Loading...
HomeMy WebLinkAboutDERR-2024-004301 195 North 1950 West Mailing Address: P.O. Box 144840 Salt Lake City, UT 84114-4840 Telephone (801) 536-4100 ) 359-8853 (801) 536-4284 www.deq.utah.gov Printed on 100% recycled paper State of Utah SPENCER J. COX Governor DEIDRE HENDERSON Lieutenant Governor Department of Environmental Quality Kimberly D. Shelley Executive Director DIVISION OF ENVIRONMENTAL RESPONSE AND REMEDIATION Brent H. Everett Director ERRC-020-24 January 31, 2024 Alison Kuhlman Monticello Site Manager U.S. Department of Energy Office of Legacy Management 2597 Legacy Way Grand Junction, Colorado 81503 RE: Draft Monticello Site Management Plan, Section 5.0 Annual Update (FY2023-FY2025) Dear Ms. Kuhlman: The Utah Department of Environmental Quality, Division of Environmental Response and Remediation (DERR) has reviewed the Draft Monticello Site Management Plan, Section 5.0 Annual Update (FY2023-FY2025) for the Monticello Mill Tailings Site and Monticello Vicinity Properties site following the response to comments from August 31, 2023. The DERR has no additional comments and concurs with finalizing the document. If you have any questions, please contact me at (385) 395-7943. Sincerely, Kelsey Robinson, Project Manager Division of Environmental Response and Remediation KR/lg Department of Energy Washington, DC 20585 Via email: duggan.jessica@epa.gov Ms. Jessica Duggan, Remedial Project Manager U.S. Environmental Protection Agency, Region 8 1595 Wynkoop Street, EPR-F Denver, CO 80202-1129 Via email: kelseyrobinson@utah.gov Ms. Kelsey Robinson Division of Environmental Response and Remediation State of Utah Department of Environmental Quality PO Box 144840 Salt Lake City, UT 84114-4840 Subject: U.S. Department of Energy Office of Legacy Management Response to U.S. Environmental Protection Agency and Utah Department of Environmental Quality Comments dated August 31, 2023, and titled Re: Draft Monticello Site Management Plan, Section 5.0 Annual Update (FY2023–FY2025) Dear Ms. Duggan and Ms. Robinson: Thank you for the comments from the U.S. Environmental Protection Agency (EPA) and Utah Department of Environmental Quality (UDEQ) sent on August 31, 2023, in response to the U.S. Department of Energy (DOE) Office of Legacy Management’s (LM) submittal, Draft Monticello Site Management Plan, Section 5.0 Annual Update (FY 2023–FY 2025). Please see LM’s response to the EPA and UDEQ comments below. Comments EPA and UDEQ (8/31/2023) Comment 1: Page 4, Section 5.2.1: Update the information about the MMTS I to include the Errata Sheet. Add the I recommendations back into Table 5-2, as it was in the 2022 SMP. LM Response (1/12/24) to EPA and UDEQ Comment 1: DOE appreciates the identification of the deletion of pertinent information. The document has been updated. Page 4, Section 5.2.1, was updated to include information about the Monticello Mill Tailings Site (MMTS) Five-Year Review (I) and the Errata Sheet. The I recommendations were added back into Table 5-2, as it was in the 2022 Site Management Plan (SMP) as recommended. EPA and UDEQ (8/31/2023) Comment 2: Page 4, Section 5.3: Update the reference to the Long-Term Surveillance and Maintenance Plan (i.e., Dec 2022). January 29, 2024 2 LM Response (1/12/24) to EPA and UDEQ Comment 2: Page 4, Section 5.3 was updated to include the citation “(see LTS&M Plan, December 2022, Rev. 2)” as recommended. EPA and UDEQ (8/31/2023) Comment 3: Page 7, Section 5.3.4, last paragraph: In the 2022 SMP, there was language added about preparing a feasibility study, documenting the decision in a ROD amendment or ESD, and incorporating it into the QAPP and LTS&M Plan after a ROD amendment or ESD is issued. Why was this information removed in the 2023 SMP? LM Response (1/12/24) to EPA and UDEQ Comment 3: DOE appreciates the identification of the omission. The information was inadvertently removed due to internal version control. The document has been updated to include the previous language about preparing a feasibility study, documenting the decision in a Record of Decision (ROD) amendment or Explanation of Significant Difference (ESD), and incorporating it into the Quality Assurance Project Plan (QAPP) and Long-Term Surveillance and Maintenance (LTS&M) Plan after a ROD amendment or ESD is issued. EPA and UDEQ (8/31/2023) Comment 4: Page 8, Section 5.4 and Page 9, Table 5-2: Include the activity and milestone dates from the remaining Issues and Recommendations identified in both the Monticello Vicinity Properties (MVP) and Monticello Mill Tailings Site (MMTS) Five-Year Review (FYR). This information was included in the 2022 SMP but removed in the 2023 SMP. Additionally, update the Feasibility Study target date to the new target date. LM Response (1/12/24) to EPA and UDEQ Comment 4: DOE appreciates the identification of the omission. These activities were originally omitted as they had been completed and no longer considered “Targets”. The omitted information was added back into Table 5-2 as it was in the 2022 SMP as recommended. Additional submission dates have been added in parenthesis for completed items. The Feasibility Study target date has been updated to the new target date as recommended. EPA and UDEQ (8/31/2023) Comment 5: Page 9, Table 5-3: I believe the QAPP is almost complete, please add the QAPP to Table 3 – Guiding Documents as DOE-LM indicated in the September 2022 Response to Comments on the 2022 SMP. LM Response (1/12/24) to EPA and UDEQ Comment 5: DOE agrees with EPA’s and UDEQ’s comment. Table 5-3 has been updated with the QAPP completion date of “April 2023.” EPA and UDEQ (8/31/2023) Comment 6: Page 9, Table 5-3: Provide the most current date for the LTS&M Plan in Table 5-3. 