Stantec - Linde PRAP and BSSteel microbial injections
Russell, John <John.RussellIII@stantec.com>Tue, Nov 28, 2023 at
4:14 PM
To: "jkatz@utah.gov" <jkatz@utah.gov>, Leigh Anderson <kanderson@utah.gov>
Hello Joe and Leigh – I hope that both your families had an enjoyable, long
weekend. In light of scheduling and logistical issues, I wanted to share
some info. w/you both:
Originally, we had intended to contract w/Regenesis for injection products at
both the Linde/Praxair and Brown Straus Steel (BSS) VCP sites….utilizing
Sean Bromley/Direct Push Services (DPS) for the actual injections.
However, I was apprised by Sean that DPS cannot schedule either of the
Linde or BSS projects --- until April 2024, at the earliest. VERY frustrated
w/DPS, as they had claimed “No problem for BSS this Fall”….and they
strung me out, unfortly.!!
Regenesis and I have been scrambling to investigate what other drilling firms
have the technical expertise, capabilities, and schedules that will
accommodate getting to both VCP sites, sooner/asap.
We have one drilling firm (Interphase Drilling, mobilizing from CA) identified
(price and schedule comparable to UT firms, if the two projects are
completed/piggy-backed with one mobilization to Utah for the drilling firm
and eqpt., etc.). The soonest Interphase can start is Jan. 2nd at the Linde
VCP site; work at Linde for 3 weeks (Mon-Fri. only) to complete the
Linde/Praxair PlumeStop injections….and then they and Stantec would
mobilize to the BSS site for microbial injections (~ 2-day project, sometime
around Jan. 23rd). In light of weather concerns – the Linde project must
4/24/24, 9:54 PM State of Utah Mail - Stantec - Linde PRAP and BSSteel microbial injections
https://mail.google.com/mail/u/0/?ik=5be3741f93&view=pt&search=all&permmsgid=msg-f:1783851395003563590&simpl=msg-f:1783851395003563590 2/3
start first. In light of upcoming Holidays and subcontracting, it will be Jan. –
before know it, etc.
Interphase can turnkey both projects at reasonable rates, as long as we
“piggy-back” both VCP projects’ field work with one Interphase mobilization
to Utah, etc.
I realize that Leigh is awaiting this info., asap…..whereas Joe (Bill et al
w/VCP) have not yet formally “approved” our Linde PRAP report that
concluded its 30-day PubNotice, last week around ~ Nov. 21st. There will be
a lot of logistics, subbing and delivering Regenesis products to each
respective VCP site….all of which will take weeks to perform.
I/Stantec cannot be contracted by Linde/Praxair, nor subcontract the Subs -
UNTIL Joe et al ‘approve’ our Linde PRAP report. I simply wanted to share
this info. w/you both and your VCP colleagues…..and learn if UDEQ might
have any timeframe for approving the Linde PRAP…?....and ensure that
Leigh is OK w/the proposed BSS injection schedule. Thank you, John
John G. Russell, III CPG
Sr. Hydrogeologist, Environmental Risk Manager
Mobile: 801 703-1927
John.RussellIII@stantec.com
Stantec
4/24/24, 9:54 PM State of Utah Mail - Stantec - Linde PRAP and BSSteel microbial injections
https://mail.google.com/mail/u/0/?ik=5be3741f93&view=pt&search=all&permmsgid=msg-f:1783851395003563590&simpl=msg-f:1783851395003563590 3/3
The content of this email is the confidential property of Stantec and should not be copied, modified, retransmitted, or used for
any purpose except with Stantec's written authorization. If you are not the intended recipient, please delete all copies and notify
us immediately.