HomeMy WebLinkAboutDDW-2024-006268
February 27, 2024
Jeffery Jon Hatch
Koosharem Town
P.O. Box 440199
Koosharem, Utah 84744
Subject:Plan Approval, North Sage Estates Subdivision (DS001);
Koosharem Town, System #21010, File #13631
Dear Jeffery Jon Hatch;The Division of Drinking Water (the Division) received the plans and specifications for the proposed North Sage Estates Subdivision from your consultant, Kelly
Chappell with Ensign Engineering, on February 15, 2024. This project has met the conditions for receiving a plan approval for the installation of the proposed pipelines.
Our understanding of the project is that a new 19 lot subdivision is proposed on the northwest side of Koosharem Town. The proposed subdivision will connect into the existing drinking
water system on 650 North at two locations, approximately 50 West and 100 West. This will provide a “looped” pipeline for the proposed subdivision. Approximately 2,300 feet of 8-inch
diameter PVC pipeline, 4 fire hydrants, 1 combination air-vacuum valve, 19 service connections and 3 isolation valves will be installed. A hydraulic analysis for this subdivision was
included in the Town’s water master plan dated December 2023. The hydraulic analysis shows that the proposed pipelines will meet the 40-psi minimum pressure during peak day demand.
We have completed our review of the plans and specifications, stamped and signed by Kelly Chappell, P.E., dated April 20, 2023, and find they basically comply with the applicable portions
of Utah’s Administrative Rules for Public Drinking Water Systems in R309. On this basis, the plans for the North Sage Estates Subdivisionare hereby approved.
This approval pertains to construction only. An Operating Permit must be obtained from the Director before the new 8-inch pipeline may be put in service. A checklist outlining the items
required for operating permit issuance is enclosed for your information.Approvals or permits from the local authority or the county may be necessary before beginning construction of
this project. As the project proceeds, notice of any changes in the approved design, as well as any change affecting the quantity or quality of the delivered water, must be submitted
to the Division. We may also conduct interim and final inspections of this project. Please notify us when actual construction begins so that these inspections can be scheduled.
This approval must be renewed if construction has not begun or if substantial equipment has not been ordered within one year of the date of this letter.
If you have any questions regarding this approval, please contact John Chartier, DEQ Central District Engineer, at (435) 559-1969, or me at (385) 515-1464.
Sincerely,
Michael Newberry, P.E.
Permitting and Engineering Support Manager
JLC/mrn/mdbEnclosures –Operating Permit Checklistcc:Eric Larsen, Central Utah Public Health Department, elarsen@centralutahhealth.org Kelly Chappell, P.E., Ensign Engineering, kchappell@ensignutah.com
Jeffery Jon Hatch, Koosharem Town, jeffh49@hotmail.com Jeffery Jon Hatch, Koosharem Town, jeffh@sorensonsranch.com John Chartier, Department of Environmental Quality, jchartier@utah.gov
jchartier 13631 PA North Sage Estates Subd
Utah Division of Drinking Water ― Checklist for Issuing Operating PermitsWater System Name:System Number: Project Description:File Number:
Items 1 through 8 below must be submitted to the Division and found to be acceptable prior to operating permit issuance (unless a water line project meets the requirements of R309-500-7
and is not required to obtain an Operating Permit).
Distribution lines (not including in-line booster pump stations) requiring Plan Approval may be placed into service prior to submitting all of the following items and receipt of Operating
Permit if the water system has received items 1 and 4 below.☐1.Certification of Rule Conformance by a professional engineer (P.E.) that all conditions of Plan Approval were accomplished,
and if applicable, changes made during construction were in conformance with rules R309-500 through 550☐2.As-built or record drawings incorporating all changes to approved plans and
specifications (unless no changes were made to the previously approved plans during construction)☐3.Confirmation that as-built or record drawings have been received by the water system☐4.Satisfactory
bacteriological samples as evidence of proper disinfection and flushing in accordance with the appropriate ANSI/AWWA standards:
☐ANSI/AWWA C651-14 AWWA Standard for Disinfecting Water MainsTwo consecutive sample sets at least 16 hours apart, none positive (e.g., every 1,200 feet, end-of-line, each branch)☐ANSI/AWWA
C652-11 AWWA Standard for Disinfection of Water-Storage FacilitiesOne or more samples, none positive☐ANSI/AWWA C653-13 AWWA Standard for Disinfection of Water Treatment PlantsTwo consecutive
samples per unit, none positive, no less than 30 minutes apart☐ANSI/AWWA C654-13 AWWA Standard for Disinfection of WellsTwo consecutive samples, none positive, no less than 30 minutes
apart☐5.Water quality data, where appropriate [For example, include raw and finished water data that demonstrate satisfactory performance of the treatment facility; sample should be
taken from a storage tank for residual volatile organic compounds after tank interior re-coating; etc.]☐6.If applicable, all other documentation that may have been required during the
plan review process☐7.If applicable, confirmation that the water system owner has received the O&M manual for the new facility☐8.If applicable, location data of new storage tank, treatment
facility, or source