3 LM Response (1/12/24) to EPA and UDEQ Comment 6: DOE agrees with EPA’s and UDEQ’s comment. Table 5-3 has been updated with the most current completion date for the LTS&M Plan for the Monticello NPL Sites (see Revision 2, issued December 2022) as recommended. Please contact me at (970) 778-5528 or alison.kuhlman@lm.doe.gov if you have any questions. Please send any correspondence to: U.S. Department of Energy Office of Legacy Management 2597 Legacy Way Grand Junction, CO 81503 Sincerely, Alison Kuhlman Monticello Site Manager Enclosure cc w/enclosure via email: Ryan Kyle, RSI John Homer, RSI Yvonne Deyo, RSI Gary McKinnon, RSI Michael Butherus, RSI Document Determination ELEM/20/138 ALISON KUHLMAN Digitally signed by ALISON KUHLMAN Date: 2024.01.29 10:30:38 -07'00' Project Schedules and Milestones December 2023 Site Management Plan Page 1 5.0 Project Schedules and Milestones (FY 2023–FY 2025) 5.1 Establishing Project Schedules and Milestones As stated in Section 1.1.2, the Site Management Plan (SMP) establishes the overall plan for Remedial Actions (RAs) at the Monticello Mill Tailings Site (MMTS) and milestones against which progress can be measured. The SMP also documents the overall plan for RAs at the Monticello Vicinity Properties site (MVP), which was deleted from the National Priorities List (NPL) on February 28, 2000. The MMTS and MVP are also referred to as the Monticello Projects. The SMP was first prepared in 1995 and was revised annually from 1998 through fiscal year (FY) 2003. Starting in FY 2004, only Section 5.0 of the SMP, “Project Schedules and Milestones,” is updated annually to reflect revised schedules agreed to by the U.S. Department of Energy (DOE), the U.S. Environmental Protection Agency (EPA), and the Utah Department of Environmental Quality (UDEQ). This update of Section 5.0 of the SMP contains project schedules and milestones for FY 2023–FY 2025. The stipulated penalty milestones listed in this section are enforceable milestones unless superseded by revised schedules agreed to by DOE, EPA, and UDEQ or by amendments to the Federal Facility Agreement (FFA) (DOE 1988b). 5.1.1 FFA Requirements Section XXX of the FFA, “Enforceability,” states that “All terms and conditions of this Agreement which relate to interim or final remedial actions, including corresponding timetables, deadlines, or schedules … shall be enforceable. …” The FFA required DOE to submit a work plan establishing how DOE would complete the tasks required by the FFA and specific timetables and a schedule for completing RAs. The FFA Work Plan was completed in May 1989 and established the enforceable timetable for completing primary documents identified in the FFA and for completing RAs. The scope of work, timetable, and schedule for RAs presented in the FFA Work Plan were superseded by the Remedial Design (RD) Work Plan, which was identified as a primary document and was submitted as a final document in January 1992. The RD Work Plan established a revised timetable with specific, stipulated penalty milestones. The stipulated penalty milestones were associated with the submittal of primary design documents that would be generated as part of the RD and notice of award to subcontractors for RA work. The timetable in the RD Work Plan was superseded by the timetables established in the 1995 version of the SMP. DOE, EPA, and UDEQ concurrence on the SMP has been the basis for establishing new enforceable milestones and target dates for all activities extending through the completion of the Monticello Projects. The SMP is a primary document, and, in accordance with the FFA, the corresponding timetables, deadlines, and schedules are enforceable. 5.1.2 Enforceable Milestones and Nonenforceable Targets DOE, with EPA and UDEQ concurrence, has developed a 3-year (fiscal year plus 2 years) rolling milestone approach for establishing a schedule for completing RAs at the Monticello NPL sites. Under this approach, schedule dates are designated as either “milestones” or “target dates.” Milestones and target dates are established in consideration of the Monticello Projects environmental budget allocation. Milestones are enforceable deadlines established for near-term December 2023 Project Schedules and Milestones Page 2 Site Management Plan activities (fiscal year plus 2 years) for which greater fiscal and technical certainty exists. Target dates are nonenforceable deadlines, generally for longer-term activities (greater than fiscal year plus 2 years) and may be converted to milestones annually. Target dates may also be established in the fiscal year plus 2-year time frame and beyond for