or Unit Rate
Task 4 - Public Notice
WP&B Total
Task 3 - CAP Meeting
Task 3 Subtotal:
Task 1 - WP&B Preparation
Task 1 Subtotal:
Task 2 -PST Vouchers
Task 2 Subtotal:
OFU-03
Utah State Prison Uintah Maximum Security Generator
14400 South Pony Express Road, Draper, Utah
4002081
OFU
Utah State Fuel Network
WSP USA E&I Inc./Corey Buchanan
OFU-03
OFU
Corey Buchanan, Bryan Morse, Ehud Ardon, Rylie Burke, Emerson Codding
Contract requirements with WSP USA Environment & Infrastructure Inc. (Formerly
Wood Environment & Infrastructure Solutions, Inc.)
Brett Gurney Fuel Network Program Manager 2/07/2024
Corey Buchanan,