completing activities associated with a stipulated penalty milestone. Each year, after receipt of the Approved Funding Program that reflects the final congressional appropriation for the current fiscal year, existing milestones are reviewed and adjusted, if necessary. An additional year of milestones is also established, adjusting the previous target dates, if necessary. Enforceable milestones for the Monticello Projects are described in Table 5-1 for those activities in FY 2023–FY 2025 for which stipulated penalties may be assessed against DOE. Each penalty date listed in Table 5-1 is defined as the date EPA and UDEQ must receive the respective document in the form identified in the table. Nonenforceable target dates for the Monticello Projects are described in Table 5-2. As work on the projects progresses, additional documents may be submitted. Additional documents will be identified in FFA quarterly reports as it is determined that they are required. Under DOE’s rolling milestone approach, DOE, EPA, and UDEQ consider a variety of factors during the annual review and establishment of milestones and target dates. These include funding availability; latest information on cost estimates; site priorities identified through consultations among DOE, EPA, UDEQ, and stakeholders; new or emerging technologies; and other relevant factors. DOE provides the regulatory agencies and other stakeholders with an opportunity to assist in developing priorities at the sites. Milestones can be renegotiated if there are insufficient congressional appropriations. Out-year nonenforceable target dates are established using realistic assumptions. DOE, EPA, and UDEQ recognize the uncertainties associated with long-term target dates that lay out DOE’s strategic vision of how it ultimately plans to accomplish projects. Beginning in September 2004, DOE, EPA, and UDEQ concurrence on updates to Section 5.0 of the SMP became the basis for establishing new enforceable milestones and nonenforceable target dates. EPA and UDEQ agree to meet with DOE annually to renegotiate the milestones and target dates established in the SMP. The enforceable milestones described in Table 5-1 for activities in FY 2023–FY 2025 may be modified only as part of this renegotiation or through the existing procedures of the FFA. EPA and UDEQ reserve the right to initiate any action deemed necessary to enforce these milestones. DOE, EPA, and UDEQ agree to abide by the existing procedure for resolving disputes as described in FFA Section XIV, “Resolution of Disputes,” and will make all reasonable efforts to informally resolve any disputes involving insufficient funding before invoking formal dispute procedures. Additionally, Section XII of the FFA (DOE 1988b) establishes procedures to be used by DOE, EPA, and UDEQ for review, comment, and response to comments on documents established as secondary or primary documents. Primary documents include those reports that are major, discrete portions of the Remedial Investigation/Feasibility Study (RI/FS) or RD/RA activities. Secondary documents include those reports that are discrete portions of the primary documents and are typically input or feeder documents. DOE is responsible for the preparation of primary and secondary documents according to established time schedules. DOE must simultaneously submit the documents to EPA and UDEQ. For both primary and secondary documents, EPA and UDEQ must provide comments within 60 calendar days unless otherwise agreed to by all parties. Project Schedules and Milestones December 2023 Site Management Plan Page 3 DOE has 60 calendar days to respond to the comments by simultaneously sending a copy of the responses to EPA and UDEQ unless otherwise agreed to by all parties. For a draft primary document, a draft-final primary document incorporating the comments is required, along with the comment responses. The draft-final primary document will become a final primary document within 30 days unless dispute resolution is invoked. Historically, on Monticello Projects, additional comments have been received by DOE from EPA and UDEQ during the final review period and have been addressed by DOE in the submittal of a final primary document. 5.2 Site Status RAs at the Monticello NPL sites have been implemented in accordance with the Record of Decision (ROD) for the corresponding site and operable unit (OU):  ROD for MVP, all OUs: Monticello Vicinity Properties Project, Declaration for the Record of Decision and Record of Decision Summary, November 1989 (MVP ROD). RAs under this ROD are complete.  ROD for MMTS, OUs I and II: Monticello Mill Tailings Site, Declaration for the Record of Decision and Record of Decision Summary, August 1990 (MMTS ROD). RAs under this ROD are complete.  ROD for MMTS, OU III: Record of Decision for the Monticello Mill Tailings (USDOE) Site Operable Unit III, Surface Water and Ground Water, Monticello, Utah, May 2004. RAs under this ROD are ongoing. The remedy selected in the MMTS OU III ROD was modified in March 2009 by a contingency remedy implemented in the Explanation of Significant Difference for the Monticello Mill Tailings (USDOE) Site Operable Unit III, Surface Water and Ground Water, Monticello, Utah (Explanation of Significant Difference [ESD]). As of January 2015, the contingency includes an expanded pump-and-treat remediation system in a focused area of the aquifer called the Area of Attainment (AOA) (see Section 5.3.4). 5.2.1 CERCLA Five-Year Reviews The RAs at the MMTS and MVP do not allow for unlimited use and unrestricted exposure in all areas because (1) contaminated soil, sediment, and debris removed from the MMTS and MVP remain encapsulated in the onsite DOE repository; (2) contamination remains in soil at the MMTS and MVP where supplemental standards were applied; and (3) contamination remains in MMTS OU III groundwater and surface water. Under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), Section 121(c), these circumstances obligate DOE to conduct Five-Year Reviews (FYRs) of the sites to ensure that the ROD-specified remedies remain protective of human health and the environment. The 2022 FYR for the MVP concluded that the remedy at OU H is protective of human health and the environment in the short-term. In order for the OU H remedy to be protective in the long-term, DOE will need to implement the three recommendations identified in the MVP FYR report. DOE received the letter of concurrence from EPA on the short-term protectiveness determination for the MVP on June 28, 2022; the statutory due date for the MVP FYR report was June 30, 2022. December 2023 Project Schedules and Milestones Page 4 Site Management Plan The statutory due date for the MMTS FYR report was June 20, 2022; however, revisions to the MMTS FYR report are ongoing. The initial protectiveness determination for OU I, OU II, and OU III was short-term protective with the same three recommendations identified for the MMTS as for the MVP. Following subsequent review and discussion, EPA and UDEQ agreed with the short-term protectiveness determination for OU I and OU II, but deferred the protectiveness determination for OU III, stating that additional information was required. On June 17, 2022, EPA issued a letter of independent finding to DOE that identified a “protectiveness deferred” determination for OU III. The letter included three additional recommendations to be implemented by DOE that would provide the information necessary for EPA to make a protectiveness determination for the MMTS in an FYR addendum. DOE committed to issuing the final MMTS FYR report by July 29, 2022, and DOE committed to include as much additional information in the report as could be obtained by that deadline. Recommendations that will take more time to implement will be completed on the schedule agreed to in the final MMTS FYR report. Additional EPA comments on the MMTS FYR report were received on September 9, 2022. Comments included the need for additional discussion regarding a protective uranium benchmark for aquatic receptors in surface water. DOE, EPA, and UDEQ subsequently met on October 19, 2022, and agreed on a path forward for addressing outstanding issues to finalize the MMTS FYR report. The errata sheets were resolved and submitted on May 31, 2023, and included the following change(s): (1) A revised Appendix G that includes DOE responses to EPA comments on the final FYR report that include additional comments received in September 2022 (2) Revisions to Appendix F that address EPA comments received in September 2022 FYR recommendations that are in process or recently finalized include the following:  DOE updated the Uniform Federal Policy Quality Assurance Project Plan, also called the QAPP; Sampling and Analysis Plan for U.S. Department of Energy Office of Legacy Management Sites (LMS/PRO/S04351), also called the SAP; program directive PD-2021-10-MNT, “Discharge measurements in Montezuma Creek”; and the reporting requirements regarding the monitoring well network in the Long-Term Surveillance and Maintenance Plan for the Monticello NPL Sites (LMS/MNT/S00387), also called the LTS&M Plan (December 2022, Rev. 2).  DOE to complete a feasibility study to evaluate remedial alternatives for achieving the water-quality restoration Remedial Action Objective (RAO).  DOE to evaluate risk to aquatic organisms using current State of Utah water quality standards.  DOE to evaluate whether institutional controls (ICs) are required to prevent human consumption of surface water for a domestic drinking water source. 5.3 Long-Term Surveillance and Maintenance In addition to FYRs required under CERCLA, DOE conducts routine inspections and surveillances (weekly, monthly, and quarterly) and annual site inspections as an ongoing evaluation of remedy effectiveness. These activities are directed under the DOE LTS&M program initiated in October 2001. DOE’s Office of Legacy Management (LM) implements Project Schedules and Milestones December 2023 Site Management Plan Page 5 the LTS&M program. The LTS&M Plan for the Monticello NPL sites is designated as a “primary” document in the FFA. LTS&M activities at the Monticello NPL sites consist of periodic surveillance and inspection of supplemental standards properties, monitoring of earthwork in city streets and utility corridors, management of recovered radioactive material in the Temporary Storage Facility (TSF) at the onsite repository, operation and maintenance of the onsite repository, monitoring for compliance with ICs that restrict land and water use, monitoring groundwater and surface water, and pertinent documentation and reporting (see LTS&M Plan, December 2022, Rev. 2). DOE plans to schedule quarterly meetings to track progress of all site activities. 5.3.1 Mill Site Remediation and Restoration Soil contamination removal activities concluded at the former mill site in July 1999. DOE transferred ownership of the former mill site property and several adjacent properties (known as “peripheral properties”) to the City of Monticello in June 2000. Mill site restoration activities were completed in August 2001. The associated wetland areas (Wetlands 1–3) were fully restored by 2004. As a condition of the land transfer agreement, the city maintains the transferred properties for public recreation. DOE continues to monitor the properties for compliance with ICs that restrict land and water use and to ensure that the remedy remains protective. There are currently no violations of land or water use restrictions. The former mill site property, which is part of MMTS OU I, is partially underlain by contaminated groundwater (OU III) and so cannot be deleted from the NPL at this time. 5.3.2 Repository and Pond 4 Operation of the OU III Groundwater Remedy Optimization (GRO) system began in January 2015 with groundwater from the AOA pumped to Pond 4, which resulted in increased water collection in the Pond 4 Leachate Collection and Removal System (LCRS) and the Pond 4 Leachate Detection System (LDS). LCRS and LDS action-level leakage rates, approved by EPA and UDEQ, were formally developed in the Repository and Pond 4 Groundwater Contingency Plan (DOE 1998d in the LTS&M Plan) and are also found in Section D5.0 of the LTS&M Plan. The action-level leakage rate established for the Pond 4 LCRS is 851 gallons per acre per day (gpad) (2000 gallons per day [gpd]) and for the LDS is 20 gpad (47 gpd), which is established over a 7-day period. These action-level leakage rates are based on the area of the floor of Pond 4, which is 2.35 acres. The leakage rate into the LCRS exceeded its action level during the week of May 18, 2015, with notification to LM, EPA, and UDEQ of the exceedance on May 22, 2015. The leakage rate into the LDS also exceeded its action level, and notification to LM, EPA, and UDEQ was also sent on May 22, 2015. The leakage rate frequently exceeded the LCRS action level from the week of May 18, 2015, until the week of September 9, 2019, when the leakage rate fell below the action level. Since the week of September 9, 2019, the LCRS action level has been exceeded three times, during the weeks of January 24, 2022, January 31, 2022, and February 7, 2022. The leakage rate in the Pond 4 LDS system exceeded the action level during the weeks of June 1, 2015 (55 gpd), March 2, 2020 (41 gpd), and June 15, 2020 (13 gpd), which was caused by equipment failure. As documented in the LTS&M Plan, the plan for managing these exceedances is to recirculate the LCRS and LDS leakage back into Pond 4. Currently, the LCRS and LDS monitoring and pumping systems are functioning as designed to recirculate water back into Pond 4. December 2023 Project Schedules and Milestones Page 6 Site Management Plan 5.3.3 Monticello Mill Tailings Site OU IIPeripheral Properties Completion reports, RA reports, and closeout documentation have been completed for the remediation of contaminated soil and sediment on all OU II properties. Twenty-two of the original 34 OU II properties without contaminated surface water or groundwater were deleted from the NPL on October 14, 2003. Twelve of the OU II properties that are underlain by contaminated groundwater have not been deleted from the NPL. DOE performs long-term surveillance of the OU II properties for compliance with ICs that restrict land and groundwater use and to ensure that the implemented remedies remain protective. There have been no violations of land or groundwater use restrictions. MMTS OU II properties that have been remediated for soil and sediment contamination but are underlain by contaminated groundwater are not eligible for deletion from the NPL until water quality RAOs are achieved. 5.3.4 Monticello Mill Tailings Site OU III—Surface Water and Groundwater The remedy for MMTS OU III was selected and documented in the MMTS OU III ROD, signed on June 2, 2004. The MMTS OU III ROD was prepared following the submittal of the Monticello Mill Tailings Site Operable Unit III Remedial Investigation Addendum/Focused Feasibility Study, January 2004, as a basis for OU III remedy selection. That document updated human health and ecological risk assessments and the groundwater model from the 1998 CERCLA RI. MMTS OU III has not been deleted from the NPL because water quality RAOs have not been achieved. The selected remedy consists of monitored natural attenuation, ICs, and biomonitoring to evaluate the potential impacts of selenium concentrations on ecological receptors at specific locations. Biomonitoring was completed in 2012, in concurrence with EPA and UDEQ, and as documented in the MMTS 2012 CERCLA FYR. Analysis of groundwater monitoring data indicates that water quality restoration is not achievable under the performance metrics established in the ROD. This was first reported in the 2006 annual groundwater report and later confirmed in Monticello Mill Tailings Site Operable Unit III Analysis of Uranium Trends in Ground Water, August 2007. DOE, with concurrence from EPA and UDEQ, therefore implemented a contingency remedy for OU III as a requirement of the ROD. The decision to implement a contingency remedy and the scope of the contingency remedy were documented in the March 2009 ESD. The ESD was provided for public review in December 2008 and became effective in March 2009. In accordance with the ESD, DOE committed to implement groundwater pump-and-treat remediation as a component of the contingency remedy until RAOs were met or another remedy was selected. The initial phase of the contingency remedy consisted of continued operation of an existing ex situ treatment system that was constructed in 2005 as a technology demonstration project. The ESD also adopted the State of Utah protection standard for uranium in domestic-use surface water (30 picocuries per liter). To evaluate the effectiveness of the contingency remedy, DOE, in accordance with the March 2009 ESD, prepared the Monticello Mill Tailings Site Operable Unit III Water Quality Compliance Strategy, December 2009. That strategy describes the work elements, schedule, and data-use objectives of the contingency remedy tasks and presents a conceptual, phased approach to attain compliance goals. Results and discussion of the completed activities were documented Project Schedules and Milestones December 2023 Site Management Plan Page 7 in the Monticello Mill Tailings Site Operable Unit III Annual Groundwater Report May 2011 Through April 2012. During July and August 2013, DOE decided to optimize the contingency remedy by implementing a more aggressive groundwater extraction and treatment approach. In FY 2014, DOE prepared an RD/RA Work Plan for the OU III contingency remedy optimization, which was finalized and approved by EPA and UDEQ in June 2014. As explained in the RD/RA Work Plan, the objective of the GRO system is to achieve the remediation goal for uranium in the AOA, which is the portion of the aquifer with the highest uranium. The GRO system consists of eight vertical extraction wells that pump groundwater from the AOA to a control or transfer building from where it is batch pumped to an engineered solar evaporation pond. Sixteen new monitoring wells were installed to monitor restoration progress in the AOA. An additional six new monitoring wells were installed on the north side of Montezuma Creek in June 2017. Construction of the optimization system occurred during spring 2014 through December 2014. Full system startup began in January 2015. The Remedial Action Completion Report for OU III Groundwater Contingency Remedy Optimization System was submitted to the regulatory agencies in May 2016 to document the as-built configuration and operating parameters of the system. Consumptive use of the aquifer water is allowable under an existing state Department of Natural Resources Fixed-Time Water Appropriation (Water Right Number 09-2347). As of April 2018, water quality monitoring to assess the performance of the OU III remedy is conducted in accordance with the SAP and the LTS&M Plan. These documents supersede the MMTS OU III ROD and the Monticello Mill Tailings Site Operable Unit III Post-Record of Decision Monitoring Plan, Draft Final, August 2004. The site-specific QAPP for MMTS OUIII was formatted in the Uniform Federal Policy format and was submitted to EPA and UDEQ in September 2023. Operation of the OU III groundwater contingency remedy will continue until current RAOs are achieved or until it is determined that meeting RAOs under the contingency remedy is not feasible in a reasonable time. Because recent evaluations indicate that the contingency remedy may not achieve RAOs in the anticipated time frame, LM is currently preparing a feasibility study to evaluate remedial alternatives for OU III. A ROD Amendment or ESD will be required to implement the remedy recommended in the feasibility study. Any determination for discontinuing the groundwater contingency remedy because RAOs are not met in a reasonable time frame will require approval from LM, EPA, and UDEQ. Transitioning from the contingency remedy will also require concurrence on performance monitoring metrics for the new remedy. The performance monitoring metrics will be incorporated into the QAPP and LTS&M plan after a ROD Amendment or ESD is issued. 5.3.5 MMTS Long-Term Decommissioning Activities Components of the MMTS infrastructure that require eventual decommissioning are the (1) OU III groundwater remediation systems, including the permeable reactive barrier (PRB); (2) OU III monitoring wells; (3) Pond 4 (repository leachate evaporation pond); and (4) the water diversion flap of the lysimeter embedded in the repository. This section further describes decommissioning of these components. December 2023 Project Schedules and Milestones Page 8 Site Management Plan Plans to decommission the PRB are not yet necessary because it is functioning as a groundwater containment device under the RD/RA Work Plan and the ESD. Upon a decision to remove or replace the PRB, a decommissioning plan will be documented in an RD/RA Work Plan that will be subject to EPA and UDEQ concurrence. The PRB is not currently in consideration for near-term (within 5 years) decommissioning, and an out-year (more than 5 years) date has not been determined. The ex situ groundwater treatment system was taken out of service in December 2014. The decision on whether to remove the ex situ treatment system has not been made, but it is possible that this system could be decommissioned within the near-term (within 5 years). Upon a decision to remove the ex situ groundwater treatment system, a decommissioning plan will be documented in an RD/RA Work Plan that will be subject to EPA and UDEQ concurrence. Groundwater monitoring for OU III will be conducted until water quality restoration has attained acceptable levels established by DOE, EPA, and UDEQ. Monitoring wells will be decommissioned when RAOs are achieved. Monitoring well decommissioning may occur in phases as regions of the aquifer achieve RAOs. Well decommissioning will be conducted in agreement between DOE, EPA, and UDEQ. Well abandonment will conform to the substantive requirements of the Utah well drilling standards, consistent with the OU III ROD. Decommissioning Pond 4 is contingent on the rate of leachate production from the disposal cell and the duration of evaporative treatment of OU III contaminated groundwater from the GRO system. Pond 4 is eligible for decommissioning only if the repository leachate is managed by other means and when evaporative treatment of OU III contaminated groundwater ceases. Pond 4 is not currently in consideration for near-term (within 5 years) decommissioning, and an out-year (more than 5 years) date has not been determined. DOE continues to monitor the drainage lysimeter embedded in the 7.5-acre facet comprising the northeast corner of the repository cover. The repository is capped by a vegetated water balance cover that is underlain by a cell meeting the EPA minimum technology requirements for a Resource Conservation and Recovery Act Subtitle C cell. The lysimeter is monitored and maintained through the LM Applied Studies and Technology program. The two existing lysimeter instrumentation basins were removed and two new upgraded basins were installed in May 2017. 5.3.6 Monticello Vicinity Properties Remediation of the MVP was completed on September 30, 1999. The final rule to delete the MVP from the NPL became effective on February 28, 2000. DOE continues to perform LTS&M activities for certain vicinity properties through annual inspections, enforcement of ICs, and monitoring. The affected MVP are the city streets, utility corridors, and U.S. Highways 191 and 491 in Monticello and private property MS-00176, where contamination was left in place and supplemental standards were applied. As part of planned utility upgrades and unplanned repairs, radioactively contaminated soils that are removed from excavations are transported to the TSF at the Monticello repository, with the exception of material excavated by the Utah Department of Transportation, which has the option to return radioactively contaminated soils to its excavations in Highways 191 and 491 within the city limits. DOE provides the required monitoring and radiological controls during these Project Schedules and Milestones December 2023 Site Management Plan Page 9 activities. Radioactive material stored in the TSF is transported to DOE’s Grand Junction, Colorado, Disposal Site for permanent disposal. As of June 2023, approximately 6 cubic yards of radiological soil is stored in the TSF. 5.4 Milestones and Targets Enforceable milestones applicable to the MVP and MMTS for the current milestone period of FY 2023–FY 2025 are listed in Table 5-1. Table 5-2 lists pending activities and documents with associated target dates. Table 5-3 and Table 5-4 list current guiding documents in effect. DOE can prepare program directives (Table 5-4) to guide field and procedural activities that are beyond the routine work scope for OU III, as defined in the LTS&M Plan. Program directives periodically expire and are reissued as necessary. Two program directives expired in 2021: “Surface-Water Discharge Measurement Protocol” and MNT-2018-02, “Sampling of Permeable Reactive Barrier (PRB) Wells, LM Monticello, Utah, Disposal and Processing Sites.” The former was updated and reissued as PD-2021-10-MNT, “Discharge measurements in Montezuma Creek”; the latter was discontinued because it was determined that PRB wells could be sampled adequately following protocols described in the SAP without the specialized procedures for low-yield, high-turbidity wells that were described in the program directive. Table 5-1. Penalty Milestones in FY 2023–FY 2025 Milestones Stipulated Penalty Datesa FY 2023 revision of Section 5.0 of Site Management Plan (draft)b August 1, 2023 FY 2024 revision of Section 5.0 of Site Management Plan (draft)b August 1, 2024 FY 2025 revision of Section 5.0 of Site Management Plan (draft)b August 1, 2025 2023 Annual Site Inspection Reportc December 31, 2023 2024 Annual Site Inspection Reportc December 31, 2024 2025 Annual Site Inspection Reportc December 30, 2025 Notes: a The date EPA and UDEQ must receive the document for review and comment. b Report progression will be as follows:  The draft report will be reviewed by EPA and UDEQ.  Any comments from the draft will be addressed in a final report. If no comments are received on the draft, DOE will reissue the report as final.  EPA and UDEQ will issue an acceptance letter of the final report. c This report is reviewed by EPA and UDEQ but is not part of the concurrence process. The dates shown are for completion of the final report. December 2023 Project Schedules and Milestones Page 10 Site Management Plan Table 5-2. MMTS and MVP Targets Activity/Document Purpose Target Date/Scope Annual groundwater reporta Evaluate water quality restoration progress October of each year Feasibility Studyb Evaluate remedial alternatives for achieving the water quality restoration RAOs for OU III Summer 2024 Semiannual FFA meeting Review project status, goals, and schedule Spring and fall of each year FFA quarterly reportsa Summarize project scope, status, and schedule 15th of February, May, August, and November of each year QAPPb Update the QAPP per federal requirements Spring of each year Performance Monitoring Metricsb Develops actions for monitoring the OU III aquifer after major changes: GRO termination or PRB removal Winter 2024 (Develop draft and submit for regulator review) Technical document to Terminate Groundwater Remedy Optimization Operationsb Develops the criteria required for turning off the GRO system Winter 2024 (Respond to regulator comments on draft) 2022 Five-Year- Review Activitiesc Operable Unit Activity Milestone Date These activities apply to MMTS OU I, OU II, OU III, and MVP OU H DOE to confirm human health risk evaluation using EPA PRG calculator July 31, 2022 (Submitted on July 29, 2022) DOE to create and send an informational letter to landowners with deed restrictions that clearly explains restrictions on their property December 31, 2022 (Submitted on December 19, 2022) DOE to complete a vulnerability and resilience assessment for Monticello sites by September 2022, provide the assessment to EPA and UDEQ, and schedule a meeting to discuss findings December 31, 2025 These activities apply to MMTS OU III DOE to update the QAPP, SAP, program directive PD-2021-10-MNT, and the LTS&M Plan to be consistent regarding monitoring well network December 31, 2022 (Submitted on April 5, 2023) DOE to complete a feasibility study to evaluate remedial alternatives for achieving the water quality restoration RAO June 30, 2024 DOE to evaluate risk to aquatic organisms using current Utah water quality standards May 31, 2023 (Submitted on December 31, 2023, comment resolution ongoing) DOE to evaluate risk to human health and environment using current Utah water quality standards May 31, 2023 (Submitted on December 31, 2023, comment resolution ongoing) DOE to evaluate whether ICs are required to prevent human consumption of surface water for a domestic drinking water source May 31, 2023 (Submitted on December 31, 2023, comment resolution ongoing) Notes: a This report is reviewed by EPA and UDEQ but is not part of the concurrence process. b Report progression will be as follows:  The draft report will be reviewed by EPA and UDEQ.  Any comments from the draft will be addressed in a final report. If no comments are received on the draft, DOE will reissue the report as final.  EPA and UDEQ will issue an acceptance letter of the final report. c Excerpts from the Sixth Five-Year Review Report for Monticello Radioactively Contaminated Properties Superfund Site, San Juan County, Monticello, Utah (June 2022) and the Sixth Five-Year Review Report for Monticello Mill Tailings (USDOE) Site, San Juan County, Monticello, Utah (July 2022). Abbreviation: PRG = preliminary remediation goal Table 5-3. OU III Guiding Documents Project Schedules and Milestones December 2023 Site Management Plan Page 11 Document Completed RI Addendum/Focused FS RI Addendum/Focused FS January 2004 Surface Water/Groundwater Decision Documents MMTS OU III ROD June 2, 2004 ESDa March 2009 MMTS OU III Water Quality Compliance Strategy December 2009 LTS&M and Monitoring MMTS OU III Analysis of Uranium Trends in Groundwater August 16, 2007 Sampling and Analysis Plan for U.S. Department of Energy Office of Legacy Management Sites Revised to include MMTS, January 2016 LTS&M Plan for the Monticello NPL Sites Revision 2 issued December 2022 Quality Assurance Project Plan, Monticello, Utah, Disposal and Processing Sites April 2023 CERCLA Reviews Sixth FYR Reports for MMTS and MVP July 2022 Note: a Explanation of Significant Difference for the Monticello Mill Tailings (USDOE) Site Operable Unit III, Surface Water and Ground Water, Monticello, Utah. Table 5-4. MMTS OU III Program Directives in Effect PD-2021-10-MNT Discharge measurements in Montezuma Creek